| TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
| Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
| Notice Eff Date/Time: 04/22/2026 4:05:52PM | Notice End Date/Time: 04/23/2026 9:00:00am |
| Post Date/Time: 4/22/2026 4:05:52 PM | Notice ID: 400820 |
| Reqrd Rsp: 1 | Rsp Date: 04/22/2026 |
| Notice Stat Desc: INITIATE | Prior Notice: |
| Subject: RESTRICTIONS FOR 04-22-2026 ID2 |
Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, April 22, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 19,746 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 20,100 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,291 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 18,000 Dths
· STA 307 (Segment 307 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 334,730 Dths
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 211,247 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 193,616 Dths
· STA 317 (Segment 317 BH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 56,041 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 182,811 Dths
· MLV 330 (Segment 324 FH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 46,365 Dths
· STA 224 (Segment 224 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 62,804 Dths
· Z5hc North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 203,214 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 267,327 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 179,403 Dths
· MLV 256 East (Segment 256 FH) - through approx 86% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 53,114 Dths
· MLV 273 (Segment 284 FH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 77,784 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
| TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
| Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
| Notice Eff Date/Time: 04/22/2026 4:05:52PM | Notice End Date/Time: 04/23/2026 9:00:00am |
| Post Date/Time: 4/22/2026 4:05:52 PM | Notice ID: 400820 |
| Reqrd Rsp: 1 | Rsp Date: 04/22/2026 |
| Notice Stat Desc: INITIATE | Prior Notice: |
| Subject: RESTRICTIONS FOR 04-22-2026 ID2 |
Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, April 22, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 19,746 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 20,100 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,291 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 18,000 Dths
· STA 307 (Segment 307 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 334,730 Dths
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 211,247 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 193,616 Dths
· STA 317 (Segment 317 BH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 56,041 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 182,811 Dths
· MLV 330 (Segment 324 FH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 46,365 Dths
· STA 224 (Segment 224 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 62,804 Dths
· Z5hc North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 203,214 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 267,327 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 179,403 Dths
· MLV 256 East (Segment 256 FH) - through approx 86% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 53,114 Dths
· MLV 273 (Segment 284 FH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 77,784 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.