NGTL Notice 3374724292

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice Type
Capacity Constraint

Effective Start Date Time
10/20/2025 12:25 pm

Subject
NGTL Service (WGAT FT-D)

Notice Text

NGTL Service (WGAT FT-D)

USJR: N/A

WGAT: Planned maintenance on the Turner Valley A1 and A2 Compressor Station (19724809) is expected to be completed today, October 20, 2025, as scheduled. Effective October 21, 2025 at 08:00 MST, service allowable for Greater WGAT will transition from 0% IT-D and Partial FT-D to 100% IT-D and 100% FT-D until further notice.

EGAT: N/A

Local Area/Location: The NPS 16 Leming Lake Lateral (19731739) pipeline modifications are ongoing and progressing well. Service allowable for segments 14, and partial 11 (Partial OSDA) will remain at 0% IT-D and 64% FT-D until further notice.

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19724809

Oct. 14, 2025

Oct. 20, 2025

Turner Valley A1 & A2

Compressor Station Maintenance

Planned

WGAT

19731739

Oct. 15, 2025

Oct. 24, 2025

NPS 16 Leming Lake Lateral

Pipeline Modification

Planned

Partial OSDA

 

Upstream James River Area

Effective:

August 15, 2025 at 08:00 MST

IT Allowable: 100%

IT-R

IT-S (receipt)

Expected End:

Until further notice

FT Allowable: 100%

FT-R

FT-P

 

Interconnects:

Aitken Creek, Big Eddy, Gordondale, Groundbirch East, January Creek

Segments:

2, 3, 4, 5, 7, partial 8, and partial 9 (Greater USJR)

 

West Gate Area

Effective:

October 14, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

Expected End:

October 21, 2025 at 08:00 MST

FT Allowable: Partial

FT-P

FT-D1

FT-D2

STFT

Interconnects:

Alberta-B.C. Border and Alberta Montana Border

Segments:

22, and partial 21 (Greater WGAT)

Effective:

October 21, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

Interconnects:

Alberta-B.C. Border and Alberta Montana Border

Segments:

22, and partial 21 (Greater WGAT)

 

East Gate Delivery Area

Effective:

September 30, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

IT-S (delivery)

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

Interconnects:

Aeco C, Carbon, Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT)

 

Local Area/Location

Effective:

October 15, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

IT-S (delivery)

 

Expected End:

Until further notice

FT Allowable: 64%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

Cold Lake

 

Segments:

14, and partial 11 (Partial OSDA)

 

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map

NGTL System - Operational Areas Map



Notice Type
Capacity Constraint

Effective Start Date Time
10/20/2025 12:25 pm

Subject
NGTL Service (WGAT FT-D)

Notice Text

NGTL Service (WGAT FT-D)

USJR: N/A

WGAT: Planned maintenance on the Turner Valley A1 and A2 Compressor Station (19724809) is expected to be completed today, October 20, 2025, as scheduled. Effective October 21, 2025 at 08:00 MST, service allowable for Greater WGAT will transition from 0% IT-D and Partial FT-D to 100% IT-D and 100% FT-D until further notice.

EGAT: N/A

Local Area/Location: The NPS 16 Leming Lake Lateral (19731739) pipeline modifications are ongoing and progressing well. Service allowable for segments 14, and partial 11 (Partial OSDA) will remain at 0% IT-D and 64% FT-D until further notice.

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19724809

Oct. 14, 2025

Oct. 20, 2025

Turner Valley A1 & A2

Compressor Station Maintenance

Planned

WGAT

19731739

Oct. 15, 2025

Oct. 24, 2025

NPS 16 Leming Lake Lateral

Pipeline Modification

Planned

Partial OSDA

 

Upstream James River Area

Effective:

August 15, 2025 at 08:00 MST

IT Allowable: 100%

IT-R

IT-S (receipt)

Expected End:

Until further notice

FT Allowable: 100%

FT-R

FT-P

 

Interconnects:

Aitken Creek, Big Eddy, Gordondale, Groundbirch East, January Creek

Segments:

2, 3, 4, 5, 7, partial 8, and partial 9 (Greater USJR)

 

West Gate Area

Effective:

October 14, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

Expected End:

October 21, 2025 at 08:00 MST

FT Allowable: Partial

FT-P

FT-D1

FT-D2

STFT

Interconnects:

Alberta-B.C. Border and Alberta Montana Border

Segments:

22, and partial 21 (Greater WGAT)

Effective:

October 21, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

Interconnects:

Alberta-B.C. Border and Alberta Montana Border

Segments:

22, and partial 21 (Greater WGAT)

 

East Gate Delivery Area

Effective:

September 30, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

IT-S (delivery)

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

Interconnects:

Aeco C, Carbon, Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT)

 

Local Area/Location

Effective:

October 15, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

IT-S (delivery)

 

Expected End:

Until further notice

FT Allowable: 64%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

Cold Lake

 

Segments:

14, and partial 11 (Partial OSDA)

 

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map

NGTL System - Operational Areas Map