Texas Eastern Transmission Notice 182224
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Notice Effective Date / Time: 08/27/2026 09:08:26 AM
Notice End Date / Time: 11/25/2026 09:08:26 AM
Notice Identifier: 182224
Notice Status Description: Initiate
Notice Type: Capacity Constraint
Posting Date / Time: 08/27/2026 08:59:19 AM
Prior Notice Identifier: None
Required Response Indicator Description: No response required
Response Date / Time: None
Subject: Lebanon Compressor Station Unplanned Outage
Notice Text:
Reduced to approximately
Berne 579,000 Dth/d
Sarahsville 579,000 Dth/d
Somerset 579,000 Dth/d
Five Points 678,000 Dth/d
Lebanon 676,000 Dth/d
Point operators located downstream of Lebanon compressor station may see lower than desired pressures.
Nominations for Gas Day August 27, 2026 will remain unaffected. However, Texas Eastern anticipates restricting all non-primary nominations for Gas Day August 28, 2026 at the Sarahsville, Five Points and Lebanon compressor stations.
TE will post further updates to the status of the repairs as soon as it is known.
Please contact your Operations Account Representative if you have any questions.
Notice Effective Date / Time: 08/27/2026 09:08:26 AM
Notice End Date / Time: 11/25/2026 09:08:26 AM
Notice Identifier: 182224
Notice Status Description: Initiate
Notice Type: Capacity Constraint
Posting Date / Time: 08/27/2026 08:59:19 AM
Prior Notice Identifier: None
Required Response Indicator Description: No response required
Response Date / Time: None
Subject: Lebanon Compressor Station Unplanned Outage
Notice Text:
Reduced to approximately
Berne 579,000 Dth/d
Sarahsville 579,000 Dth/d
Somerset 579,000 Dth/d
Five Points 678,000 Dth/d
Lebanon 676,000 Dth/d
Point operators located downstream of Lebanon compressor station may see lower than desired pressures.
Nominations for Gas Day August 27, 2026 will remain unaffected. However, Texas Eastern anticipates restricting all non-primary nominations for Gas Day August 28, 2026 at the Sarahsville, Five Points and Lebanon compressor stations.
TE will post further updates to the status of the repairs as soon as it is known.
Please contact your Operations Account Representative if you have any questions.