Equitrans Gathering Notice 43692
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
01-15-2026 00:00:00
Page 1 of 2
System Wide Notice Detail
TSP Name:
EUREKA
TSP:
Post Date/Time:
Thu Jan 15 00:00:00 GMT 2026
Subject:
Zink Compressor Station Maintenance [01-28-26] UPDATE
Notice Type:
CRITICAL
Notice ID:
43692
Prior Notice:
43675
43675
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
01-15-2026
Notice Eff Time:
00:00:00
Notice End Date:
04-30-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
Notice Text:
Update to Notice ID #43675
Eureka Midstream LLC is providing notice that the planned maintenance previously scheduled for the January 21, 2026, Gas Day, at Zink
Compressor Station has been rescheduled to the January 28, 2026, Gas Day.
Original Notice (Revised)
Eureka Midstream LLC is providing notice of planned maintenance at Zink Compressor Station impacting deliveries to its downstream interconnects
on the January 28, 2026, Gas Day.
In conjunction with this maintenance, Operationally Available Capacity is reduced to a combined nomination total of 630,000 DTH at the REX
Interconnect, Meter #60059 (Eureka Cameron) and LXP Interconnect Meter #743103 for the January 28, 2026, Gas Day. All operators with
production flowing to Zink Compressor Station should expect to see higher than normal line pressure and a possible reduction in flow to receipts.
Nominations should be adjusted accordingly.
Nominations at Delivery Meter # 743103 (LXP-Eureka) from the EM-ORS Receipt IC (Meter # 10057) will not be impacted by this maintenance.
Nominations will be scheduled to not exceed the aforementioned amounts. These amounts are based on projected operating conditions and are
subject to change.
Should specific shut-ins be required, Equitrans Midstream will notify impacted parties.
01-15-2026 00:00:00
Page 2 of 2
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
*For production operations, Zink Compressor Station throughput will be reduced to 598 MMCFD for the January 28, 2026, Gas Day.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name:
EUREKA
TSP:
Post Date/Time:
Thu Jan 15 00:00:00 GMT 2026
Subject:
Zink Compressor Station Maintenance [01-28-26] UPDATE
Notice Type:
CRITICAL
Notice ID:
43692
Prior Notice:
43675
43675
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
01-15-2026
Notice Eff Time:
00:00:00
Notice End Date:
04-30-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
Update to Notice ID #43675
Eureka Midstream LLC is providing notice that the planned maintenance previously scheduled for the January 21, 2026, Gas Day, at Zink
Compressor Station has been rescheduled to the January 28, 2026, Gas Day.
Original Notice (Revised)
Eureka Midstream LLC is providing notice of planned maintenance at Zink Compressor Station impacting deliveries to its downstream interconnects
on the January 28, 2026, Gas Day.
In conjunction with this maintenance, Operationally Available Capacity is reduced to a combined nomination total of 630,000 DTH at the REX
Interconnect, Meter #60059 (Eureka Cameron) and LXP Interconnect Meter #743103 for the January 28, 2026, Gas Day. All operators with
production flowing to Zink Compressor Station should expect to see higher than normal line pressure and a possible reduction in flow to receipts.
Notice Text:
Nominations should be adjusted accordingly.
Nominations at Delivery Meter # 743103 (LXP-Eureka) from the EM-ORS Receipt IC (Meter # 10057) will not be impacted by this maintenance.
Nominations will be scheduled to not exceed the aforementioned amounts. These amounts are based on projected operating conditions and are
subject to change.
Should specific shut-ins be required, Equitrans Midstream will notify impacted parties.
01-15-2026 00:00:00
Page 1 of 2
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
*For production operations, Zink Compressor Station throughput will be reduced to 598 MMCFD for the January 28, 2026, Gas Day.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
01-15-2026 00:00:00
Page 2 of 2