Notice Type
Open Season

Effective Start Date Time
04/29/2026 12:07 am

Subject
Update on Upcoming NGTL Expansion Capacity Offerings

Notice Text

 

Update on upcoming NGTL Service Offerings

NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership (collectively NGTL ) is providing an update to the bulletin issued on March 19, 2026.

NGTL s next delivery service offerings are expected to be approximately 825,000 GJ/day in several delivery constrained areas, including Oilsands Delivery Area, Greater Edmonton Area, and Empress and McNeill Borders. This Expansion Capacity will be available at different target service commencement dates:

       125,000 GJ/day in 2030

       500,000 GJ/day in 2031, and

       200,000 GJ/d in 2032

Approximately 60% of the delivery service available in 2030, 2031 and 2032 will be offered using a fixed offering process with a 15-year term, with the balance offered at the Empress and McNeill Borders in accordance with Appendix A. These offerings are expected to close in Q3 2026 with further information expected to be shared in May 2026 through a bulletin.

NGTL also plans to hold a receipt service offering in the area west of Saddle Hills compressor station in Segment 4 GRDL. The total available expansion service for this offering is estimated to be approximately 500 mmcf/day with targeted service commencement in 2031. This offering is expected to close in Q3 2026 with further information expected to be shared in May 2026 through a bulletin.

NGTL is evaluating further delivery and receipt offerings, including FT-D1 and FT-LE service offerings at the Willow Valley Interconnect.

Any potential future Intra-AB and EGAT service offerings will be subject to future annual plans, and the outcomes from the offerings outlined in this bulletin and the 2029 Greater Edmonton Area Service Offering, which closed on April 20, 2026.

NGTL will continue to further develop its plans and discuss them with customers, including in the TTFP forum, and communicate additional information in future bulletins.

 

Summary of the above offerings is provided in the table below:

Description

Available Services

Anticipated Process

Approximate Offering Timing

Estimated Quantity

Target Service Commencement Date

Greater Edmonton Area Delivery

FT-D2/D3 & OS-EXT

Fixed Offering

Closed April 20, 2026

~275 TJ/d

November 2029

Delivery1

FT-D1/D2/D3 & OS-EXT

Common Capacity

(60% Fixed & 40% Appendix A Offerings)

~Q2-Q3 2026

~125+ TJ/d

~500+ TJ/d

~200+ TJ/d

2030

2031

2032

West of Saddle Receipt1

FT-R

Fixed Offering

~Q2-Q3 2026

~500 mmcf/d

2031

Willow Valley Interconnect Delivery1

FT-D1 & FT-LE

Appendix A Offering

Details pending further evaluation

Other Delivery1

FT-D1/D2/D3 & OS-EXT

Common Capacity

(Fixed & Appendix A Offerings)

Subject to previous offering outcomes

Other Receipt1

FT-R

Fixed Offering

Subject to previous offering outcomes

1Offering information is preliminary and may change based on customer interest, outcomes of previous offerings, Annual Plan, etc.

Capital sanctioning for facilities related to these offerings will require a supportive business case which includes but is not limited to agreement on an Investment Framework, which will be discussed at the TTFP in the coming months.

Other Receipt Service Offering

 

NGTL is offering a separate receipt service offering, details for which can be found through a separate bulletin through this LINK , which is not subject to the Investment Framework.

 

 

QUESTIONS

 

Please contact your Marketing Representative  if you have questions.

 



Notice Type
Open Season

Effective Start Date Time
04/29/2026 12:07 am

Subject
Update on Upcoming NGTL Expansion Capacity Offerings

Notice Text

 

Update on upcoming NGTL Service Offerings

NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership (collectively NGTL ) is providing an update to the bulletin issued on March 19, 2026.

NGTL s next delivery service offerings are expected to be approximately 825,000 GJ/day in several delivery constrained areas, including Oilsands Delivery Area, Greater Edmonton Area, and Empress and McNeill Borders. This Expansion Capacity will be available at different target service commencement dates:

       125,000 GJ/day in 2030

       500,000 GJ/day in 2031, and

       200,000 GJ/d in 2032

Approximately 60% of the delivery service available in 2030, 2031 and 2032 will be offered using a fixed offering process with a 15-year term, with the balance offered at the Empress and McNeill Borders in accordance with Appendix A. These offerings are expected to close in Q3 2026 with further information expected to be shared in May 2026 through a bulletin.

NGTL also plans to hold a receipt service offering in the area west of Saddle Hills compressor station in Segment 4 GRDL. The total available expansion service for this offering is estimated to be approximately 500 mmcf/day with targeted service commencement in 2031. This offering is expected to close in Q3 2026 with further information expected to be shared in May 2026 through a bulletin.

NGTL is evaluating further delivery and receipt offerings, including FT-D1 and FT-LE service offerings at the Willow Valley Interconnect.

Any potential future Intra-AB and EGAT service offerings will be subject to future annual plans, and the outcomes from the offerings outlined in this bulletin and the 2029 Greater Edmonton Area Service Offering, which closed on April 20, 2026.

NGTL will continue to further develop its plans and discuss them with customers, including in the TTFP forum, and communicate additional information in future bulletins.

 

Summary of the above offerings is provided in the table below:

Description

Available Services

Anticipated Process

Approximate Offering Timing

Estimated Quantity

Target Service Commencement Date

Greater Edmonton Area Delivery

FT-D2/D3 & OS-EXT

Fixed Offering

Closed April 20, 2026

~275 TJ/d

November 2029

Delivery1

FT-D1/D2/D3 & OS-EXT

Common Capacity

(60% Fixed & 40% Appendix A Offerings)

~Q2-Q3 2026

~125+ TJ/d

~500+ TJ/d

~200+ TJ/d

2030

2031

2032

West of Saddle Receipt1

FT-R

Fixed Offering

~Q2-Q3 2026

~500 mmcf/d

2031

Willow Valley Interconnect Delivery1

FT-D1 & FT-LE

Appendix A Offering

Details pending further evaluation

Other Delivery1

FT-D1/D2/D3 & OS-EXT

Common Capacity

(Fixed & Appendix A Offerings)

Subject to previous offering outcomes

Other Receipt1

FT-R

Fixed Offering

Subject to previous offering outcomes

1Offering information is preliminary and may change based on customer interest, outcomes of previous offerings, Annual Plan, etc.

Capital sanctioning for facilities related to these offerings will require a supportive business case which includes but is not limited to agreement on an Investment Framework, which will be discussed at the TTFP in the coming months.

Other Receipt Service Offering

 

NGTL is offering a separate receipt service offering, details for which can be found through a separate bulletin through this LINK , which is not subject to the Investment Framework.

 

 

QUESTIONS

 

Please contact your Marketing Representative  if you have questions.