Capacity Constraint

Effective Timely Cycle, Gas Day February 20, 2026, nominations are sealed from all increases through the following locations:

-       MLV-14

In addition, the following capacities have been reduced:

-       MLV-14 – IT and ER/ED nominations forward-haul through mainline valve 14 are reduced by 100% and Secondary Out of Path (SOP) nominations forward-haul through mainline valve 14 are reduced by 90%.

End date 2/21/2026 09:00 AM CCT

Capacity Constraint

Effective Timely Cycle, Gas Day February 20, 2026, nominations are sealed from all increases through the following locations:

-       MLV-14

In addition, the following capacities have been reduced:

-       MLV-14 – IT and ER/ED nominations forward-haul through mainline valve 14 are reduced by 100% and Secondary Out of Path (SOP) nominations forward-haul through mainline valve 14 are reduced by 90%.