Transwestern Pipeline Company Notice 115114

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice Type Description: Force Majeure
Notice Identifier: 115114
Critical Notice Description: Critical notice
Posting Date/Time: Feb 11 2026 12:07PM
Notice Status Description: Supersede
Required Response Indicator Description: No response required
Response Date/Time:
TSP: 7933047
TSP Name: TRANSWESTERN PIPELINE COMPANY, LLC
Subject: Force Majeure - Compressor Station P3 Mechanical Failure - 2/11/26 - REVISION 1
Notice Effective Date/Time: Feb 11 2026 9:00AM
Notice End Date/Time: Feb 12 2026 8:59AM
Notice Text:

February 11, 2026


To: All Transwestern Customers

Subject: Force Majeure - Compressor Station P3 - Revision 1

Revision 1: Transwestern Pipeline has made the necessary repairs at Compressor Station P3.  We will bring the capacity back up to normal on ID-2 today, Wednesday 2/11/26.

Reason: Mechanical Failure

February 11, 2026

P-3 Station Delivery Capacity reduced from 253,000 MMBtu/d to approximately 150,000 MMBtu/d.

We anticipate this will impact approximately 50,000 MMBtu/d of scheduled volumes.

Interconnects Affected:
POI 57274 -ANR Red Deer
POI   9198 - CIG Tumbleweed
POI 79064- Enbridge Trunk E (Palo Duro)
POI   8042 - PEPL Hansford/Sherman
POI 60667 - NNG Gray
POI 10594 - Southern Star

February 11, 2026 (Intraday 2)

Back to full capacity through P-3 Compressor Station.

Transwestern reserves the right to revise the above listed schedule. Please continue to monitor theTranswestern website for updates and schedule changes. Contact your account or scheduling representative if you need additional information.

Reason:
Notice Type Description: Force Majeure
Notice Identifier: 115114
Critical Notice Description: Critical notice
Posting Date/Time: Feb 11 2026 12:07PM
Notice Status Description: Supersede
Required Response Indicator Description: No response required
Response Date/Time:
TSP: 7933047
TSP Name: TRANSWESTERN PIPELINE COMPANY, LLC
Subject: Force Majeure - Compressor Station P3 Mechanical Failure - 2/11/26 - REVISION 1
Notice Effective Date/Time: Feb 11 2026 9:00AM
Notice End Date/Time: Feb 12 2026 8:59AM
Notice Text:

February 11, 2026


To: All Transwestern Customers

Subject: Force Majeure - Compressor Station P3 - Revision 1

Revision 1: Transwestern Pipeline has made the necessary repairs at Compressor Station P3.  We will bring the capacity back up to normal on ID-2 today, Wednesday 2/11/26.

Reason: Mechanical Failure

February 11, 2026

P-3 Station Delivery Capacity reduced from 253,000 MMBtu/d to approximately 150,000 MMBtu/d.

We anticipate this will impact approximately 50,000 MMBtu/d of scheduled volumes.

Interconnects Affected:
POI 57274 -ANR Red Deer
POI   9198 - CIG Tumbleweed
POI 79064- Enbridge Trunk E (Palo Duro)
POI   8042 - PEPL Hansford/Sherman
POI 60667 - NNG Gray
POI 10594 - Southern Star

February 11, 2026 (Intraday 2)

Back to full capacity through P-3 Compressor Station.

Transwestern reserves the right to revise the above listed schedule. Please continue to monitor theTranswestern website for updates and schedule changes. Contact your account or scheduling representative if you need additional information.

Reason: