Transco Pipeline Notice 16017117

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 09/03/2025
Notice Eff Time: 12:47:57 CDT
Notice End Date:
Notice End Time:
Notice ID: 16017117
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 09/03/2025
Post Time: 12:47:57 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Station 35 (Job 240432) 2025 Planned Outage and Maintenance Summary

Transco will be performing necessary pipeline integrity assessments associated with Job #240432 on its 2025 Planned Outage and Maintenance Summary. This maintenance activity will impact the availability of transportation services moving south to north through Station 35 for each pig run date.

The specific dates for the assessments are subject to change, but the current schedule is outlined below:

Pig Runs

Dates

Gauge Tool

10/14

Cleaner Tool

10/16

Combo Tool

10/21

CMFL Tool

10/23

EMAT Tool

10/28

Operating Conditions resulting from this work will require Transco to manage scheduled quantities for all transportation priorities moving south to north through the location indicated below.

 

The location Throughput Section Boundary (TSB) for station 35 at mainline milepost 327.27 S-N will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the TSB and the available quantity of transportation services during the indicated period.

 

TSB Name - Location

Location ID

Flow Direction

Station 35 S to N MP 327.27

9011644

South to North

 

 

Estimated Outage

Location ID

Design Capacity (Dt/d)

Total Quantity Available (Dt/d)

% Available Total Primary-Firm vs Design Capacity

% Cuts (Primary) – Potential Shipper Impact (Based on Historical Utilization)*

10/14, 10/16, 10/21, 10/23, 10/28

 

9011644

 

708,995

 

250,000

 

35%

 

60-65%

 

 

If you have any questions, please contact your Transportation Services Representative.