Natural Gas Pipeline Notice 47282

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE Notice Eff Date/Time:  10/08/2026 8:45:51AM Notice End Date/Time:  12/31/2026 9:00:00am Post Date/Time:  10/8/2026 8:45:51 AM Notice ID: 47282 Reqrd Rsp:  1 Rsp Date/Time:  10/8/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  SEGMENT 8 (CS 167) HOT TAP INSTALLATION
Notice Text:

COMPRESSOR STATION 167 – HOT TAP INSTALLATION

 

As posted on Natural's Outage Impact Report (X26-1186280 and X26-1186271) Natural will be performing multiple hot tap installation work on the Permian #1 line near Compressor Station 167 (CS 167) located in Lea County, New Mexico (Segment 9 of Natural's Permian Zone).  This work requires Natural to reduce its operating capacity, thus limiting Natural's throughput capacity northbound through Compressor Station 167 (CS 167).

 

The transport scheduling constraint will be at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 into Segment 8 will be impacted for the duration of this restriction.  For scheduling purposes, the Permian Pool (LOC 25077) is located south of the constraint.  Additionally, firm transports associated with Permian storage withdrawals will be impacted.

 

As such, effective for gas day, Wednesday, December 9, 2026 only, Natural will schedule Primary Firm and Secondary in-path Firm transports to 76% of contract MDQ northbound through CS 167 from Segment 9 into Segment 8.  AOR/ITS and Secondary out-of-path Firm transports will not be available. 

 

The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization. 

 

Continue to monitor Natural's interactive website for any updates to the end date and/or scheduling percentage during this restriction.

 

Please contact your Account Director or Scheduling Representative if you have any questions.

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE Notice Eff Date/Time:  10/08/2026 8:45:51AM Notice End Date/Time:  12/31/2026 9:00:00am Post Date/Time:  10/8/2026 8:45:51 AM Notice ID: 47282 Reqrd Rsp:  1 Rsp Date/Time:  10/8/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  SEGMENT 8 (CS 167) HOT TAP INSTALLATION
Notice Text:

COMPRESSOR STATION 167 – HOT TAP INSTALLATION

 

As posted on Natural's Outage Impact Report (X26-1186280 and X26-1186271) Natural will be performing multiple hot tap installation work on the Permian #1 line near Compressor Station 167 (CS 167) located in Lea County, New Mexico (Segment 9 of Natural's Permian Zone).  This work requires Natural to reduce its operating capacity, thus limiting Natural's throughput capacity northbound through Compressor Station 167 (CS 167).

 

The transport scheduling constraint will be at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 into Segment 8 will be impacted for the duration of this restriction.  For scheduling purposes, the Permian Pool (LOC 25077) is located south of the constraint.  Additionally, firm transports associated with Permian storage withdrawals will be impacted.

 

As such, effective for gas day, Wednesday, December 9, 2026 only, Natural will schedule Primary Firm and Secondary in-path Firm transports to 76% of contract MDQ northbound through CS 167 from Segment 9 into Segment 8.  AOR/ITS and Secondary out-of-path Firm transports will not be available. 

 

The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization. 

 

Continue to monitor Natural's interactive website for any updates to the end date and/or scheduling percentage during this restriction.

 

Please contact your Account Director or Scheduling Representative if you have any questions.