TSP Name : Gulf South Pipeline Company, LLC

Category : Critical

Notice Type Desc : Maintenance

Notice Stat Desc : Initiate

Notice ID : 5038097

Prior Notice :

Reqrd Rsp Desc : No response required

Subject : Index 301-8-L-A Pipeline Maintenance

TSP : 078444247

Post Date/Time : 05/07/2026 01:24:00 PM

Notice Effective Date/Time : 09/15/2026 09:00:00 AM

Notice End Date/Time : 10/16/2026 09:00:00 AM

Response Date/Time :

Critical : Y

Notice Text :

Gulf South will be performing maintenance on Index 301-8-L-A Pipeline.

The following points will be shut-in for the duration of the maintenance:

- Loc 7362 (Mobile-Saraland)
- Loc 20777 (Jacinto Port (Bayou Sara Junction))
- 1 Spire Farmtap

This maintenance has the potential to impact all services, including Primary Firm Service.

Demand charge credits will not be issued during the maintenance period unless Primary Firm
Service is scheduled down during the Timely Nomination Cycle. Any demand charge credits will be
calculated pursuant to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas
Tariff.

The following groups are subject to impact:

Saraland Deliveries Scheduling Group

No impact anticipated to net zero nominations between receipt and delivery points north of
Hatter's Pond Junction located on Index 301-8-20.

East Whistler Deliveries Scheduling Group

Capacity could be impacted by as much as 150,000 Dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Service.

No impact anticipated to net zero nominations between receipt and delivery points located east of
Hurricane Junction.

Demand charge credits will not be issued during the maintenance period unless Primary Firm
Service is scheduled down during the Timely Nomination Cycle. Any demand charge credits will be
calculated pursuant to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas
Tariff.

If you have any questions, please contact your customer service representative.

Notice

Page 1 of 1

05/07/2026 1:24:32 PM

Notice
TSP Name : Gulf South Pipeline Company, LLC
TSP : 078444247
Category : Critical
Post Date/Time : 05/07/2026 01:24:00 PM
Notice Type Desc : Maintenance
Notice Effective Date/Time : 09/15/2026 09:00:00 AM
Notice Stat Desc : Initiate
Notice End Date/Time : 10/16/2026 09:00:00 AM
Notice ID : 5038097
Response Date/Time :
Prior Notice :
Critical : Y
Reqrd Rsp Desc : No response required
Subject : Index 301-8-L-A Pipeline Maintenance
Notice Text :
Gulf South will be performing maintenance on Index 301-8-L-A Pipeline.
The following points will be shut-in for the duration of the maintenance:
- Loc 7362 (Mobile-Saraland)
- Loc 20777 (Jacinto Port (Bayou Sara Junction))
- 1 Spire Farmtap
This maintenance has the potential to impact all services, including Primary Firm Service.
Demand charge credits will not be issued during the maintenance period unless Primary Firm
Service is scheduled down during the Timely Nomination Cycle. Any demand charge credits will be
calculated pursuant to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas
Tariff.
The following groups are subject to impact:
Saraland Deliveries Scheduling Group
No impact anticipated to net zero nominations between receipt and delivery points north of
Hatter's Pond Junction located on Index 301-8-20.
East Whistler Deliveries Scheduling Group
Capacity could be impacted by as much as 150,000 Dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Service.
No impact anticipated to net zero nominations between receipt and delivery points located east of
Hurricane Junction.
Demand charge credits will not be issued during the maintenance period unless Primary Firm
Service is scheduled down during the Timely Nomination Cycle. Any demand charge credits will be
calculated pursuant to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas
Tariff.
If you have any questions, please contact your customer service representative.
05/07/2026 1:24:32 PM
Page 1 of 1