Tennessee Gas Pipeline Notice 398658

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  01/23/2026 3:13:04PM Notice End Date/Time:  01/24/2026 9:00:00am
Post Date/Time:  1/23/2026 3:13:04 PM Notice ID: 398658
Reqrd Rsp:  1 Rsp Date:  01/23/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 01-24-2026 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Saturday, January 24, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEM WIDE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

EXCESSIVE HOURLY TAKES WARNING SYSTEMWIDE

 

 

 

METER RESTRICTIONS

·         TGP/SNG Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through 100% of SIPss due to operational concerns; 34,944 Dths

·         Atmos KY/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through approx 28% of SIPss due to nominations in excess of operational capacity; 1,251 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 34% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 158,746 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP due to operational concerns; 4,350 Dths

·         STA 307 (Segment 307 BH) - through approx 97% of SOP due to nominations in excess of operational capacity; 347,731 Dths

·         MLV 314 East (Segment 314 BH) - through approx 64% of SOP due to nominations in excess of operational capacity; 334,484 Dths

·         STA 315 (Segment 315 BH) - through approx 55% of SOP due to nominations in excess of operational capacity; 343,704 Dths

·         STA 317 (Segment 317 BH) - through approx 25% of SOP due to nominations in excess of operational capacity; 76,516 Dths

·         STA 321 (Segment 321 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 1,007,558 Dths

·         STA 325 (Segment 324 FH) - through approx 56% of SOP due to nominations in excess of operational capacity; 173,562 Dths

·         MLV 330 (Segment 324 FH) - through approx 39% of SOP due to nominations in excess of operational capacity; 103,241 Dths

·         MLV 336 East (Segment 336 FH) - through 100% of SOP due to nominations in excess of operational capacity; 4,804 Dths

·         STA 224 (Segment 224 FH) - through 100% of SOP due to nominations in excess of operational capacity; 163,275 Dths

·         Z5hc North (Segment 299 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 530,357 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP due to nominations in excess of operational capacity; 648,212 Dths

·         STA 249 (Segment 249 FH) - through 100% of SOP due to nominations in excess of operational capacity; 420,085 Dths

·         STA 254 (Segment 249 FH) - through approx 86% of SOP due to nominations in excess of operational capacity; 102,766 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP due to operational concerns; 8,495 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:

o   Northern MA (460018)

o   Portland MA (460025)

o   Portland PA (460020)

o   Bear Creek PA (460017)

·         Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their  Maximum Daily Withdrawal (MDWQ) until further notice

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:

o   Pine Prairie Virtual (54628)

·         No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:

o   Northern MA (460018) IS-MA

o   Bear Creek PA (460017) IS-PA

·         No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  01/23/2026 3:13:04PM Notice End Date/Time:  01/24/2026 9:00:00am
Post Date/Time:  1/23/2026 3:13:04 PM Notice ID: 398658
Reqrd Rsp:  1 Rsp Date:  01/23/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 01-24-2026 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Saturday, January 24, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEM WIDE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

EXCESSIVE HOURLY TAKES WARNING SYSTEMWIDE

 

 

 

METER RESTRICTIONS

·         TGP/SNG Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through 100% of SIPss due to operational concerns; 34,944 Dths

·         Atmos KY/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through approx 28% of SIPss due to nominations in excess of operational capacity; 1,251 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 34% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 158,746 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP due to operational concerns; 4,350 Dths

·         STA 307 (Segment 307 BH) - through approx 97% of SOP due to nominations in excess of operational capacity; 347,731 Dths

·         MLV 314 East (Segment 314 BH) - through approx 64% of SOP due to nominations in excess of operational capacity; 334,484 Dths

·         STA 315 (Segment 315 BH) - through approx 55% of SOP due to nominations in excess of operational capacity; 343,704 Dths

·         STA 317 (Segment 317 BH) - through approx 25% of SOP due to nominations in excess of operational capacity; 76,516 Dths

·         STA 321 (Segment 321 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 1,007,558 Dths

·         STA 325 (Segment 324 FH) - through approx 56% of SOP due to nominations in excess of operational capacity; 173,562 Dths

·         MLV 330 (Segment 324 FH) - through approx 39% of SOP due to nominations in excess of operational capacity; 103,241 Dths

·         MLV 336 East (Segment 336 FH) - through 100% of SOP due to nominations in excess of operational capacity; 4,804 Dths

·         STA 224 (Segment 224 FH) - through 100% of SOP due to nominations in excess of operational capacity; 163,275 Dths

·         Z5hc North (Segment 299 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 530,357 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP due to nominations in excess of operational capacity; 648,212 Dths

·         STA 249 (Segment 249 FH) - through 100% of SOP due to nominations in excess of operational capacity; 420,085 Dths

·         STA 254 (Segment 249 FH) - through approx 86% of SOP due to nominations in excess of operational capacity; 102,766 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP due to operational concerns; 8,495 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:

o   Northern MA (460018)

o   Portland MA (460025)

o   Portland PA (460020)

o   Bear Creek PA (460017)

·         Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their  Maximum Daily Withdrawal (MDWQ) until further notice

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:

o   Pine Prairie Virtual (54628)

·         No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:

o   Northern MA (460018) IS-MA

o   Bear Creek PA (460017) IS-PA

·         No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.