Transco Pipeline Notice 16555673

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 02/11/2026
Notice Eff Time: 13:47:47 CST
Notice End Date:
Notice End Time:
Notice ID: 16555673
Notice Stat Desc: Supersede
Notice Type Desc: Force Maj
Post Date: 02/11/2026
Post Time: 13:47:47 CST
Prior Notice: 16544208
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Notice of Force Majeure Event - Unplanned Equipment Outage Station 115

Subject: Update - Notice of Force Majeure Event - Unplanned Equipment Outage Station 115

Update: Due to improved system conditions, the available capacity will be increased per the table below, effective February 12, 2026.  Work to resolve the issue is ongoing with the return to service timeline and is still TBD. Additional updates and a more accurate timeline will be provided as more information becomes available.

Transcontinental Gas Pipe Line Company, LLC (“Transco”), pursuant to Section 11 of the General Terms and Conditions of its FERC Gas Tariff, hereby provides an update to the force majeure event involving the unplanned outage at Compressor Station 115.

Operating Conditions resulting from this work will require Transco to restrict scheduled quantities for all transportation priorities moving South to North through the location indicated below. Transactions moving North to South through this location will not be impacted.

The delivery-based Throughput Section Boundary (TSB) at mainline milepost 1007.66 will be used to manage capacity during this unplanned work.

 

TSB Name - Location

Location ID

Flow Direction

Station 115 MP 1007.66

9011120

South to North

 

 

Estimated Outage

 

 

Design Capacity (Mdth/d)

Total Primary Firm Qty Available (Mdth/d)

%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization)

February 8, 2026 (ID2),February 11, 2026

4,746

3,850

6 – 13%

February 12, 2026 -TBD

4,746

3,950

0 – 5%

 

 

 

 

If you have any questions, please contact your Transportation Services Representative.