Tennessee Gas Pipeline Notice 401015

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/30/2026 6:50:58PM Notice End Date/Time:  05/01/2026 9:00:00am
Post Date/Time:  4/30/2026 6:50:58 PM Notice ID: 401015
Reqrd Rsp:  1 Rsp Date:  04/30/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 05-01-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Friday, May 01, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

none

 

METER RESTRICTIONS

·         ANR/TGP TGP Anr Greenville Intercon Delivery Meter (Pin 420941) - through 100% of SOP increases due to operational concerns; 10,000 Dths

·         ETNG/TGP East Lobelville Tn Perry Delivery Meter (Pin 420042) - through 100% of receipt SIPsp increases due to displacement gas unavailable for backhaul; 29,175 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through approx 99% of SOP increases due to operational concerns; 56,131 Dths

·         STA 32 (Segment 132 FH) - through approx 81% of IT increases due to scheduled maintenance and nominations in excess of operational capacity; 25,131 Dths

·         MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 14,640 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 14,000 Dths

·         STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 7,105 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 2,966 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 18,761 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 322,439 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 331,496 Dths

·         STA 315 (Segment 315 BH) - through approx 84% of SOP increases due to nominations in excess of operational capacity; 305,635 Dths

·         STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 80,687 Dths

·         STA 321 (Segment 321 FH) - through approx 90% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 390,749 Dths

·         MLV 330 (Segment 324 FH) - through approx 42% of SOP increases due to nominations in excess of operational capacity; 52,616 Dths

·         Z5hc North (Segment 299 FH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 210,752 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 283,709 Dths

·         STA 249 (Segment 249 FH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 83,416 Dths

·         MLV 256 East (Segment 256 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 12,109 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 92,589 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/30/2026 6:50:58PM Notice End Date/Time:  05/01/2026 9:00:00am
Post Date/Time:  4/30/2026 6:50:58 PM Notice ID: 401015
Reqrd Rsp:  1 Rsp Date:  04/30/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 05-01-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Friday, May 01, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

none

 

METER RESTRICTIONS

·         ANR/TGP TGP Anr Greenville Intercon Delivery Meter (Pin 420941) - through 100% of SOP increases due to operational concerns; 10,000 Dths

·         ETNG/TGP East Lobelville Tn Perry Delivery Meter (Pin 420042) - through 100% of receipt SIPsp increases due to displacement gas unavailable for backhaul; 29,175 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through approx 99% of SOP increases due to operational concerns; 56,131 Dths

·         STA 32 (Segment 132 FH) - through approx 81% of IT increases due to scheduled maintenance and nominations in excess of operational capacity; 25,131 Dths

·         MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 14,640 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 14,000 Dths

·         STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 7,105 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 2,966 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 18,761 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 322,439 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 331,496 Dths

·         STA 315 (Segment 315 BH) - through approx 84% of SOP increases due to nominations in excess of operational capacity; 305,635 Dths

·         STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 80,687 Dths

·         STA 321 (Segment 321 FH) - through approx 90% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 390,749 Dths

·         MLV 330 (Segment 324 FH) - through approx 42% of SOP increases due to nominations in excess of operational capacity; 52,616 Dths

·         Z5hc North (Segment 299 FH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 210,752 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 283,709 Dths

·         STA 249 (Segment 249 FH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 83,416 Dths

·         MLV 256 East (Segment 256 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 12,109 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 92,589 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.