National Fuel Gas Supply Notice 1161309
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: National Fuel Gas Supply Corporation - Critical Notice
TSP: 007912959
Post Date: 5/2/2025
Post Time: 09:20:00AM CCT
Notice Type: Maintenance, Curtailment
Reqrd Rsp:
Critical: Y
Notice ID: 1161309
Notice Status: 2
Notice Eff Date/Time: 6/2/2025 07:00:00AM CCT
Notice End Date/Time: 8/15/2025 03:00:00PM CCT
Superseded System Notice ID: 1158159
Subject: Line KPA Replacement ***REVISION 1***
Notice Text
Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/2/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/2/2025 through 6/6/2025
8/11/2025 through 8/15/2025
Updates will be provided as they become available.
***ORIGINAL SUPERSEDED NOTICE TEXT BELOW***
Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
that the pipeline from Lewis Run to Maloney Farms to be shut in from 6/2/2025 through 8/15/2025.
Updates will be provided as they become available.
Volumes from the below meter station will be shut in during the work:
PSP1128821 Vineyard Oil & Gas Co.
TSP Name: National Fuel Gas Supply Corporation - Critical Notice
TSP: 007912959
Post Date: 5/2/2025
Post Time: 09:20:00AM CCT
Notice Type: Maintenance, Curtailment
Reqrd Rsp:
Critical: Y
Notice ID: 1161309
Notice Status: 2
Notice Eff Date/Time: 6/2/2025 07:00:00AM CCT
Notice End Date/Time: 8/15/2025 03:00:00PM CCT
Superseded System Notice ID: 1158159
Subject: Line KPA Replacement ***REVISION 1***
Notice Text
Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
a portion of the pipeline from Lewis Run to Maloney Farms to be isolated from 6/2/2025 through 8/15/2025.
The remaining portion of the pipeline will be placed back in service.
Volumes from the below meter station will be shut in for the following time periods:
6/2/2025 through 6/6/2025
8/11/2025 through 8/15/2025
Updates will be provided as they become available.
***ORIGINAL SUPERSEDED NOTICE TEXT BELOW***
Supply will be replacing a section of Line KPA near Lewis Run. The replacement will require
that the pipeline from Lewis Run to Maloney Farms to be shut in from 6/2/2025 through 8/15/2025.
Updates will be provided as they become available.
Volumes from the below meter station will be shut in during the work:
PSP1128821 Vineyard Oil & Gas Co.