Tennessee Gas Pipeline Notice 401059

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  05/02/2026 7:26:23PM Notice End Date/Time:  05/03/2026 9:00:00am
Post Date/Time:  5/2/2026 7:26:23 PM Notice ID: 401059
Reqrd Rsp:  1 Rsp Date:  05/02/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 05-03-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Sunday, May 03, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

ofo daily critical day 1 for over-deliveries into the system or under-takes out of the system for various parts of the system (see notice identifier 401023) for lmmas, lmpas and sas acting as balancing parties only

 

METER RESTRICTIONS

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 91% of SIPss increases due to nominations in excess of operational capacity; 51,332 Dths

SEGMENT RESTRICTIONS

·         STA 204 (Segment 204 BH) - through 100% of SOP increases due to operational concerns; 18,000 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 324,555 Dths

·         MLV 314 East (Segment 314 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 221,349 Dths

·         STA 315 (Segment 315 BH) - through approx 79% of SOP increases due to nominations in excess of operational capacity; 230,055 Dths

·         STA 317 (Segment 317 BH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 63,072 Dths

·         STA 321 (Segment 321 FH) - through approx 94% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 437,162 Dths

·         MLV 330 (Segment 324 FH) - through approx 27% of SOP increases due to nominations in excess of operational capacity; 36,322 Dths

·         MLV 336 East (Segment 336 FH) - through approx 46% of SOP increases due to nominations in excess of operational capacity; 13,060 Dths

·         Z5hc North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 188,129 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,822 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 76,053 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  05/02/2026 7:26:23PM Notice End Date/Time:  05/03/2026 9:00:00am
Post Date/Time:  5/2/2026 7:26:23 PM Notice ID: 401059
Reqrd Rsp:  1 Rsp Date:  05/02/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 05-03-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Sunday, May 03, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

ofo daily critical day 1 for over-deliveries into the system or under-takes out of the system for various parts of the system (see notice identifier 401023) for lmmas, lmpas and sas acting as balancing parties only

 

METER RESTRICTIONS

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 91% of SIPss increases due to nominations in excess of operational capacity; 51,332 Dths

SEGMENT RESTRICTIONS

·         STA 204 (Segment 204 BH) - through 100% of SOP increases due to operational concerns; 18,000 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 324,555 Dths

·         MLV 314 East (Segment 314 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 221,349 Dths

·         STA 315 (Segment 315 BH) - through approx 79% of SOP increases due to nominations in excess of operational capacity; 230,055 Dths

·         STA 317 (Segment 317 BH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 63,072 Dths

·         STA 321 (Segment 321 FH) - through approx 94% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 437,162 Dths

·         MLV 330 (Segment 324 FH) - through approx 27% of SOP increases due to nominations in excess of operational capacity; 36,322 Dths

·         MLV 336 East (Segment 336 FH) - through approx 46% of SOP increases due to nominations in excess of operational capacity; 13,060 Dths

·         Z5hc North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 188,129 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,822 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 76,053 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.