East Tennessee Natural Gas Notice 181276

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Critical Notice Description: Critical Notices

Notice Effective Date / Time: 08/04/2026 06:19:06 PM

Notice End Date / Time: 11/02/2026 06:19:06 PM

Notice Identifier: 181276

Notice Status Description: Initiate

Notice Type: Capacity Constraint

Posting Date / Time: 08/04/2026 06:11:25 PM

Prior Notice Identifier: None

Required Response Indicator Description: No response required

Response Date / Time: None

Subject: Wartburg to Topside 3100-1 Unplanned Outage

Notice Text:

Due to third party activity, ETNG has experienced an unplanned outage on its 3100-1 Line Valve Section 1 between its Wartburg Compressor Station and Topside.  As a result of this unplanned outage, effective immediately, ETNG will be lowering the line pressure between Wartburg to Topside Valve Section 1 on the 3100-1 Line until this segment has been appropriately remediated.  Meters downstream of the isolation may experience lower than historical operating pressures.    At this time, ETNG does not anticipate any reduction to nominations through Wartburg. 

                                            

The following meter will be unavailable for flow until Wartburg to Topside Valve Section 1 is returned to normal operations:

 

MR 59337 - ARIANA ENERGY MORGAN CO. 9

 

ETNG will post updates to the status of the repairs as soon as it is known.

 

Please contact your Operations Account Representative should you have any questions.



Critical Notice Description: Critical Notices

Notice Effective Date / Time: 08/04/2026 06:19:06 PM

Notice End Date / Time: 11/02/2026 06:19:06 PM

Notice Identifier: 181276

Notice Status Description: Initiate

Notice Type: Capacity Constraint

Posting Date / Time: 08/04/2026 06:11:25 PM

Prior Notice Identifier: None

Required Response Indicator Description: No response required

Response Date / Time: None

Subject: Wartburg to Topside 3100-1 Unplanned Outage

Notice Text:

Due to third party activity, ETNG has experienced an unplanned outage on its 3100-1 Line Valve Section 1 between its Wartburg Compressor Station and Topside.  As a result of this unplanned outage, effective immediately, ETNG will be lowering the line pressure between Wartburg to Topside Valve Section 1 on the 3100-1 Line until this segment has been appropriately remediated.  Meters downstream of the isolation may experience lower than historical operating pressures.    At this time, ETNG does not anticipate any reduction to nominations through Wartburg. 

                                            

The following meter will be unavailable for flow until Wartburg to Topside Valve Section 1 is returned to normal operations:

 

MR 59337 - ARIANA ENERGY MORGAN CO. 9

 

ETNG will post updates to the status of the repairs as soon as it is known.

 

Please contact your Operations Account Representative should you have any questions.