Tennessee Gas Pipeline Notice 402707

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS Notice Eff Date/Time:  07/10/2026 7:29:55PM Notice End Date/Time:  07/11/2026 9:00:00am Post Date/Time:  7/10/2026 7:29:55 PM Notice ID: 402707 Reqrd Rsp:  1 Rsp Date:  7/10/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  RESTRICTIONS FOR 07-10-2026 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of Friday, July 10, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·       TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of IT increases due to pipeline maintenance at delivery location; 50 Dths

·       GULFSTH/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 34 Dths

SEGMENT RESTRICTIONS

·       STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 400 Dths

·       MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 5,000 Dths

·       STA 110 South (Segment 187 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·       STA 317 (Segment 317 BH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 83,505 Dths

·       STA 245 (Segment 245 FH) - through approx 53% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 43,834 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS Notice Eff Date/Time:  07/10/2026 7:29:55PM Notice End Date/Time:  07/11/2026 9:00:00am Post Date/Time:  7/10/2026 7:29:55 PM Notice ID: 402707 Reqrd Rsp:  1 Rsp Date:  7/10/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  RESTRICTIONS FOR 07-10-2026 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of Friday, July 10, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·       TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of IT increases due to pipeline maintenance at delivery location; 50 Dths

·       GULFSTH/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 34 Dths

SEGMENT RESTRICTIONS

·       STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 400 Dths

·       MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 5,000 Dths

·       STA 110 South (Segment 187 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·       STA 317 (Segment 317 BH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 83,505 Dths

·       STA 245 (Segment 245 FH) - through approx 53% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 43,834 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.