Tennessee Gas Pipeline Notice 397208
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
| Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
| Notice Eff Date/Time: 11/21/2025 6:58:54PM | Notice End Date/Time: 11/22/2025 9:00:00am |
| Post Date/Time: 11/21/2025 6:58:54 PM | Notice ID: 397208 |
| Reqrd Rsp: 1 | Rsp Date: 11/21/2025 |
| Notice Stat Desc: INITIATE | Prior Notice: |
| Subject: RESTRICTIONS FOR 11-22-2025 EC |
Effective Evening Cycle (9:00) for the gas day of Saturday, November 22, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPss increases due to operational concerns; 25,033 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SIPss increases due to nominations in excess of operational capacity; 84,203 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to operational concerns; 1,337 Dths
· STA 860 South 500 Line (Segment 548 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 343,132 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 265,491 Dths
· STA 315 (Segment 315 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 200,950 Dths
· STA 317 (Segment 317 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 57,259 Dths
· STA 321 (Segment 321 FH) - through approx 73% of SOP increases due to nominations in excess of operational capacity; 294,866 Dths
· MLV 330 (Segment 324 FH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 240,527 Dths
· STA 224 (Segment 224 FH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 65,329 Dths
· Z5hc North (Segment 299 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 268,817 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 423,456 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 336,705 Dths
· STA 254 (Segment 249 FH) - through approx 64% of SOP increases due to nominations in excess of operational capacity; 85,133 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 155,869 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 147,494 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
| TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
| Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
| Notice Eff Date/Time: 11/21/2025 6:58:54PM | Notice End Date/Time: 11/22/2025 9:00:00am |
| Post Date/Time: 11/21/2025 6:58:54 PM | Notice ID: 397208 |
| Reqrd Rsp: 1 | Rsp Date: 11/21/2025 |
| Notice Stat Desc: INITIATE | Prior Notice: |
| Subject: RESTRICTIONS FOR 11-22-2025 EC |
Effective Evening Cycle (9:00) for the gas day of Saturday, November 22, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPss increases due to operational concerns; 25,033 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SIPss increases due to nominations in excess of operational capacity; 84,203 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to operational concerns; 1,337 Dths
· STA 860 South 500 Line (Segment 548 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 343,132 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 265,491 Dths
· STA 315 (Segment 315 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 200,950 Dths
· STA 317 (Segment 317 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 57,259 Dths
· STA 321 (Segment 321 FH) - through approx 73% of SOP increases due to nominations in excess of operational capacity; 294,866 Dths
· MLV 330 (Segment 324 FH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 240,527 Dths
· STA 224 (Segment 224 FH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 65,329 Dths
· Z5hc North (Segment 299 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 268,817 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 423,456 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 336,705 Dths
· STA 254 (Segment 249 FH) - through approx 64% of SOP increases due to nominations in excess of operational capacity; 85,133 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 155,869 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 147,494 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.