TSP Name: National Fuel Gas Supply Corporation - Critical Notice

TSP: 007912959

                                                                                                                        Post Date: 6/11/2025
                                                                                                                        Post Time: 09:01:00AM CCT
Notice Type: Maintenance, Curtailment
                                                                                                                        Reqrd Rsp:
Critical: Y
Notice ID: 1170975
Notice Status: 2
Notice Eff Date/Time: 6/19/2025 06:00:00AM CCT
Notice End Date/Time: 6/23/2025 04:00:00PM CCT
Superseded System Notice ID: 1167967

Subject: Line KPA Replacement ***REVISION 3***
Notice Text
Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/16/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/19/2025 through 6/23/2025
8/11/2025 through 8/15/2025

Updates will be provided as they become available.


PSP1128821    Vineyard Oil & Gas Co.


***REVISION 002 SUPERSEDED NOTICE TEXT BELOW***



Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/16/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/16/2025 through 6/20/2025
8/11/2025 through 8/15/2025

Updates will be provided as they become available.


PSP1128821    Vineyard Oil & Gas Co.


***REVISION 001 SUPERSEDED NOTICE TEXT BELOW***


Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/2/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/2/2025 through 6/6/2025
8/11/2025 through 8/15/2025

Updates will be provided as they become available.


***ORIGINAL SUPERSEDED NOTICE TEXT BELOW***

Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
that the pipeline from Lewis Run to Maloney Farms to be shut in from 6/2/2025 through 8/15/2025.

Updates will be provided as they become available.

Volumes from the below meter station will be shut in during the work:


PSP1128821    Vineyard Oil & Gas Co.

TSP Name: National Fuel Gas Supply Corporation - Critical Notice

TSP: 007912959

Post Date: 6/11/2025
Post Time: 09:01:00AM CCT
Notice Type: Maintenance, Curtailment
Reqrd Rsp:
Critical: Y
Notice ID: 1170975
Notice Status: 2
Notice Eff Date/Time: 6/19/2025 06:00:00AM CCT
Notice End Date/Time: 6/23/2025 04:00:00PM CCT
Superseded System Notice ID: 1167967

Subject: Line KPA Replacement ***REVISION 3***
Notice Text
Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/16/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/19/2025 through 6/23/2025
8/11/2025 through 8/15/2025

Updates will be provided as they become available.


PSP1128821    Vineyard Oil & Gas Co.


***REVISION 002 SUPERSEDED NOTICE TEXT BELOW***



Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/16/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/16/2025 through 6/20/2025
8/11/2025 through 8/15/2025

Updates will be provided as they become available.


PSP1128821    Vineyard Oil & Gas Co.


***REVISION 001 SUPERSEDED NOTICE TEXT BELOW***


Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/2/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/2/2025 through 6/6/2025
8/11/2025 through 8/15/2025

Updates will be provided as they become available.


***ORIGINAL SUPERSEDED NOTICE TEXT BELOW***

Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
that the pipeline from Lewis Run to Maloney Farms to be shut in from 6/2/2025 through 8/15/2025.

Updates will be provided as they become available.

Volumes from the below meter station will be shut in during the work:


PSP1128821    Vineyard Oil & Gas Co.