Southern Star Central Gas Pipeline Notice 11085

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name: Southern Star Central Gas Pipeline, Inc
TSP: 007906233
Notice ID: 11085
Critical: Y
Notice Type Desc: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 11083
Notice Eff Date Time: 03/04/2026 02:49 pm
Notice Eff End Date Time: None
Post Date Time: 03/04/2026 02:49 pm
Subject: Planned Service Outage - March 4th, 2026

Notice Text

Southern Star’s 2026 “Planned Service Outage” has been posted to the “Notices” area under the Planned Service Outage category and includes upcoming planned maintenance scheduled for this year. Changes to this schedule are always possible and will be posted to the bulletin board as soon as firm dates are known.






New (1)

  1. The Spring Storage testing at the Elk Storage Field is scheduled to begin March 16th, 2026, and Return to service March 23rd, 2026. The following customers will be affected: 40,000 dth/d EGT Jane (location 10997), and 100,000 dth/d PEPL Princeton Receipt (location 17131).






The PSO Dashboard provides an interactive way to find and filter information related to the PSO items.

PSO Dashboard link: Planned Service Outage

PSO PDF: PSO

 

Scott Warren                      Office: 270.852.4559                      Cell: 270.302.6433

Buster Ashley                     Office: 270.852.4546                      Cell: 270.314.1436

TSP Name: Southern Star Central Gas Pipeline, Inc
TSP: 007906233
Notice ID: 11085
Critical: Y
Notice Type Desc: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 11083
Notice Eff Date Time: 03/04/2026 02:49 pm
Notice Eff End Date Time: None
Post Date Time: 03/04/2026 02:49 pm
Subject: Planned Service Outage - March 4th, 2026

Notice Text

Southern Star’s 2026 “Planned Service Outage” has been posted to the “Notices” area under the Planned Service Outage category and includes upcoming planned maintenance scheduled for this year. Changes to this schedule are always possible and will be posted to the bulletin board as soon as firm dates are known.






New (1)

  1. The Spring Storage testing at the Elk Storage Field is scheduled to begin March 16th, 2026, and Return to service March 23rd, 2026. The following customers will be affected: 40,000 dth/d EGT Jane (location 10997), and 100,000 dth/d PEPL Princeton Receipt (location 17131).






The PSO Dashboard provides an interactive way to find and filter information related to the PSO items.

PSO Dashboard link: Planned Service Outage

PSO PDF: PSO

 

Scott Warren                      Office: 270.852.4559                      Cell: 270.302.6433

Buster Ashley                     Office: 270.852.4546                      Cell: 270.314.1436