SEGMENT 13 – STATION MAINTENANCE – COMPRESSOR STATION 108
As posted on Natural's Outage Impact Report (X26-921503), Natural will be performing station maintenance at Compressor Station 108 (CS 108) located in Warren County, Iowa (Segment 13 of Natural's Amarillo Mainline Receipt Zone). Natural is required to limit the operating capacity northbound through CS 108 during this restriction.
As such, effective for gas day Tuesday, September 8, 2026 continuing through Friday, September 18, 2026, Natural will only schedule Primary Firm and Secondary in-path Firm transports northbound through Compressor Station 106 (CS 106) located in Gage County, Nebraska (Segment 12 of Natural's Amarillo Mainline Receipt Zone). AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this restriction. Trailblazer Gage (LOC 902900) is south of the constraint. Amarillo Mainline pool (LOC 10566) is north of the constraint.
SEGMENT PRIMARY ONLY NORTHBOUND:
SEGMENT 12 - COMPRESSOR STATION 106 (CS 106)
Continue to monitor Natural's interactive website for any updates. Please contact your Account Director or Scheduling Representative if you have any questions.
SEGMENT 13 – STATION MAINTENANCE – COMPRESSOR STATION 108
As posted on Natural's Outage Impact Report (X26-921503), Natural will be performing station maintenance at Compressor Station 108 (CS 108) located in Warren County, Iowa (Segment 13 of Natural's Amarillo Mainline Receipt Zone). Natural is required to limit the operating capacity northbound through CS 108 during this restriction.
As such, effective for gas day Tuesday, September 8, 2026 continuing through Friday, September 18, 2026, Natural will only schedule Primary Firm and Secondary in-path Firm transports northbound through Compressor Station 106 (CS 106) located in Gage County, Nebraska (Segment 12 of Natural's Amarillo Mainline Receipt Zone). AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this restriction. Trailblazer Gage (LOC 902900) is south of the constraint. Amarillo Mainline pool (LOC 10566) is north of the constraint.
SEGMENT PRIMARY ONLY NORTHBOUND:
SEGMENT 12 - COMPRESSOR STATION 106 (CS 106)