Equitrans Notice 137278

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

03-04-2026 00:00:00

Page 1 of 1

System Wide Notice Detail

TSP Name:

EQUITRANS, L.P.

TSP:

189569585

Post Date/Time:

Wed Mar 04 00:00:00 GMT 2026

Subject:

Cygrymus Compressor Station Maintenance (Transmission) 03-09-26 Update

Notice Type:

CRITICAL

Notice ID:

137278

Prior Notice:

137221

137221

Notice Status Desc:

Supersede

Critical Desc:

Critical Notice

Notice Eff Date:

03-04-2026

Notice Eff Time:

00:00:00

Notice End Date:

06-30-2026

Notice End Time:

00:00:00

Required Response Indicator Description:

NO RESPONSE REQUIRED

Notice Text:

Equitrans L.P. is providing notice of a start time change for the upcoming maintenance at its Cygrymus Compressor Station. The start time has been
updated from 7:00 AM ET to 3:00 AM ET.

Equitrans L.P. will perform maintenance at its Cygrymus Compressor Stations in its Mainline Operational Area 3 beginning at 3:00 AM ET on
March 09, 2026.

In conjunction with this maintenance, customers may experience higher than normal pressures on the following pipelines in Mainline Operational
Area 2, Mainline Operational Area 3 and Mainline Operational Area 4:H-111, H-115, H-148, H-149, H-302, H-306, GSF-912, GSF-993, H-557,
GSF-604, H-527, H-515, H-518, H-511, H-509, and H-508.

Equitrans L.P. will notify impacted parties of anticipated point specific volume reductions.

Estimated duration of the maintenance is 10 days. Customers should monitor Equitrans’ Informational Postings Website for updates to this notice
and applicable posted Operationally Available Capacity.

*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.


System Wide Notice Detail
TSP Name:
EQUITRANS, L.P.
TSP:
189569585
Post Date/Time:
Wed Mar 04 00:00:00 GMT 2026
Subject:
Cygrymus Compressor Station Maintenance (Transmission) 03-09-26 Update
Notice Type:
CRITICAL
Notice ID:
137278
Prior Notice:
137221
137221
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
03-04-2026
Notice Eff Time:
00:00:00
Notice End Date:
06-30-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
NO RESPONSE REQUIRED
Equitrans L.P. is providing notice of a start time change for the upcoming maintenance at its Cygrymus Compressor Station. The start time has been
updated from 7:00 AM ET to 3:00 AM ET.
Equitrans L.P. will perform maintenance at its Cygrymus Compressor Stations in its Mainline Operational Area 3 beginning at 3:00 AM ET on
March 09, 2026.
In conjunction with this maintenance, customers may experience higher than normal pressures on the following pipelines in Mainline Operational
Notice Text:
Area 2, Mainline Operational Area 3 and Mainline Operational Area 4:H-111, H-115, H-148, H-149, H-302, H-306, GSF-912, GSF-993, H-557,
GSF-604, H-527, H-515, H-518, H-511, H-509, and H-508.
Equitrans L.P. will notify impacted parties of anticipated point specific volume reductions.
Estimated duration of the maintenance is 10 days. Customers should monitor Equitrans’ Informational Postings Website for updates to this notice
and applicable posted Operationally Available Capacity.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
03-04-2026 00:00:00
Page 1 of 1