Westcoast Energy Notice 182098

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Critical Notice Description: Critical Notices

Notice Effective Date / Time: 08/24/2026 08:00:19 AM

Notice End Date / Time: 11/22/2026 08:00:19 AM

Notice Identifier: 182098

Notice Status Description: Initiate

Notice Type: Capacity Constraint

Posting Date / Time: 08/24/2026 07:54:46 AM

Prior Notice Identifier: None

Required Response Indicator Description: No response required

Response Date / Time: None

Subject: Fort St John Mainline to Station 2 (Station #1 Westbound) Capacity for August 25, 2026

Notice Text:
As per notice #180829 Westcoast will be allowing the following flow on Fort St John Mainline to Station 2

Fort St John Mainline to Station 2 Capacity

August 25, 2026: 1,003,815 GJ

Fort St John Mainline to Station 2 will be authorized above the capacity based on eastbound displacement authorizations.

The constraint is below Firm Contracted Capacity. Shippers can access the Constrained Locations Firm Shipper Share Report for more detailed information (Nominations>Scheduled Quantity>Constrained Locations Firm Shipper Share).

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.

Critical Notice Description: Critical Notices

Notice Effective Date / Time: 08/24/2026 08:00:19 AM

Notice End Date / Time: 11/22/2026 08:00:19 AM

Notice Identifier: 182098

Notice Status Description: Initiate

Notice Type: Capacity Constraint

Posting Date / Time: 08/24/2026 07:54:46 AM

Prior Notice Identifier: None

Required Response Indicator Description: No response required

Response Date / Time: None

Subject: Fort St John Mainline to Station 2 (Station #1 Westbound) Capacity for August 25, 2026

Notice Text:
As per notice #180829 Westcoast will be allowing the following flow on Fort St John Mainline to Station 2

Fort St John Mainline to Station 2 Capacity

August 25, 2026: 1,003,815 GJ

Fort St John Mainline to Station 2 will be authorized above the capacity based on eastbound displacement authorizations.

The constraint is below Firm Contracted Capacity. Shippers can access the Constrained Locations Firm Shipper Share Report for more detailed information (Nominations>Scheduled Quantity>Constrained Locations Firm Shipper Share).

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.