TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS Notice Eff Date/Time:  05/31/2026 10:59:31AM Notice End Date/Time:  06/01/2026 9:00:00am Post Date/Time:  5/31/2026 10:59:31 AM Notice ID: 401719 Reqrd Rsp:  1 Rsp Date:  5/31/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  RESTRICTIONS FOR 05-31-2026 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Sunday, May 31, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

ofo daily critical day 1 for all of zones 4, 5 and 6 for UNDER-takes from the system or OVER-deliveries into the system for lm-MA, SA ACTING AS BALANCING PARTIES AND LM-PA BALANCING PARTIES ONLY.

 

METER RESTRICTIONS

·         Greenbrier Tn 2 (Dual) Delivery Meter (Pin 420289) - through approx 15% of SIPss receipt increases due to displacement gas unavailable for backhaul; 22,070 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 30,000 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 52,275 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 9,944 Dths

·         MLV 548 (Segment 542 BH) - through SIPss increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 110 South (Segment 187 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths

·         MLV 314 East (Segment 314 BH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 201,956 Dths

·         STA 315 (Segment 315 BH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 308,310 Dths

·         STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 76,526 Dths

·         MLV 330 (Segment 324 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 73,796 Dths

·         Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 133,901 Dths

·         STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 84,145 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 107,374 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS Notice Eff Date/Time:  05/31/2026 10:59:31AM Notice End Date/Time:  06/01/2026 9:00:00am Post Date/Time:  5/31/2026 10:59:31 AM Notice ID: 401719 Reqrd Rsp:  1 Rsp Date:  5/31/2026 12:00:00 AM Notice Stat Desc:  INITIATE Prior Notice:  Subject:  RESTRICTIONS FOR 05-31-2026 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Sunday, May 31, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

ofo daily critical day 1 for all of zones 4, 5 and 6 for UNDER-takes from the system or OVER-deliveries into the system for lm-MA, SA ACTING AS BALANCING PARTIES AND LM-PA BALANCING PARTIES ONLY.

 

METER RESTRICTIONS

·         Greenbrier Tn 2 (Dual) Delivery Meter (Pin 420289) - through approx 15% of SIPss receipt increases due to displacement gas unavailable for backhaul; 22,070 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 30,000 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 52,275 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 9,944 Dths

·         MLV 548 (Segment 542 BH) - through SIPss increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 110 South (Segment 187 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths

·         MLV 314 East (Segment 314 BH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 201,956 Dths

·         STA 315 (Segment 315 BH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 308,310 Dths

·         STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 76,526 Dths

·         MLV 330 (Segment 324 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 73,796 Dths

·         Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 133,901 Dths

·         STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 84,145 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 107,374 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.