Tennessee Gas Pipeline Notice 402004
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Effective Intraday 2 Cycle (18:00) for the gas day of Thursday, June 11, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 4,650 Dths
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to pipeline maintenance at delivery location; 1,104 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 37% of SIPps increases due to nominations in excess of operational capacity; 22,111 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through approx 21% of SOP increases due to operational concerns; 6,261 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,500 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 11,104 Dths
· STA 110 South (Segment 187 BH) - through SIPps increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 78% of SOP increases due to nominations in excess of operational capacity; 205,453 Dths
· STA 315 (Segment 315 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 209,139 Dths
· STA 317 (Segment 317 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 119,213 Dths
· MLV 329 (Segment 324 FH) - into PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· Z5hc North (Segment 299 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 149,819 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 266,136 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 77,725 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 91,938 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 154,813 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Effective Intraday 2 Cycle (18:00) for the gas day of Thursday, June 11, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 4,650 Dths
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to pipeline maintenance at delivery location; 1,104 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 37% of SIPps increases due to nominations in excess of operational capacity; 22,111 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through approx 21% of SOP increases due to operational concerns; 6,261 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,500 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 11,104 Dths
· STA 110 South (Segment 187 BH) - through SIPps increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 78% of SOP increases due to nominations in excess of operational capacity; 205,453 Dths
· STA 315 (Segment 315 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 209,139 Dths
· STA 317 (Segment 317 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 119,213 Dths
· MLV 329 (Segment 324 FH) - into PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· Z5hc North (Segment 299 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 149,819 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 266,136 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 77,725 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 91,938 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 154,813 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.