Tennessee Gas Pipeline Notice 403313

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  CAPACITY CONSTRAINT Notice Type Desc (2):  SEGMENTS Notice Eff Date/Time:  08/06/2026 6:44:05AM Notice End Date/Time:  08/07/2026 9:00:00am Post Date/Time:  8/6/2026 6:44:05 AM Notice ID: 403313 Reqrd Rsp:  1 Rsp Date/Time:  8/6/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  403265 Subject:  ANT PIP RESTR 187BH & 539BH EFF 8-7-26
Notice Text:
 
ANTICIPATED PRIMARY IN THE PATH RESTRICTIONS AT STA 110 (SEGMENT 187 BH) AND STA 542 (SEGMENT 539 BH) EFFECTIVE 8-7-2026 
 

Due to current nominations, planned and unplanned maintenance and operational conditions, effective Timely Cycle for gas day of Friday, August 7, 2026, and continuing until further notice, Tennessee anticipates scheduling Primary In the Path (“PIP”) transports to no less than the percentage of firm contracts pathed through the following segments:

 

STA 110 (Segment 187 BH) – no less than 88% of contract MDQ

 

STA 542 (Segment 539 BH) – NO PRIMARY IN THE PATH RESTRICTIONS ANTICIPATED

 

The stated scheduling percentages are based upon the current level of firm capacity contracted for during these restrictions and are subject to change based upon operational conditions and Shipper utilization.

 
Please contact your Account Director or Scheduling Representative if you have any questions. 
 
 
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  CAPACITY CONSTRAINT Notice Type Desc (2):  SEGMENTS Notice Eff Date/Time:  08/06/2026 6:44:05AM Notice End Date/Time:  08/07/2026 9:00:00am Post Date/Time:  8/6/2026 6:44:05 AM Notice ID: 403313 Reqrd Rsp:  1 Rsp Date/Time:  8/6/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  403265 Subject:  ANT PIP RESTR 187BH & 539BH EFF 8-7-26
Notice Text:
 
ANTICIPATED PRIMARY IN THE PATH RESTRICTIONS AT STA 110 (SEGMENT 187 BH) AND STA 542 (SEGMENT 539 BH) EFFECTIVE 8-7-2026 
 

Due to current nominations, planned and unplanned maintenance and operational conditions, effective Timely Cycle for gas day of Friday, August 7, 2026, and continuing until further notice, Tennessee anticipates scheduling Primary In the Path (“PIP”) transports to no less than the percentage of firm contracts pathed through the following segments:

 

STA 110 (Segment 187 BH) – no less than 88% of contract MDQ

 

STA 542 (Segment 539 BH) – NO PRIMARY IN THE PATH RESTRICTIONS ANTICIPATED

 

The stated scheduling percentages are based upon the current level of firm capacity contracted for during these restrictions and are subject to change based upon operational conditions and Shipper utilization.

 
Please contact your Account Director or Scheduling Representative if you have any questions.