Tennessee Gas Pipeline Notice 404029

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS Notice Eff Date/Time:  09/06/2026 7:14:51PM Notice End Date/Time:  09/07/2026 9:00:00am Post Date/Time:  9/6/2026 7:14:51 PM Notice ID: 404029 Reqrd Rsp:  1 Rsp Date/Time:  9/6/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  RESTRICTIONS FOR 09-07-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Monday, September 07, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 ON THE 500 lINE FROM STA 527 TO STA 542 FOR OVERTAKES from the system OR UNDERDELIVERieS into the system  FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES

 

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 219 FOR OVERDELIEVERIES INTO THE SYSTEM OR UNDERTAKES OUT OF THE SYSTEM FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES

 

 

 

METER RESTRICTIONS

·         FGT/TGP Carnes Mississippi Stone Delivery Meter (Pin 420366) - through 100% of PIP due to planned and unplanned maintenance

·         TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of IT increases due to operational concerns; 17 Dths

·         WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through approx 45% of SA increases due to nominations in excess of operational capacity; 9,127 Dths

·         ETNG/TGP East Lobelville Tn Perry Receipt Meter (Pin 420042) - through 100% of IT increases receipts due to displacement gas unavailable for backhaul; 1,800 Dths

·         AGT/TGP Lincoln Ma Tie Over Worches Receipt Meter (Pin 420350) - through 100% of IT increases receipts due to displacement gas unavailable for backhaul; 3,628 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 91,415 Dths

·         MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,494 Dths

·         STA 860 (Segment 860 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 14,964 Dths

·         STA 114 East (Segment 114 BH) - through PIP increases due to force majeure

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 368,652 Dths

·         MLV 314 East (Segment 314 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 217,372 Dths

·         STA 315 (Segment 315 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 227,659 Dths

·         STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 147,972 Dths

·         STA 321 (Segment 321 FH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 411,717 Dths

·         MLV 330 (Segment 324 FH) - through approx 64% of SOP increases due to nominations in excess of operational capacity; 90,479 Dths

·         MLV 355 (Segment 355 BH) - through 100% of SOP increases due to operational concerns; 144 Dths

·         STA 313Hcg - Z4 Hc (Segment 399 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 52,201 Dths

·         Z5hc North (Segment 299 FH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 154,100 Dths

·         STA 245 (Segment 245 FH) - through approx 70% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 146,165 Dths

·         STA 249 (Segment 249 FH) - through approx 36% of SOP increases due to nominations in excess of operational capacity; 47,788 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 85% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 42,141 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 152,031 Dths

LINEPACK RESTRICTIONS

PAYBACK NOMINATIONS WILL BE EVALUATED AT EACH CYCLE AND SCHEDULED ONLY IF OPERATIONALLY FEASIBLE.

 

 

 

STORAGE RESTRICTIONS

No Authorized Overrun Injections Services under Rate Schedule FS-AO at the following storage fields:

o   Northern MA (460018) storage field

o   Portland MA (460025) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

o   Northern MA (460018) storage field

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service in Zones 4, 5 and 6

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service in Zones 4, 5 and 6

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS Notice Eff Date/Time:  09/06/2026 7:14:51PM Notice End Date/Time:  09/07/2026 9:00:00am Post Date/Time:  9/6/2026 7:14:51 PM Notice ID: 404029 Reqrd Rsp:  1 Rsp Date/Time:  9/6/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  RESTRICTIONS FOR 09-07-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Monday, September 07, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 ON THE 500 lINE FROM STA 527 TO STA 542 FOR OVERTAKES from the system OR UNDERDELIVERieS into the system  FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES

 

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 219 FOR OVERDELIEVERIES INTO THE SYSTEM OR UNDERTAKES OUT OF THE SYSTEM FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES

 

 

 

METER RESTRICTIONS

·         FGT/TGP Carnes Mississippi Stone Delivery Meter (Pin 420366) - through 100% of PIP due to planned and unplanned maintenance

·         TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of IT increases due to operational concerns; 17 Dths

·         WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through approx 45% of SA increases due to nominations in excess of operational capacity; 9,127 Dths

·         ETNG/TGP East Lobelville Tn Perry Receipt Meter (Pin 420042) - through 100% of IT increases receipts due to displacement gas unavailable for backhaul; 1,800 Dths

·         AGT/TGP Lincoln Ma Tie Over Worches Receipt Meter (Pin 420350) - through 100% of IT increases receipts due to displacement gas unavailable for backhaul; 3,628 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 91,415 Dths

·         MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,494 Dths

·         STA 860 (Segment 860 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 14,964 Dths

·         STA 114 East (Segment 114 BH) - through PIP increases due to force majeure

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 368,652 Dths

·         MLV 314 East (Segment 314 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 217,372 Dths

·         STA 315 (Segment 315 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 227,659 Dths

·         STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 147,972 Dths

·         STA 321 (Segment 321 FH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 411,717 Dths

·         MLV 330 (Segment 324 FH) - through approx 64% of SOP increases due to nominations in excess of operational capacity; 90,479 Dths

·         MLV 355 (Segment 355 BH) - through 100% of SOP increases due to operational concerns; 144 Dths

·         STA 313Hcg - Z4 Hc (Segment 399 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 52,201 Dths

·         Z5hc North (Segment 299 FH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 154,100 Dths

·         STA 245 (Segment 245 FH) - through approx 70% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 146,165 Dths

·         STA 249 (Segment 249 FH) - through approx 36% of SOP increases due to nominations in excess of operational capacity; 47,788 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 85% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 42,141 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 152,031 Dths

LINEPACK RESTRICTIONS

PAYBACK NOMINATIONS WILL BE EVALUATED AT EACH CYCLE AND SCHEDULED ONLY IF OPERATIONALLY FEASIBLE.

 

 

 

STORAGE RESTRICTIONS

No Authorized Overrun Injections Services under Rate Schedule FS-AO at the following storage fields:

o   Northern MA (460018) storage field

o   Portland MA (460025) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

o   Northern MA (460018) storage field

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service in Zones 4, 5 and 6

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service in Zones 4, 5 and 6

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.