Operational Flow Order (OFO)

 

Pursuant to General Terms and Conditions, Section 38, of Iroquois’ FERC Gas Tariff, Effective Thursday, November 20th Gas Day an Iroquois Operational Flow Order (OFO) is in effect for all points:

 

•           South of MLV-12

 

Due to expected high volumes and forecasted weather conditions Iroquois is requiring all point operators in the affected area to adhere to their scheduled volumes to maintain pipeline pressures necessary for operations. No due unscheduled shipper gas (OBA) will be available. Operators are required to operate within tariff guidelines.  Flow Control will be implemented and activated if necessary.

 

Iroquois reminds all operators and agents of directly connected power plants of the related parameters as set forth by FERC Order 698. Iroquois requires all directly connected power plant operators to submit burn profiles and nominations prior to gas flow. Flexibility on burn rates is limited and power plant operators are urged to burn ratably based on scheduled volumes.  

 

If you have any further questions, please contact your account representative or Gas Control.

 

End date November 22nd, 2025, 9:00 am (CCT).

 





Iroquois Gas Transmission System respects your online time and privacy. You have received this email because you elected to subscribe. To unsubscribe, login to Iroquois’ Customer Activities application via the link at www.iroquois.com, go to the Contract & Administration menu item and choose the Notice Preference sub menu item. Uncheck the notice types you no longer wish to receive and press the Save button.

 

Operational Flow Order (OFO)

 

Pursuant to General Terms and Conditions, Section 38, of Iroquois’ FERC Gas Tariff, Effective Thursday, November 20th Gas Day an Iroquois Operational Flow Order (OFO) is in effect for all points:

 

•           South of MLV-12

 

Due to expected high volumes and forecasted weather conditions Iroquois is requiring all point operators in the affected area to adhere to their scheduled volumes to maintain pipeline pressures necessary for operations. No due unscheduled shipper gas (OBA) will be available. Operators are required to operate within tariff guidelines.  Flow Control will be implemented and activated if necessary.

 

Iroquois reminds all operators and agents of directly connected power plants of the related parameters as set forth by FERC Order 698. Iroquois requires all directly connected power plant operators to submit burn profiles and nominations prior to gas flow. Flexibility on burn rates is limited and power plant operators are urged to burn ratably based on scheduled volumes.  

 

If you have any further questions, please contact your account representative or Gas Control.

 

End date November 22nd, 2025, 9:00 am (CCT).

 





Iroquois Gas Transmission System respects your online time and privacy. You have received this email because you elected to subscribe. To unsubscribe, login to Iroquois’ Customer Activities application via the link at www.iroquois.com, go to the Contract & Administration menu item and choose the Notice Preference sub menu item. Uncheck the notice types you no longer wish to receive and press the Save button.