Capacity Constraint

 

Effective Timely Cycle, Gas Day July 4, 2026, nominations are sealed from all increases through the following locations:

-          MLV-14

-          Brookfield Interconnect with Algonquin Gas Transmission.

 

In addition, the following capacity has been reduced:

-          MLV-14 – Interruptible and Extended Receipt/Extended Delivery nominations forward-haul through mainline valve 14 are reduced by 100% and Secondary Out of Path nominations forward-haul through mainline valve 14 are reduced by 25%.

-     Brookfield Interconnect – Park and Interruptible receipt nominations at the Brookfield Interconnect are reduced by 100%, and Secondary receipt nominations at the Brookfield Interconnect are reduced by 94%.

 

If you have any further questions, please contact the Iroquois Scheduling or Gas Control Group. 

End date 07/05/2026 09:00 AM CCT

 

Capacity Constraint

 

Effective Timely Cycle, Gas Day July 4, 2026, nominations are sealed from all increases through the following locations:

-          MLV-14

-          Brookfield Interconnect with Algonquin Gas Transmission.

 

In addition, the following capacity has been reduced:

-          MLV-14 – Interruptible and Extended Receipt/Extended Delivery nominations forward-haul through mainline valve 14 are reduced by 100% and Secondary Out of Path nominations forward-haul through mainline valve 14 are reduced by 25%.

-     Brookfield Interconnect – Park and Interruptible receipt nominations at the Brookfield Interconnect are reduced by 100%, and Secondary receipt nominations at the Brookfield Interconnect are reduced by 94%.

 

If you have any further questions, please contact the Iroquois Scheduling or Gas Control Group. 

End date 07/05/2026 09:00 AM CCT