Iroquois Gas Transmission System Notice 7053
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Gas Day December 23, 2025, nominations are sealed from all increases through the following locations:
-
MLV-14
(Effective Timely Cycle)
-
MLV-1
(Effective Intraday 1 Cycle)
In addition, the following capacity reductions apply:
-
MLV-14 – Interruptible,
ER/ED and Secondary Out of Path (SOP) nominations forward-haul through mainline
valve 14 are reduced by 100%.
-
MLV-14 –
Interruptible nominations forward-haul through mainline valve 1 are subject to
reductions.
If you have any further questions, please contact the Iroquois Scheduling or Gas Control Group.
End date 12/24/2025 09:00 AM CCT
Capacity Constraint
Effective Gas Day December 23, 2025, nominations are sealed from all increases through the following locations:
-
MLV-14
(Effective Timely Cycle)
-
MLV-1
(Effective Intraday 1 Cycle)
In addition, the following capacity reductions apply:
-
MLV-14 – Interruptible,
ER/ED and Secondary Out of Path (SOP) nominations forward-haul through mainline
valve 14 are reduced by 100%.
-
MLV-14 –
Interruptible nominations forward-haul through mainline valve 1 are subject to
reductions.
If you have any further questions, please contact the Iroquois Scheduling or Gas Control Group.
End date 12/24/2025 09:00 AM CCT