Gulf South Pipeline Notice 5037743

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name : Gulf South Pipeline Company, LLC

Category : Critical

Notice Type Desc : Maintenance

Notice Stat Desc : Initiate

Notice ID : 5037743

Prior Notice :

Reqrd Rsp Desc : No response required

Subject : Index 59-22 Meter Maintenance

TSP : 078444247

Post Date/Time : 02/25/2026 04:29:00 PM

Notice Effective Date/Time : 04/06/2026 09:00:00 AM

Notice End Date/Time : 04/11/2026 09:00:00 AM

Response Date/Time :

Critical : Y

Notice Text :

Gulf South will be performing maintenance at Index 59-22.

The following point will be shut-in for the duration of the maintenance:

- Loc 8544 (Lufkin Creosote Plant)

Based on current operating conditions, no capacity impact is expected at this time.

This maintenance has the potential to impact all services, including Primary Firm Service.

Demand charge credits will not be issued during the maintenance period unless Primary Firm
Service is scheduled down during the Timely Nomination Cycle. Any demand charge credits will be
calculated pursuant to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas
Tariff.

If you have any questions, please contact your customer service representative.

Notice

Page 1 of 1

02/25/2026 4:29:53 PM

Notice
TSP Name : Gulf South Pipeline Company, LLC
TSP : 078444247
Category : Critical
Post Date/Time : 02/25/2026 04:29:00 PM
Notice Type Desc : Maintenance
Notice Effective Date/Time : 04/06/2026 09:00:00 AM
Notice Stat Desc : Initiate
Notice End Date/Time : 04/11/2026 09:00:00 AM
Notice ID : 5037743
Response Date/Time :
Prior Notice :
Critical : Y
Reqrd Rsp Desc : No response required
Subject : Index 59-22 Meter Maintenance
Notice Text :
Gulf South will be performing maintenance at Index 59-22.
The following point will be shut-in for the duration of the maintenance:
- Loc 8544 (Lufkin Creosote Plant)
Based on current operating conditions, no capacity impact is expected at this time.
This maintenance has the potential to impact all services, including Primary Firm Service.
Demand charge credits will not be issued during the maintenance period unless Primary Firm
Service is scheduled down during the Timely Nomination Cycle. Any demand charge credits will be
calculated pursuant to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas
Tariff.
If you have any questions, please contact your customer service representative.
02/25/2026 4:29:53 PM
Page 1 of 1