NGTL Notice 3374724579
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
02/19/2026 1:31 pm
Subject
NGTL Service (NEDA IT-D)
Notice Text
NGTL Service (NEDA IT-D)
USJR: N/A
WGAT: N/A
EGAT/NEDA: Due to unplanned maintenance at the Gadsby
Compressor Station as well as increased demand with forecasted colder
temperatures, service allowable for segments 6, 10, 11, 13, 14, 15, 16, 23, 24,
and partial 28 (NEDA) will transition from 100% IT-D and 100% FT-D to 0% IT-D
and 100% FT-D effective February 19, 2026 at 13:00 MST until further notice.
Local Area/Location: Service allowable for partial
segment 11 and segment 14 will be included in the NEDA area mentioned above.
|
New Information |
|
Updated Information |
|
Current and upcoming outages |
||||||
|
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
|
20476291 |
Feb 18,
2026 |
TBD |
Gadsby Compressor Station |
Compressor
Station Maintenance |
Unplanned |
NEDA |
|
Upstream
James River Area |
|||||
|
Effective: |
January 20, 2026
at 08:00 MST |
IT
Allowable:
100% |
IT-R |
IT-S (receipt) |
|
|
Expected
End: |
Until further notice |
FT
Allowable: 100% |
FT-R |
FT-P |
|
|
Interconnects: |
Aitken Creek, Big
Eddy, Gordondale, Groundbirch
East, January Creek |
||||
|
Segments: |
|||||
|
West Gate Area |
||||||
|
Effective: |
December
8, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-D |
|||
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C.
Border and Alberta Montana Border |
|||||
|
Segments: |
||||||
|
East Gate Delivery Area |
||||||
|
Effective: |
December 30, 2025
at 08:00 MST |
IT Allowable: 100% |
IT-D |
IT-S
(delivery) |
||
|
Expected
End: |
February 19, 2026 at 13:00
MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Aeco C, Carbon,
Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold
Lake, Warwick SE |
|||||
|
Segments: |
6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT) |
|||||
|
Effective: |
February 19, 2026 at 13:00
MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
||
|
Expected End: |
Until further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Unity, Cold Lake, Warwick SE |
|||||
|
Segments: |
||||||
|
Local Area/Location |
|
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.