NGTL Notice 3374724433
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
12/02/2025 7:22 pm
Subject
NGTL Service (WGAT FT-D)
Notice Text
NGTL Service (WGAT FT-D)
USJR: N/A.
WGAT: Due to unplanned maintenance at the Turner
Valley A3 Compressor Station and high utilization on the WGAT system, service
allowable for Greater West Gate will transition from 100% IT-D and 100% FT-D to
0% IT-D and Partial FT-D effective December 3, 2025 at
08:00 MST until further notice. Authorization levels will be limited to 81 106m3/d.
Return to service is a priority and technicians are on site and committed to
safely returning the compressor station to service as soon as possible. At
the current time, return to service is estimated to be within 1-2 days.
EGAT/NEDA: N/A.
Local Area/Location: N/A.
|
New Information |
|
Updated Information |
|
Current and upcoming outages |
||||||
|
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
|
20364734 |
Nov 25, 2025 |
TBD |
Turner Valley A3 |
Compressor Station Maintenance |
Unplanned |
WGAT |
|
Upstream James River Area |
|||||
|
Effective: |
November
1, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-R |
IT-S (receipt) |
|
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
|
Interconnects: |
Aitken Creek, Big Eddy, Gordondale,
Groundbirch East, January Creek |
||||
|
Segments: |
|||||
|
West Gate Area |
||||||
|
Effective: |
November 28,
2025 at 08:00 MST |
IT Allowable:
100% |
IT-D |
|||
|
Expected End: |
December 3, 2025 at 08:00
MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||
|
Segments: |
||||||
|
Effective: |
December 3, 2025 at 08:00
MST |
IT
Allowable: 0% |
IT-D |
|||
|
Expected
End: |
Until further notice |
FT
Allowable: Partial |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C.
Border and Alberta Montana Border |
|||||
|
Segments: |
||||||
|
East
Gate Delivery Area |
||||||
|
Effective: |
November
15, 2025 at 08:00 MST |
IT
Allowable:
100% |
IT-D |
IT-S (delivery) |
||
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Aeco C, Carbon,
Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil,
Unity, Warwick SE |
|||||
|
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT) |
|||||
|
Local Area/Location |
|
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.
Capacity Constraint
Effective Start Date Time
12/02/2025 7:22 pm
Subject
NGTL Service (WGAT FT-D)
Notice Text
NGTL Service (WGAT FT-D)
USJR: N/A.
WGAT: Due to unplanned maintenance at the Turner
Valley A3 Compressor Station and high utilization on the WGAT system, service
allowable for Greater West Gate will transition from 100% IT-D and 100% FT-D to
0% IT-D and Partial FT-D effective December 3, 2025 at
08:00 MST until further notice. Authorization levels will be limited to 81 106m3/d.
Return to service is a priority and technicians are on site and committed to
safely returning the compressor station to service as soon as possible. At
the current time, return to service is estimated to be within 1-2 days.
EGAT/NEDA: N/A.
Local Area/Location: N/A.
|
New Information |
|
Updated Information |
|
Current and upcoming outages |
||||||
|
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
|
20364734 |
Nov 25, 2025 |
TBD |
Turner Valley A3 |
Compressor Station Maintenance |
Unplanned |
WGAT |
|
Upstream James River Area |
|||||
|
Effective: |
November
1, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-R |
IT-S (receipt) |
|
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
|
Interconnects: |
Aitken Creek, Big Eddy, Gordondale,
Groundbirch East, January Creek |
||||
|
Segments: |
|||||
|
West Gate Area |
||||||
|
Effective: |
November 28,
2025 at 08:00 MST |
IT Allowable:
100% |
IT-D |
|||
|
Expected End: |
December 3, 2025 at 08:00
MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||
|
Segments: |
||||||
|
Effective: |
December 3, 2025 at 08:00
MST |
IT
Allowable: 0% |
IT-D |
|||
|
Expected
End: |
Until further notice |
FT
Allowable: Partial |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C.
Border and Alberta Montana Border |
|||||
|
Segments: |
||||||
|
East
Gate Delivery Area |
||||||
|
Effective: |
November
15, 2025 at 08:00 MST |
IT
Allowable:
100% |
IT-D |
IT-S (delivery) |
||
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Aeco C, Carbon,
Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil,
Unity, Warwick SE |
|||||
|
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT) |
|||||
|
Local Area/Location |
|
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.