East Tennessee Natural Gas Notice 181412
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Critical Notice Description: Critical Notices
Notice Effective Date / Time: 08/06/2026 07:21:52 PM
Notice End Date / Time: 11/04/2026 07:21:52 PM
Notice Identifier: 181412
Notice Status Description: Supersede
Notice Type: Capacity Constraint
Posting Date / Time: 08/06/2026 07:12:54 PM
Prior Notice Identifier: 181276
Required Response Indicator Description: No response required
Response Date / Time: None
Subject: Wartburg to Topside 3100-1 Unplanned Outage -- COMPLETE
Notice Text:
East Tennessee Natural Gas (ETNG) has completed the previously posted unplanned outage on its 3100-1 Line Valve Section 1 between its Wartburg Compressor Station and Topside and the pipeline has returned to normal operations. Effective immediately, all restrictions associated with this outage have been lifted. Contact your Operations Account Representative if you have any questions.
Notice Effective Date / Time: 08/06/2026 07:21:52 PM
Notice End Date / Time: 11/04/2026 07:21:52 PM
Notice Identifier: 181412
Notice Status Description: Supersede
Notice Type: Capacity Constraint
Posting Date / Time: 08/06/2026 07:12:54 PM
Prior Notice Identifier: 181276
Required Response Indicator Description: No response required
Response Date / Time: None
Subject: Wartburg to Topside 3100-1 Unplanned Outage -- COMPLETE
Notice Text:
East Tennessee Natural Gas (ETNG) has completed the previously posted unplanned outage on its 3100-1 Line Valve Section 1 between its Wartburg Compressor Station and Topside and the pipeline has returned to normal operations. Effective immediately, all restrictions associated with this outage have been lifted. Contact your Operations Account Representative if you have any questions.
Critical Notice Description: Critical Notices
Notice Effective Date / Time: 08/06/2026 07:21:52 PM
Notice End Date / Time: 11/04/2026 07:21:52 PM
Notice Identifier: 181412
Notice Status Description: Supersede
Notice Type: Capacity Constraint
Posting Date / Time: 08/06/2026 07:12:54 PM
Prior Notice Identifier: 181276
Required Response Indicator Description: No response required
Response Date / Time: None
Subject: Wartburg to Topside 3100-1 Unplanned Outage -- COMPLETE
Notice Text:
East Tennessee Natural Gas (ETNG) has completed the previously posted unplanned outage on its 3100-1 Line Valve Section 1 between its Wartburg Compressor Station and Topside and the pipeline has returned to normal operations. Effective immediately, all restrictions associated with this outage have been lifted. Contact your Operations Account Representative if you have any questions.
Notice Effective Date / Time: 08/06/2026 07:21:52 PM
Notice End Date / Time: 11/04/2026 07:21:52 PM
Notice Identifier: 181412
Notice Status Description: Supersede
Notice Type: Capacity Constraint
Posting Date / Time: 08/06/2026 07:12:54 PM
Prior Notice Identifier: 181276
Required Response Indicator Description: No response required
Response Date / Time: None
Subject: Wartburg to Topside 3100-1 Unplanned Outage -- COMPLETE
Notice Text:
East Tennessee Natural Gas (ETNG) has completed the previously posted unplanned outage on its 3100-1 Line Valve Section 1 between its Wartburg Compressor Station and Topside and the pipeline has returned to normal operations. Effective immediately, all restrictions associated with this outage have been lifted. Contact your Operations Account Representative if you have any questions.