Tennessee Gas Pipeline Notice 401830
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Effective Timely Cycle (9:00) for the gas day of Friday, June 05, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· ANR/TGP TGP ANR Greenville Intercon Delivery Meter (Pin 420941) - through 100% of SIPps due to operational concerns; 1,000 Dths
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps due to pipeline maintenance at delivery location; 9,795 Dths
· TET/TGP Dry Creek Sales Casey Delivery Meter (Pin 420886) - through approx 93% of IT due to operational concerns; 26,021 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through approx 55% of SOP due to operational concerns; 68,701 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP due to nominations in excess of operational capacity; 2,500 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 5,000 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 10,000 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 1,428 Dths
· STA 110 South (Segment 187 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 85% of SOP due to nominations in excess of operational capacity; 362,311 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 438,924 Dths
· STA 317 (Segment 317 BH) - through approx 76% of SOP due to nominations in excess of operational capacity; 169,059 Dths
· STA 321 (Segment 321 FH) - through approx 52% of SOP due to nominations in excess of operational capacity; 587,672 Dths
· STA 325 (Segment 324 FH) - through approx 26% of SOP due to nominations in excess of operational capacity; 131,010 Dths
· MLV 330 (Segment 324 FH) - through approx 26% of SOP due to nominations in excess of operational capacity; 147,281 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP due to operational concerns; 9,200 Dths
· Z5 HC North (Segment 299 FH) - through approx 76% of SOP due to nominations in excess of operational capacity; 592,462 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 896,810 Dths
· STA 249 (Segment 249 FH) - through approx 41% of SOP due to nominations in excess of operational capacity; 206,263 Dths
· MLV 273 (Segment 284 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 214,084 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Effective Timely Cycle (9:00) for the gas day of Friday, June 05, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· ANR/TGP TGP ANR Greenville Intercon Delivery Meter (Pin 420941) - through 100% of SIPps due to operational concerns; 1,000 Dths
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps due to pipeline maintenance at delivery location; 9,795 Dths
· TET/TGP Dry Creek Sales Casey Delivery Meter (Pin 420886) - through approx 93% of IT due to operational concerns; 26,021 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through approx 55% of SOP due to operational concerns; 68,701 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP due to nominations in excess of operational capacity; 2,500 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 5,000 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 10,000 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 1,428 Dths
· STA 110 South (Segment 187 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 85% of SOP due to nominations in excess of operational capacity; 362,311 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 438,924 Dths
· STA 317 (Segment 317 BH) - through approx 76% of SOP due to nominations in excess of operational capacity; 169,059 Dths
· STA 321 (Segment 321 FH) - through approx 52% of SOP due to nominations in excess of operational capacity; 587,672 Dths
· STA 325 (Segment 324 FH) - through approx 26% of SOP due to nominations in excess of operational capacity; 131,010 Dths
· MLV 330 (Segment 324 FH) - through approx 26% of SOP due to nominations in excess of operational capacity; 147,281 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP due to operational concerns; 9,200 Dths
· Z5 HC North (Segment 299 FH) - through approx 76% of SOP due to nominations in excess of operational capacity; 592,462 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 896,810 Dths
· STA 249 (Segment 249 FH) - through approx 41% of SOP due to nominations in excess of operational capacity; 206,263 Dths
· MLV 273 (Segment 284 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 214,084 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.