Gulf South Pipeline Notice 5036235
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Notice
Critical / Planned Service Outage
TSP:
Post Date/Time:
78444247
03/24/2025 11:12:58AM
Category:
TSP Name: Gulf South Pipeline Company, LLC
Notice Effective Date/Time: 03/24/2025 11:15:00AM
Notice Type Desc: Maintenance
Wilson Compressor Station Maintenance
Subject:
Supersede
5036235
Notice Stat Desc:
Prior Notice:
Notice ID:
Response Date/Time:
Reqrd Rsp Desc:
Notice End Date/Time: 03/27/2025 09:00:00 AM
Critical: Y
5036021
No response required
Update: Revised capacity limitations
-------------------------------------------------------------------------
Wilson Compressor South Scheduling Group:
-------------------------------------------------------------------------
Gas Day 3/24:
Capacity could be impacted by as much as 1,220,000 dth/d for EVE and ID1 before dropping to a 150,000
dth/d impact for the remainder of the gas day. Capacity will be impacted by as much as 550,000 dth/d for
the gas day. Primary Firm may be impacted.
The following meter will need to be shut-in during the duration of the 9-hr maintenance on Gas Day 3/24:
- Loc 23376 (Coastal Bend (Enterprise))
Gas Day 3/25 & 3/26:
Capacity could be impacted by as much as 150,000 dth/d for the duration of the maintenance. Primary Firm
may be impacted.
Notice Text:
03/24/2025 11:14:28AM
Page 1 of 1
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical / Planned Service Outage
Post Date/Time: 03/24/2025 11:12:58AM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 03/24/2025 11:15:00AM
Notice Stat Desc: Supersede
Notice End Date/Time: 03/27/2025 09:00:00 AM
Notice ID: 5036235
Response Date/Time:
Prior Notice: 5036021
Critical: Y
Reqrd Rsp Desc: No response required
Subject: Wilson Compressor Station Maintenance
Notice Text:
Update: Revised capacity limitations
-------------------------------------------------------------------------
Wilson Compressor South Scheduling Group:
-------------------------------------------------------------------------
Gas Day 3/24:
Capacity could be impacted by as much as 1,220,000 dth/d for EVE and ID1 before dropping to a 150,000
dth/d impact for the remainder of the gas day. Capacity will be impacted by as much as 550,000 dth/d for
the gas day. Primary Firm may be impacted.
The following meter will need to be shut-in during the duration of the 9-hr maintenance on Gas Day 3/24:
- Loc 23376 (Coastal Bend (Enterprise))
Gas Day 3/25 & 3/26:
Capacity could be impacted by as much as 150,000 dth/d for the duration of the maintenance. Primary Firm
may be impacted.
03/24/2025 11:14:28AM
Page 1 of 1