Tennessee Gas Pipeline Notice 402179
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Effective Intraday 2 Cycle (18:00) for the gas day of Thursday, June 18, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to pipeline maintenance at delivery location; 1,104 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 35,761 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,500 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· STA 204 (Segment 204 BH) - through SIPps increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through SIPss increases due to scheduled maintenance and nominations in excess of operational capacity
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 186,617 Dths
· STA 315 (Segment 315 BH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 173,955 Dths
· STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 123,886 Dths
· STA 321 (Segment 321 FH) - through approx 27% of SOP increases due to nominations in excess of operational capacity; 13,703 Dths
· MLV 330 (Segment 324 FH) - through approx 66% of SOP increases due to nominations in excess of operational capacity; 34,077 Dths
· Z5hc North (Segment 299 FH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 148,688 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 269,074 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 17,489 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 157,817 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Effective Intraday 2 Cycle (18:00) for the gas day of Thursday, June 18, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to pipeline maintenance at delivery location; 1,104 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 35,761 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,500 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· STA 204 (Segment 204 BH) - through SIPps increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through SIPss increases due to scheduled maintenance and nominations in excess of operational capacity
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 186,617 Dths
· STA 315 (Segment 315 BH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 173,955 Dths
· STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 123,886 Dths
· STA 321 (Segment 321 FH) - through approx 27% of SOP increases due to nominations in excess of operational capacity; 13,703 Dths
· MLV 330 (Segment 324 FH) - through approx 66% of SOP increases due to nominations in excess of operational capacity; 34,077 Dths
· Z5hc North (Segment 299 FH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 148,688 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 269,074 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 17,489 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 157,817 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.