Gulf South Pipeline Notice 5036853

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name : Gulf South Pipeline Company, LLC

Category : Critical

Notice Type Desc : Maintenance

Notice Stat Desc : Supersede

Notice ID : 5036853

Prior Notice : 5036553

Reqrd Rsp Desc : No response required

Subject : UPDATE: Gulf South Capacity Impacted by Third Party

Maintenance

TSP : 078444247

Post Date/Time : 07/28/2025 01:44:00 PM

Notice Effective Date/Time : 07/28/2025 01:46:00 PM

Notice End Date/Time : 08/28/2025 09:00:00 AM

Response Date/Time :

Critical : Y

Notice Text :

UPDATED DATE RANGE:
-------------------------------------------------------------------------------------------------
----------------------------------------
Gulf South Pipeline Company, LLC wishes to inform its customers that operational capacity through
the following scheduling groups may be impacted in association with posted maintenance on the
Texas Gas Transmission pipeline:

Marksville Delivery Revised
Arnaudville Del
Olla Deliveries
Bayou Sale to Napoleonville
Area 2, 3, 11, 23 Deliveries

Gas Day 5/27 - 6/16:

Capacity could be impacted by as much as 200,000 dth/d for the duration of the maintenance.

Gas Day 6/17 - 8/27:

Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.

Reference Texas Gas Transmission, LLC Critical Notice ID: 5036456 and Notice ID: 5036352 for
further information.

-------------------------------------------------------------------------------------------------
If you have any questions, please contact your customer service representative.

Notice

Page 1 of 1

07/28/2025 1:44:52 PM

Notice
TSP Name : Gulf South Pipeline Company, LLC
TSP : 078444247
Category : Critical
Post Date/Time : 07/28/2025 01:44:00 PM
Notice Type Desc : Maintenance
Notice Effective Date/Time : 07/28/2025 01:46:00 PM
Notice Stat Desc : Supersede
Notice End Date/Time : 08/28/2025 09:00:00 AM
Notice ID : 5036853
Response Date/Time :
Prior Notice : 5036553
Critical : Y
Reqrd Rsp Desc : No response required
Subject : UPDATE: Gulf South Capacity Impacted by Third Party
Maintenance
Notice Text :
UPDATED DATE RANGE:
-------------------------------------------------------------------------------------------------
----------------------------------------
Gulf South Pipeline Company, LLC wishes to inform its customers that operational capacity through
the following scheduling groups may be impacted in association with posted maintenance on the
Texas Gas Transmission pipeline:
Marksville Delivery Revised
Arnaudville Del
Olla Deliveries
Bayou Sale to Napoleonville
Area 2, 3, 11, 23 Deliveries
Gas Day 5/27 - 6/16:
Capacity could be impacted by as much as 200,000 dth/d for the duration of the maintenance.
Gas Day 6/17 - 8/27:
Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.
Reference Texas Gas Transmission, LLC Critical Notice ID: 5036456 and Notice ID: 5036352 for
further information.
-------------------------------------------------------------------------------------------------
If you have any questions, please contact your customer service representative.
07/28/2025 1:44:52 PM
Page 1 of 1