National Fuel Gas Supply Notice 1241722

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name: National Fuel Gas Supply Corporation - Critical Notice

TSP: 007912959

                                                                                                                        Post Date: 3/25/2026
                                                                                                                        Post Time: 08:41:00AM CCT
Notice Type: Curtailment, Planned Service Outage, Scheduling Alert
                                                                                                                        Reqrd Rsp: 5
Critical: Y
Notice ID: 1241722
Notice Status: 2
Notice Eff Date/Time: 4/6/2026 09:00:00AM CCT
Notice End Date/Time: 4/11/2026 09:00:00AM CCT
Superseded System Notice ID: 1237162

Subject: East Aurora Compressor Station Outage: April 2026 - Rev 1
Notice Text
East Aurora Compressor Station Outage: April 2026 - Rev 1

East Aurora compressor station will be out of service from April 6th through April 10th. Impact to shippers is only expected GD 6 through GD 9.

During this time period (GD6-GD9), the capacity target for Niagara Spur Deliveries will be set to 250,000 dth. Accordingly, the total primary deliveries to the
following points downstream of East Aurora station will be restricted to this limit:

TGP - East Aurora (420077)
TGP - Clarence (420497)
TGP - Pekin (420326)
TGP - Lewiston (420092)
TCPL - Niagara (421079)

Updates will be provided as available.

********** Prior Notice Below **********

East Aurora Compressor Station Outage - April 2026

East Aurora compressor station will be out of service from April 6th through April 9th.

During this time period, the combined primary deliveries to the following points downstream of East Aurora station will be limited to 250,000 dth:

TGP - East Aurora (420077)
TGP - Clarence (420497)
TGP - Pekin (420326)
TGP - Lewiston (420092)
TCPL - Niagara (421079)

Updates will be provided as available.

TSP Name: National Fuel Gas Supply Corporation - Critical Notice

TSP: 007912959

Post Date: 3/25/2026
Post Time: 08:41:00AM CCT
Notice Type: Curtailment, Planned Service Outage, Scheduling Alert
Reqrd Rsp: 5
Critical: Y
Notice ID: 1241722
Notice Status: 2
Notice Eff Date/Time: 4/6/2026 09:00:00AM CCT
Notice End Date/Time: 4/11/2026 09:00:00AM CCT
Superseded System Notice ID: 1237162

Subject: East Aurora Compressor Station Outage: April 2026 - Rev 1
Notice Text
East Aurora Compressor Station Outage: April 2026 - Rev 1

East Aurora compressor station will be out of service from April 6th through April 10th. Impact to shippers is only expected GD 6 through GD 9.

During this time period (GD6-GD9), the capacity target for Niagara Spur Deliveries will be set to 250,000 dth. Accordingly, the total primary deliveries to the
following points downstream of East Aurora station will be restricted to this limit:

TGP - East Aurora (420077)
TGP - Clarence (420497)
TGP - Pekin (420326)
TGP - Lewiston (420092)
TCPL - Niagara (421079)

Updates will be provided as available.

********** Prior Notice Below **********

East Aurora Compressor Station Outage - April 2026

East Aurora compressor station will be out of service from April 6th through April 9th.

During this time period, the combined primary deliveries to the following points downstream of East Aurora station will be limited to 250,000 dth:

TGP - East Aurora (420077)
TGP - Clarence (420497)
TGP - Pekin (420326)
TGP - Lewiston (420092)
TCPL - Niagara (421079)

Updates will be provided as available.