Iroquois Gas Transmission System Notice 7113

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Capacity Constraint

Effective Timely Cycle, Gas Day February 4, 2026, nominations are sealed from all increases through the following locations:

-       MLV-14

-       MLV-31

-       Brookfield Interconnect with Algonquin Gas Transmission

In addition, the following capacities have been reduced:

-       MLV-14 – IT, ER/ED, and Secondary Out of Path (SOP) nominations forward-haul through mainline valve 14 are reduced by 100%.

-       MLV-31 – IT and ER/ED nominations forward-haul through mainline valve 31 are reduced by 100%.

-       Brookfield Interconnect – Park and Interruptible receipt nominations are reduced by 100% and Secondary receipt nominations are reduced by 90%.

End date 2/5/2026 09:00 AM CCT

Capacity Constraint

Effective Timely Cycle, Gas Day February 4, 2026, nominations are sealed from all increases through the following locations:

-       MLV-14

-       MLV-31

-       Brookfield Interconnect with Algonquin Gas Transmission

In addition, the following capacities have been reduced:

-       MLV-14 – IT, ER/ED, and Secondary Out of Path (SOP) nominations forward-haul through mainline valve 14 are reduced by 100%.

-       MLV-31 – IT and ER/ED nominations forward-haul through mainline valve 31 are reduced by 100%.

-       Brookfield Interconnect – Park and Interruptible receipt nominations are reduced by 100% and Secondary receipt nominations are reduced by 90%.

End date 2/5/2026 09:00 AM CCT