Notice Type
Capacity Constraint

Effective Start Date Time
07/17/2025 7:44 pm

Subject
NGTL Service (EGAT IT-D)

Notice Text

NGTL Service (EGAT IT-D)

USJR: N/A

 

WGAT: N/A

 

EGAT: Due to unforeseen delays related to environmental factors outside our control, maintenance on the NPS 42 Foothills Pipeline Zone 6 and 9 (19700928) is unable to proceed as planned starting tomorrow. The outage will be removed from the DOP in today's publication and we expect to be able to provide an update early next week. Service allowable for segments 15, 16, 17, 18, 19, 20, 23, partial 21 and partial 28 (lower EGAT) will therefore remain at 100% IT-D and 100% FT-D until further notice instead of transitioning to Partial IT-D and 100% FT-D on July 18, 2025 at 08:00 as previously communicated.

Local Area/Location: N/A

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

 Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19700928

TBD

TBD

NPS 42 Foothills Pipeline Zone 6 and 9

Pipeline Maintenance

Planned

EGAT

 

Upstream James River Area

Effective:

June 27, 2025 at 08:00 MST

IT Allowable: 100%

IT-R

  IT-S (receipt)

Expected End:

Until Further Notice

FT Allowable: 100%

FT-R

FT-P

 

Interconnects:

  Aitken Creek, Big Eddy, Gordondale, Groundbirch East, January Creek

Segments:

  2, 3, 4, 5, 7, partial 8, and partial 9 (Greater USJR)

 

West Gate Area

Effective:

June 02, 2025 at 08:00 MST

IT Allowable: 100%

  IT-D

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

Interconnects:

  Alberta-B.C. Border and Alberta Montana Border

Segments:

 22 and partial 21 (Greater WGAT)

 

East Gate Delivery Area

Effective:

June 27, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

  IT-S (delivery)

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Aeco C, Carbon, Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT)

 

Local Area/Location

N/A

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map

NGTL System - Operational Areas Map



Notice Type
Capacity Constraint

Effective Start Date Time
07/17/2025 7:44 pm

Subject
NGTL Service (EGAT IT-D)

Notice Text

NGTL Service (EGAT IT-D)

USJR: N/A

 

WGAT: N/A

 

EGAT: Due to unforeseen delays related to environmental factors outside our control, maintenance on the NPS 42 Foothills Pipeline Zone 6 and 9 (19700928) is unable to proceed as planned starting tomorrow. The outage will be removed from the DOP in today's publication and we expect to be able to provide an update early next week. Service allowable for segments 15, 16, 17, 18, 19, 20, 23, partial 21 and partial 28 (lower EGAT) will therefore remain at 100% IT-D and 100% FT-D until further notice instead of transitioning to Partial IT-D and 100% FT-D on July 18, 2025 at 08:00 as previously communicated.

Local Area/Location: N/A

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

 Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19700928

TBD

TBD

NPS 42 Foothills Pipeline Zone 6 and 9

Pipeline Maintenance

Planned

EGAT

 

Upstream James River Area

Effective:

June 27, 2025 at 08:00 MST

IT Allowable: 100%

IT-R

  IT-S (receipt)

Expected End:

Until Further Notice

FT Allowable: 100%

FT-R

FT-P

 

Interconnects:

  Aitken Creek, Big Eddy, Gordondale, Groundbirch East, January Creek

Segments:

  2, 3, 4, 5, 7, partial 8, and partial 9 (Greater USJR)

 

West Gate Area

Effective:

June 02, 2025 at 08:00 MST

IT Allowable: 100%

  IT-D

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

Interconnects:

  Alberta-B.C. Border and Alberta Montana Border

Segments:

 22 and partial 21 (Greater WGAT)

 

East Gate Delivery Area

Effective:

June 27, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

  IT-S (delivery)

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Aeco C, Carbon, Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT)

 

Local Area/Location

N/A

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map

NGTL System - Operational Areas Map