Effective Evening Cycle (9:00) for the gas day of Wednesday, June 17, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases due to pipeline maintenance at delivery location; 4,804 Dths
SEGMENT RESTRICTIONS
· STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,325 Dths
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 105,684 Dths
· STA 9 (Segment 109 BH) - through approx 25% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 18,755 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,500 Dths
· STA 860 (Segment 860 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 53,600 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 6,500 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 236,450 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 283,180 Dths
· STA 317 (Segment 317 BH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 67,873 Dths
· STA 321 (Segment 321 FH) - through approx 78% of SOP increases due to nominations in excess of operational capacity; 236,805 Dths
· STA 325 (Segment 324 FH) - through approx 5% of SOP increases due to nominations in excess of operational capacity; 6,594 Dths
· MLV 330 (Segment 324 FH) - through approx 61% of SOP increases due to nominations in excess of operational capacity; 76,541 Dths
· Z5hc North (Segment 299 FH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 195,762 Dths
· STA 245 (Segment 245 FH) - through approx 95% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 334,589 Dths
· STA 249 (Segment 249 FH) - through approx 14% of SOP increases due to nominations in excess of operational capacity; 17,817 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 217,222 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Effective Evening Cycle (9:00) for the gas day of Wednesday, June 17, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases due to pipeline maintenance at delivery location; 4,804 Dths
SEGMENT RESTRICTIONS
· STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,325 Dths
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 105,684 Dths
· STA 9 (Segment 109 BH) - through approx 25% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 18,755 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,500 Dths
· STA 860 (Segment 860 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 53,600 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 6,500 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 236,450 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 283,180 Dths
· STA 317 (Segment 317 BH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 67,873 Dths
· STA 321 (Segment 321 FH) - through approx 78% of SOP increases due to nominations in excess of operational capacity; 236,805 Dths
· STA 325 (Segment 324 FH) - through approx 5% of SOP increases due to nominations in excess of operational capacity; 6,594 Dths
· MLV 330 (Segment 324 FH) - through approx 61% of SOP increases due to nominations in excess of operational capacity; 76,541 Dths
· Z5hc North (Segment 299 FH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 195,762 Dths
· STA 245 (Segment 245 FH) - through approx 95% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 334,589 Dths
· STA 249 (Segment 249 FH) - through approx 14% of SOP increases due to nominations in excess of operational capacity; 17,817 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 217,222 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.