Kinetica Pipeline Expansion
August 2025
www.kineticallc.com
Project Schedule
Milestone
Date(s)
Project Kickoff
Aug. 2025
Open Season
Sept. – Oct.
2025
File FERC 7(c)
Nov. 2025
Receive FERC notice to
begin construction
Sept. 2026
Project in service
Q1 2027
About Kinetica
Kinetica Partners, LLC (Kinetica) is a midstream energy company operating over
1,600 miles of pipeline and multiple liquid handling facilities across the Gulf of
America region. Many of these assets were formerly owned and operated by
Tennessee Gas Pipeline (TGP), giving Kinetica a strong foundation of proven
infrastructure. Since its founding in 2010, Kinetica has focused on providing safe,
reliable, and responsive natural gas transportation and liquid handling services for
producers in the region, with an emphasis on operational simplicity, system
stability, and long-term customer relationships.
Project Overview
Kinetica is advancing a pipeline expansion to increase natural gas transportation
capacity from West Louisiana (Egan area) to the constrained Southeast Louisiana
(Gulf South/500L) market. The project utilizes existing offshore infrastructure,
originally designed for gathering Gulf of America gas, and requires only
compression additions at Pecan Island and Cocodrie to support the eastbound
flow. By leveraging underutilized assets, this approach minimizes the
permitting and construction timeline
The system currently transports up to 125,000 dekatherms per day and the
planned expansion will increase capacity to 500,000 dekatherms per day with
room for future growth. Of this expanded capacity 250,000 per day can flow into
Gulf South at Lirette and 350,000 per day can flow into TGP at Cocodrie.
Current Receipt Point:
•
CGT – Egan
Current Delivery Points:
•
Discovery
•
Lirette (LIG)
•
Targa Venice (TETCO/CGT/Gulf South)
Expansion delivery opportunities:
•
Up to 350,000 dth per day to eastern delivery points at TGP Cocodrie or
MLV 526 (TETCO/CGT ) with additional compression
•
Up to 250,000 dth per day at Lirette (Gulf South)
As part of the expansion, Kinetica is launching an open season to solicit interest
from market participants. Respondents will have the opportunity to propose:
•
New receipt points
•
New delivery points
•
Transportation rates and volume commitments
The project is currently in development, with a target in-service date of Q1-
2027 for Phase II. It offers a timely solution to bridge rising supply from the
West with constrained markets and growing demand in the East.
Project Details
Compression Facilities
Cocodrie, Terrebonne Parish, LA
Pecan Island, Vermillion Parish, LA
MLV526, Plaquemine Parish, LA
Estimated In Service Date
18 months
Term
To be Determined
Maximum Daily Quantity (“MDQ”)
125,000 dekatherms/day (Phase I)
500,000 dekatherms/day (Phase II)
Demand Rate
To be Determined
Delivery Point Options
•
Gulf South at Lirette (up to 250,000 dth/day)
•
TGP at Cocodrie (up to 350,000 dth/day)
•
TETCO at MLV 526 (up to 300,000 dth/day)
•
Open to additional proposals
Fuel Retention
Estimated 1.5%
Regulatory Status
Project to proceed subject to FERC approval
Existing LIG Lirette (80,000 dth/day) &
proposed Gulf South Lirette (250,000
dth/day) Delivery Points
Proposed Cocodrie Station
(TGP – 350,000 dth/day) &
Compressor installation
Pecan Island Compressor Station
Venice Plant
Delivery Point
CGT- Egan
Receipt Point
Discovery (290,000 dth/day)
Delivery Point
Document Outline
Kinetica Pipeline Expansion
Project Details
Estimated In Service Date
18 months
About Kinetica
Term
To be Determined
Kinetica Partners, LLC (Kinetica) is a midstream energy company operating over
Demand Rate
1,600 miles of pipeline and multiple liquid handling facilities across the Gulf of
To be Determined
America region. Many of these assets were formerly owned and operated by
Tennessee Gas Pipeline (TGP), giving Kinetica a strong foundation of proven
Maximum Daily Quantity (“MDQ”)
infrastructure. Since its founding in 2010, Kinetica has focused on providing safe,
125,000 dekatherms/day (Phase I)
reliable, and responsive natural gas transportation and liquid handling services for
500,000 dekatherms/day (Phase II)
producers in the region, with an emphasis on operational simplicity, system
Delivery Point Options
stability, and long-term customer relationships.
•
Gulf South at Lirette (up to 250,000 dth/day)
•
TGP at Cocodrie (up to 350,000 dth/day)
Project Overview
•
TETCO at MLV 526 (up to 300,000 dth/day)
•
Open to additional proposals
Kinetica is advancing a pipeline expansion to increase natural gas transportation
Compression Facilities
capacity from West Louisiana (Egan area) to the constrained Southeast Louisiana
Cocodrie, Terrebonne Parish, LA
(Gulf South/500L) market. The project utilizes existing offshore infrastructure,
Pecan Island, Vermillion Parish, LA
originally designed for gathering Gulf of America gas, and requires only
MLV526, Plaquemine Parish, LA
compression additions at Pecan Island and Cocodrie to support the eastbound
flow. By leveraging underutilized assets, this approach minimizes the
Fuel Retention
permitting and construction timeline
Estimated 1.5%
The system currently transports up to 125,000 dekatherms per day and the
Regulatory Status
planned expansion will increase capacity to 500,000 dekatherms per day with
Project to proceed subject to FERC approval
room for future growth. Of this expanded capacity 250,000 per day can flow into
Gulf South at Lirette and 350,000 per day can flow into TGP at Cocodrie.
Current Receipt Point:
•
CGT – Egan
Project Schedule
Current Delivery Points:
•
Discovery
Milestone
Date(s)
•
Lirette (LIG)
•
Targa Venice (TETCO/CGT/Gulf South)
Expansion delivery opportunities:
Project Kickoff
Aug. 2025
•
Up to 350,000 dth per day to eastern delivery points at TGP Cocodrie or
MLV 526 (TETCO/CGT ) with additional compression
•
Up to 250,000 dth per day at Lirette (Gulf South)
Open Season
Sept. – Oct.
2025
As part of the expansion, Kinetica is launching an open season to solicit interest
from market participants. Respondents will have the opportunity to propose:
File FERC 7(c)
Nov. 2025
•
New receipt points
•
New delivery points
Receive FERC notice to
•
Transportation rates and volume commitments
begin construction
Sept. 2026
The project is currently in development, with a target in-service date of Q1-
2027 for Phase II. It offers a timely solution to bridge rising supply from the
Project in service
Q1 2027
West with constrained markets and growing demand in the East.
www.kineticallc.com
August 2025
Discovery (290,000 dth/day)
Delivery Point
Existing LIG Lirette (80,000 dth/day) &
proposed Gulf South Lirette (250,000
dth/day) Delivery Points
Proposed Cocodrie Station
(TGP – 350,000 dth/day) &
Compressor installation
CGT- Egan
Receipt Point
Venice Plant
Delivery Point
Pecan Island Compressor Station