Type | Posted | Effective | End | Identifier | Status | Subject | Response |
---|---|---|---|---|---|---|---|
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 06/12/25 | 06/12/25 | 06/14/25 | 123981 | EGTS Pratt IC and Sandrock IC Maintenance 06-11-25 Complete | ||
CAPACITY CONSTRAINT | 06/05/25 | 06/05/25 | 06/07/25 | 123781 | Plasma Compressor Station Maintenance 06-05-25 Complete | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 06/05/25 | 06/05/25 | 06/06/25 | 123780 | EGTS Pratt IC and Sandrock IC Maintenance 06-02-25 Complete | ||
OPERATIONAL FLOW ORDER | 06/05/25 | 06/05/25 | 08/31/25 | 123779 | OFO Effective 6/7/2025 at 10AM ET | ||
PLANNED SERVICE OUTAGE | 06/04/25 | 06/04/25 | 06/09/25 | 123739 | Corona Compressor Station Maintenance 06-03-25 Complete | ||
OPERATIONAL FLOW ORDER | 06/03/25 | 06/03/25 | 06/08/25 | 123699 | OFO Lifted Effective Immediately | ||
PLANNED SERVICE OUTAGE | 06/03/25 | 06/03/25 | 07/03/25 | 123679 | GSF-604 Pipeline Maintenance 06-24-25 | ||
CAPACITY CONSTRAINT | 06/03/25 | 06/03/25 | 06/28/25 | 123659 | Plasma and Corona Compressor Station Maintenance 06-24-25 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 06/02/25 | 06/02/25 | 06/03/25 | 123619 | TP-7676 Pipeline Maintenance (East) 05-12-25 Complete | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 05/28/25 | 05/28/25 | 06/03/25 | 123459 | TP-7676 Pipeline Maintenance (East) 05-12-25 Update 2 | ||
PLANNED SERVICE OUTAGE | 05/23/25 | 05/23/25 | 06/05/25 | 123319 | Corona Compressor Station Maintenance 06-03-25 | ||
CURTAILMENT | 05/23/25 | 05/23/25 | 05/24/25 | 123299 | Mainline Transmission High Pressure Advisory 05-22-25 Complete | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 05/21/25 | 05/21/25 | 05/22/25 | 123199 | H-515 Pipeline Maintenance 06-03-25 - Postponed | ||
CAPACITY CONSTRAINT | 05/19/25 | 05/19/25 | 08/31/25 | 123139 | H-508 and H-509 Pipelines Operationally Available Capacity Limit Update 5-21-2025 | ||
CURTAILMENT | 05/19/25 | 05/19/25 | 05/23/25 | 123119 | Mainline Transmission High Pressure Advisory 05-22-25 | ||
OPERATIONAL FLOW ORDER | 05/12/25 | 05/13/25 | 05/20/25 | 122939 | OFO Effective 5/13/2025 at 10AM ET | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 05/08/25 | 06/03/25 | 06/06/25 | 122840 | H-515 Pipeline Maintenance 06-03-25 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 05/08/25 | 06/09/25 | 06/29/25 | 122819 | TP-7676 Pipeline Maintenance (West) 06-09-25 | ||
CAPACITY CONSTRAINT | 05/06/25 | 06/05/25 | 06/07/25 | 122759 | Plasma Compressor Station Maintenance 06-05-25 | ||
OPERATIONAL FLOW ORDER | 05/05/25 | 05/05/25 | 05/06/25 | 122699 | OFO Lifted Effective 5/6/2025 at 10AM ET | ||
OPERATIONAL FLOW ORDER | 05/02/25 | 05/02/25 | 08/31/25 | 122619 | OFO Effective 5/3/2025 at 10AM ET | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/30/25 | 06/11/25 | 06/12/25 | 122520 | EGTS Pratt IC and Sandrock IC Maintenance 06-11-25 Update | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/30/25 | 06/02/25 | 06/05/25 | 122519 | EGTS Pratt IC and Sandrock IC Maintenance 06-02-25 Update | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/30/25 | 06/11/25 | 06/12/25 | 122500 | EGTS Pratt IC Maintenance 06-11-25 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/30/25 | 06/02/25 | 06/05/25 | 122499 | EGTS Pratt IC Maintenance 06-02-25 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/30/25 | 05/05/25 | 05/07/25 | 122479 | TP-7676 Pipeline Maintenance (East) 05-12-25 Update | ||
PLANNED SERVICE OUTAGE | 04/29/25 | 04/29/25 | 04/30/25 | 122439 | Corona Compressor Station Maintenance 04-29-25 Complete | ||
PLANNED SERVICE OUTAGE | 04/29/25 | 04/29/25 | 04/30/25 | 122419 | Corona Compressor Station Maintenance 04-29-25 Completed | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/29/25 | 04/29/25 | 04/30/25 | 122399 | Heracles IC Maintenance 04-29-25 Complete | ||
OPERATIONAL FLOW ORDER | 04/29/25 | 04/29/25 | 07/31/25 | 122379 | OFO Lifted Effective 4/29/2025 at 10AM ET | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/23/25 | 04/23/25 | 05/04/25 | 122241 | TP-7676 Pipeline Pigging 04-23-25 Complete | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/23/25 | 04/23/25 | 05/04/25 | 122239 | TP-7676 Pipeline Pigging 04-23-25 Complete | ||
OPERATIONAL FLOW ORDER | 04/23/25 | 04/23/25 | 05/04/25 | 122219 | OFO Effective 4/24/2025 at 10AM ET | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/14/25 | 04/14/25 | 04/15/25 | 121959 | Heracles IC Maintenance 04-29-25 | ||
CURTAILMENT | 04/10/25 | 04/10/25 | 04/11/25 | 121840 | Copley Compressor Station Unplanned Maintenance 04-09-25 Complete! | ||
CURTAILMENT | 04/09/25 | 04/09/25 | 04/10/25 | 121759 | Copley Compressor Station Unplanned Maintenance 04-09-25 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/02/25 | 05/05/25 | 05/07/25 | 121539 | TP-7676 Pipeline Maintenance (East) 05-05-25 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/02/25 | 04/23/25 | 04/25/25 | 121519 | TP-7676 Pipeline Pigging 04-23-25 Update | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/01/25 | 04/23/25 | 04/25/25 | 121439 | TP-7676 Pipeline Pigging 04-23-25 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 04/01/25 | 07/09/25 | 07/12/25 | 121419 | D-494 Pipeline Maintenance Update 07-09-25 | ||
CAPACITY CONSTRAINT | 03/28/25 | 03/28/25 | 03/29/25 | 121319 | Plasma Capacity Constraint Lifted 4-1-2025 | ||
CAPACITY CONSTRAINT | 03/27/25 | 03/27/25 | 06/30/25 | 121260 | Equitrans to MVP Capacity Constraint Lifted 4-1-2025 | ||
CAPACITY CONSTRAINT | 03/27/25 | 03/27/25 | 06/30/25 | 121259 | H-508 and H-509 Pipelines Operationally Available Capacity Limit Update 4-1-2025 | ||
CAPACITY CONSTRAINT | 03/26/25 | 03/26/25 | 03/27/25 | 121219 | Blacksville Compressor Station Maintenance 03-25-25 COMPLETE | ||
PLANNED SERVICE OUTAGE | 03/24/25 | 03/24/25 | 06/30/25 | 121159 | Corona Compressor Station Maintenance 04-29-25 | ||
CURTAILMENT | 03/20/25 | 03/20/25 | 03/21/25 | 121059 | Copley Compressor Station Unplanned Maintenance 03-19-25 Complete | ||
CURTAILMENT | 03/18/25 | 03/18/25 | 03/20/25 | 120979 | Copley Compressor Station Unplanned Maintenance 03-19-25 | ||
CAPACITY CONSTRAINT | 03/11/25 | 03/25/25 | 03/26/25 | 120799 | Blacksville Compressor Station Maintenance 03-25-25 | ||
OPERATIONAL FLOW ORDER | 03/06/25 | 03/06/25 | 04/07/25 | 120619 | OFO Effective 3/7/2025 at 10AM ET | ||
CAPACITY CONSTRAINT | 03/04/25 | 03/04/25 | 12/31/00 | 120440 | Plasma Compressor Station Maintenance 03-04-25 Update 3 | ||
OPERATIONAL FLOW ORDER | 02/28/25 | 02/28/25 | 05/31/25 | 120299 | OFO Effective 3/1/2025 at 10AM ET | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 02/27/25 | 04/08/25 | 04/09/25 | 120239 | D-494 Pipeline Maintenance 04-08-25 HEADER CORRECTION TO NOTICE: 120219 | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 02/27/25 | 04/08/25 | 04/09/25 | 120219 | D-494 Pipeline Maintenance Update 05-30-24 | ||
OPERATIONAL FLOW ORDER | 02/10/25 | 02/10/25 | 05/31/25 | 119699 | OFO Effective 2/11/2025 at 10AM ET | ||
CAPACITY CONSTRAINT | 02/06/25 | 02/06/25 | 12/31/00 | 119579 | Plasma Compressor Station Maintenance 03-04-25 Update 2 | ||
OPERATIONAL FLOW ORDER | 01/30/25 | 01/30/25 | 04/30/25 | 119419 | OFO Lifted Effective 2/1/2025 at 10AM ET | ||
CURTAILMENT | 01/24/25 | 01/24/25 | 04/30/25 | 119259 | Plasma and Corona Compressor Station Maintenance 01-21-25 Update | ||
CAPACITY CONSTRAINT | 01/23/25 | 01/23/25 | 12/31/00 | 119222 | Plasma Compressor Station Maintenance 03-04-25 Update | ||
CAPACITY CONSTRAINT | 01/23/25 | 01/23/25 | 04/30/25 | 119199 | Plasma Compressor Station Maintenance 02-25-25 | ||
CURTAILMENT | 01/17/25 | 01/17/25 | 04/30/25 | 119039 | Plasma and Corona Compressor Station Maintenance 01-14-25 Complete | ||
CAPACITY CONSTRAINT | 01/16/25 | 01/16/25 | 04/30/25 | 119022 | Plasma Compressor Station Maintenance 02-25-25 | ||
OPERATIONAL FLOW ORDER | 01/06/25 | 01/06/25 | 04/30/25 | 118739 | OFO Effective 1/8/2025 at 10AM ET | ||
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE | 12/18/24 | 12/18/24 | 03/31/25 | 118259 | H-108 Pipeline Pigging 12-18-24 Complete | ||
CURTAILMENT | 12/12/24 | 12/12/24 | 03/31/25 | 118100 | Plasma and Corona Compressor Station Maintenance 01-21-25 | ||
CURTAILMENT | 12/12/24 | 12/12/24 | 03/31/25 | 118099 | Plasma and Corona Compressor Station Maintenance 01-14-25 | ||
CURTAILMENT | 12/07/24 | 12/07/24 | 03/31/25 | 117979 | Plasma Compressor Station Unplanned Maintenance 12-05-24 Complete | ||
CURTAILMENT | 12/05/24 | 12/05/24 | 03/31/25 | 117919 | Plasma Compressor Station Unplanned Maintenance 12-05-24 Update | ||
CURTAILMENT | 12/05/24 | 12/05/24 | 03/31/25 | 117899 | Plasma Compressor Station Unplanned Maintenance 12-05-24 |