Columbia Gas Transmission Notice 25948213
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
|
TSP Name
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
25948213
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/02/25
09/02/25
10/02/25
1:10:50 PM
12:00:00 AM
12:00:00 AM
Subject: Cobb Compressor Station Maintenance, Effective September 8-21, 2025
Author: Dillon Schoolcraft
Notice Text
Columbia Gas Transmission, LLC (TCO) reminds customers of upcoming maintenance activities at Cobb Compressor Station scheduled to begin on Monday, September 8, 2025, through Sunday, September 21, 2025. In an effort to minimize the commercial impact, there will be no associated capacity restrictions for Gas Day Monday, September 9, 2025. However, effective Timely Cycle for Gas Day September 9, 2025, the following Internal Constraints will be reduced to Zero Total Capacity:Cobb Northeast MA40 (A03NORTH)Cobb Northwest MA18 (A03LOW)Additionally, effective Timely Cycle for Gas Day Sunday, September 14, 2025, the following Internal Constraints will also be reduced to Zero Total Capacity:Cobb South MA18 (A03SOUTH)Cobb Line H (A03LINEH)COBB CS MA18 (COBBA03)Reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 38 of TCO’s FERC Gas Tariff (“Tariff”). However, TCO will only issue RCCs if TCO is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day average usage quantity less any scheduled quantities on the contract. By means of this notice, TCO is establishing which specific Gas Days will be included when determining a shipper’s 7-day average usage quantity pursuant to the provisions in the Tariff. Please contact your Customer Services Representative with any questions.
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
25948213
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/02/25
09/02/25
10/02/25
1:10:50 PM
12:00:00 AM
12:00:00 AM
Subject: Cobb Compressor Station Maintenance, Effective September 8-21, 2025
Author: Dillon Schoolcraft
Notice Text
Columbia Gas Transmission, LLC (TCO) reminds customers of upcoming maintenance activities at Cobb Compressor Station scheduled to begin on Monday, September 8, 2025, through Sunday, September 21, 2025. In an effort to minimize the commercial impact, there will be no associated capacity restrictions for Gas Day Monday, September 9, 2025. However, effective Timely Cycle for Gas Day September 9, 2025, the following Internal Constraints will be reduced to Zero Total Capacity:Cobb Northeast MA40 (A03NORTH)Cobb Northwest MA18 (A03LOW)Additionally, effective Timely Cycle for Gas Day Sunday, September 14, 2025, the following Internal Constraints will also be reduced to Zero Total Capacity:Cobb South MA18 (A03SOUTH)Cobb Line H (A03LINEH)COBB CS MA18 (COBBA03)Reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 38 of TCO’s FERC Gas Tariff (“Tariff”). However, TCO will only issue RCCs if TCO is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day average usage quantity less any scheduled quantities on the contract. By means of this notice, TCO is establishing which specific Gas Days will be included when determining a shipper’s 7-day average usage quantity pursuant to the provisions in the Tariff. Please contact your Customer Services Representative with any questions.