Tennessee Gas Pipeline Notice 396669

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  10/30/2025 2:49:28PM Notice End Date/Time:  10/31/2025 9:00:00am
Post Date/Time:  10/30/2025 2:49:28 PM Notice ID: 396669
Reqrd Rsp:  1 Rsp Date:  10/30/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  TGP Outage Impact Report
Notice Text:

 

 

 

 

 

 

 

-Primary impact restrictions may be necessary

 

 

 

TGP - Outage Impact Report

 

 

 

-Major impact restrictions may be necessary

 

 

Seven Day Forecast (updated 10/30/25)

 

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

Station / Seg

Est Nominal

Operating Capacity (Thousand Dth)

Monday

(11/3)

Tuesday

(11/4)

Wednesday

(11/5)

Thursday

(11/6)

Friday

(11/7)

Saturday

(11/8)

Sunday

(11/9)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409

(Donna Line) (segment 490 FH)

 

585

 

585

 

585

 

585

 

585

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

MLV 404-2 to MLV 405-2: Anomaly Remediation (M) (10/29/2025 - 11/3/2025)

MLV 403-2 to MLV 404-2: Anomaly Remediation (M) (11/3/2025 - 11/14/2025)

Station 9

(segment 109 BH)

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

Station 17

(segment 117 FH)

 

1,143

1130

(13)

1130

(13)

1130

(13)

1130

(13)

1130

(13)

1130

(13)

1130

(13)

MLV 17-1D to MLV 18-1: Anomaly Remediation (11/3/2025 - 11/21/2025)

Station 25

(segment 125 FH)

 

1,101

1087

(14)

1087

(14)

1087

(14)

1087

(14)

1087

(14)

1087

(14)

1087

(14)

Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 40 South

(segment 132 FH)

 

1,299

 

1,299

 

1286

(13)

 

1,299

 

1,299

 

1,299

 

1,299

 

1,299

MLV 32-3D to MLV 40-3S: Pig Runs - Maintenance (11/4/2025)

 

Station 47

(segment 143 FH)

 

 

1,354

 

 

1200

(154)

 

 

1200

(154)

 

 

1200

(154)

 

 

1200

(154)

 

 

1250

(104)

 

 

1250

(104)

 

 

1250

(104)

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-2A to MLV 48-2: Pipe Replacement (M) (11/1/2025 - 11/12/2025) Sta 47: Unit 1D - Flush & Clean Cooling Systems (11/3/2025 - 11/6/2025) Sta 47: Unit 2D - Flush & Clean Cooling Systems (11/3/2025 - 11/6/2025)

Sta 54: Unit 6B - Power Overhaul (10/1/2025 - 11/24/2025)

Sta 54: Unit 8B - Power Overhaul (10/1/2025 - 11/24/2025)

 

Station 63

(segment 163 FH)

 

 

1,287

 

 

1185

(102)

 

 

810

(477)

 

 

1187

(100)

 

 

810

(477)

 

 

1187

(100)

 

 

1187

(100)

 

 

1187

(100)

MLV 63-4D to MLV 71-4S: Pig Runs - EMAT 11/6/25 (11/6/2025) MLV 63-4D to MLV 71-4S: Pig Runs - MFL-C 11/4/25 (11/4/2025)

MLV 64-2 to MLV 65-2: Immediate Anomaly Remediation (10/8/2025 - 11/15/2025)

MLV 84-4 to MLV 85-4: Class Change Pipe Replacement (9/26/2025 -

11/3/2025)

Station 823

(segment 823 BH)

 

759

 

759

580

(179)

145

(614)

580

(179)

 

759

 

759

 

759

Sta 827 to Sta 823: Pig Run - Maintenance (M) (11/5/2025) Sta 834 to Sta 827: Maintenance Pig (M) (11/5/2025)

Station 827 (Alexandria): Station Recycle Valve (11/4/2025 - 11/6/2025)

Station 834

(segment 834 BH)

 

733

718

(15)

718

(15)

718

(15)

718

(15)

718

(15)

718

(15)

718

(15)

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

 

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

 

1,632

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)

MLV 548

(segment 542 BH)

 

1,771

1735

(36)

1735

(36)

1735

(36)

1735

(36)

1735

(36)

1735

(36)

1735

(36)

Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/5/2025)

 

Station 860

(segment 548 BH)

 

 

1,697

 

1681

(16)

 

1681

(16)

 

1585

(112)

 

980

(717)

 

1681

(16)

 

1681

(16)

 

1681

(16)

MLV 546-1 to MLV 542-1: Pig Runs - Maintenance (11/5/2025) MLV 546-2 to MLV 542-2: Pig Runs - Maintenance (11/6/2025) MLV 546-3 to MLV 544-3: Pig Runs - Maintenance (11/4/2025) Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025)

Sta 555: Unit 1A - Engine Maintenance (11/3/2025 - 11/7/2025)

 

 

 

Station 860 North (Segment 860 BH)

 

 

 

 

 

2,028

 

 

 

 

1920

(108)

 

 

 

 

1920

(108)

 

 

 

 

 

2,028

 

 

 

 

1930

(98)

 

 

 

 

1935

(93)

 

 

 

 

1935

(93)

 

 

 

 

1935

(93)

MLV 861-1 to MLV 862-1: Install New 30" Valve 861-1A (11/6/2025 - 11/12/2025)

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025)

Sta 860: Unit 1C - 4K Turbine Water Wash (11/3/2025 - 11/4/2025) Sta 860: Unit 1C - Engine Inspection/Condition Assessment (11/3/2025 -

11/4/2025)

Sta 860: Unit 2C - 4K Turbine Water Wash (11/5/2025 - 11/6/2025) Sta 860: Unit 2C - Engine Inspection/Condition Assessment (11/5/2025 -

11/6/2025)

 

 

 

 

Station 110

(segment 187 BH)

(south thru Kentucky)

 

 

 

 

 

 

2,775

 

 

 

 

 

 

2550

(225)

 

 

 

 

 

 

2175

(600)

 

 

 

 

 

 

2550

(225)

 

 

 

 

 

 

2175

(600)

 

 

 

 

 

 

2550

(225)

 

 

 

 

 

 

2560

(215)

 

 

 

 

 

 

2560

(215)

MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement (M) (11/1/2025 - 11/30/2025)

MLV 87-4 to MLV 96-4: Pig Runs - Caliper 11/6/25 (M) (11/6/2025) MLV 87-4 to MLV 96-4: Pig Runs - Cleaning / Gauge 11/4/25 (M) (11/4/2025)

MLV 90-3 to MLV 91-3: HDD River Crossing Replacement (10/23/2025 - 11/19/2025)

MLV 96-4 to MLV 97-4: Anomaly Remediation (9/25/2025 - 11/14/2025) Sta 106: Unit 1C - Replace Power Cylinder Bearing #7 (4/14/2025 - 11/14/2025)

Sta 87: Unit 2E - Turbocharger Replacement (10/27/2025 - 11/21/2025) Sta 87: Unit 8C - Install Governor (11/3/2025 - 11/7/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)

Station 114

(segment 114 BH)

 

948

 

948

 

948

 

948

 

948

 

948

 

948

 

948

 

Station 204

(Segment 204 BH)

 

1,895

 

1732

(163)

 

1432

(463)

 

1732

(163)

 

1432

(463)

 

1732

(163)

 

1732

(163)

 

1732

(163)

MLV 209-4 to MLV 204-4: Pig Runs - Cal & IMU 11/04/25 (M) (11/4/2025) MLV 209-4 to MLV 204-4: Pig Runs - MFL-A 11/06/25 (M) (11/6/2025)

MLV 213-2A to MLV 214-2: Special Permit Replacement (10/9/2025 -

11/19/2025)

Station 245

(segment 245 FH)

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

1,045

 

1,045

 

970

(75)

 

970

(75)

 

1,045

 

1,045

 

1,045

Sta 261 Agawam: Unit 5A - Change Valve (M) (11/5/2025 - 11/6/2025)


 

 

 

 

 

 

 

-Primary impact restrictions may be necessary

 

 

 

TGP - Outage Impact Report

 

 

 

-Major impact restrictions may be necessary

 

 

Seven Day Forecast (updated 10/30/25)

 

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

Station / Seg

Est Nominal

Operating Capacity (Thousand Dth)

Monday

(11/3)

Tuesday

(11/4)

Wednesday

(11/5)

Thursday

(11/6)

Friday

(11/7)

Saturday

(11/8)

Sunday

(11/9)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 267 South (segment 266

FH)

 

503

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

Sta 267: Bldg A Controls Upgrade (9/2/2025 - 11/26/2025)

Station 307

(segment 307 BH)

 

1,202

1145

(57)

1145

(57)

1145

(57)

1145

(57)

1145

(57)

 

1,202

 

1,202

Sta 307: Unit 2A - Engine Maintenance (11/3/2025 - 11/7/2025)

Station 315

(segment 315 BH)

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

1635

(250)

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

Sta 325: Unit 3A - Engine ESD Valve (10/2/2025 - 11/3/2025) Sta 325: Units 4A - Vibration (9/8/2025 - 11/3/2025)

Station 405 HC Line (segment 299

FH)

 

827

 

827

 

827

 

827

 

827

 

827

 

827

 

827

 

Station 224

(segment 224 FH)

 

399

205

(194)

205

(194)

205

(194)

205

(194)

205

(194)

 

399

 

399

Sta 229: Automation Upgrade & Maintenance (M) (8/11/2025 - 11/7/2025)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

November 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(11/3 - 11/9)

Week 2

(11/10 - 11/16)

Week 3

(11/17 - 11/23)

Week 4

(11/24 - 11/30)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409A (Alamo) (segment 492

FH)

 

295

 

 

295

 

145

(150)

 

295

MLV 409A-901 to MLV 409A-902: Pig Run - Cleaning 11/18/25 (M) (11/18/2025) MLV 409A-901 to MLV 409A-902: Pig Run - MFL-A 11/19/25 (M) (11/19/2025)

Station 409 (Donna Line) (segment 490

FH)

 

585

 

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

125

(313)

 

438

 

438

MLV 403-2 to MLV 404-2: Anomaly Remediation (M) (11/3/2025 - 11/14/2025)

MLV 4

(segment 101 FH)

 

1,033

 

 

1,033

 

1,033

 

1,033

MLV 1-2BL to MLV 1-2A: GCX Expansion Hot Tap/Tie in (M) (11/18/2025 - 11/21/2025)

Station 9

(segment 109 BH)

 

1,066

 

 

1,066

 

1,066

 

1,066

 

Station 17

(segment 117 FH)

 

1,143

 

1130

(13)

1130

(13)

 

1,143

MLV 17-1D to MLV 18-1: Anomaly Remediation (11/3/2025 - 11/21/2025)

Station 25

(segment 125 FH)

 

1,101

 

1087

(14)

1087

(14)

1087

(14)

MLV 26-1 Relocation: Highway 59 Widening (11/11/2025 - 12/10/2025) Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 40 KN South (segment 501

FH)

 

285

 

 

100

(185)

 

285

 

285

Sta 500-1 to Sta 823 (MLV 507-1): Pig Run - Maintenance (M) (11/11/2025)

 

 

Station 47

(segment 143 FH)

 

 

 

1,354

 

 

 

1250

(104)

 

 

890

(464)

 

 

890

(464)

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-2A to MLV 48-2: Pipe Replacement (M) (11/1/2025 - 11/12/2025) MLV 47-3A to MLV 48-3: Pipe Replacement (11/25/2025 - 12/10/2025) MLV 47-4A to MLV 48-4: Pipe Replacement (M) (11/13/2025 - 11/24/2025)

MLV 53-3BR to MLV 54-3BL: HydroTest (11/19/2025 - 12/16/2025)

Sta 54: Unit 6B - Power Overhaul (10/1/2025 - 11/24/2025) Sta 54: Unit 8B - Power Overhaul (10/1/2025 - 11/24/2025)

 

 

Station 63

(segment 163 FH)

 

 

 

1,287

 

 

 

1185

(102)

 

 

1135

(152)

 

 

1135

(152)

MLV 64-2 to MLV 65-2: Immediate Anomaly Remediation (10/8/2025 - 11/15/2025)

MLV 65-2 to MLV 66-2: Immediate Anomaly Remediation (11/17/2025 - 11/30/2025)

MLV 66-2 to MLV 67-2: Immediate Anomaly Remediation (11/17/2025 - 11/30/2025)

MLV 71-1D to MLV 77-1A: Pig Re-Runs - MDS 11/12/25 (11/12/2025)

Station 823

(segment 823 BH)

 

759

 

 

759

 

759

 

759

 

Station 834

(segment 834 BH)

 

733

 

718

(15)

718

(15)

718

(15)

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

 

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

1,632

 

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)

Station 542

(segment 539 BH)

 

1,905

 

1865

(40)

 

1,905

 

1,905

Sta 542: Unit 1B - Safety Device Testing (11/10/2025 - 11/14/2025)

MLV 548

(segment 542 BH)

 

1,771

 

1735

(36)

1735

(36)

1735

(36)

Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/5/2025)

Station 860

(segment 548 BH)

 

1,697

 

1681

(16)

1681

(16)

1681

(16)

Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025)

Station 860 North (Segment 860 BH)

 

 

2,028

 

 

1800

(228)

 

 

2,028

 

 

2,028

MLV 861-1 to MLV 862-1: Install New 30" Valve 861-1A (11/6/2025 - 11/12/2025)

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025) Sta. 860: A Building - replace discharge valves (11/11/2025 - 11/12/2025)


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

November 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(11/3 - 11/9)

Week 2

(11/10 - 11/16)

Week 3

(11/17 - 11/23)

Week 4

(11/24 - 11/30)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

 

 

 

Station 110

(segment 187 BH)

(south thru Kentucky)

 

 

 

 

 

 

2,775

 

 

 

 

 

 

 

2175

(600)

 

 

 

 

 

 

2540

(235)

 

 

 

 

 

 

2625

(150)

MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement (M) (11/1/2025 - 11/30/2025)

MLV 87-4 to MLV 96-4: Pig Runs - AFD Combo 11/11/25 (M) (11/11/2025) MLV 87-4 to MLV 96-4: Pig Runs - EMAT 11/13/25 (M) (11/13/2025)

MLV 90-3 to MLV 91-3: HDD River Crossing Replacement (10/23/2025 - 11/19/2025)

MLV 96-4 to MLV 97-4: Anomaly Remediation (9/25/2025 - 11/14/2025) Sta 106 Clay City: Upgrade B Building Jacket Water System (11/14/2025 - 12/5/2025)

Sta 106: Unit 1C - Replace Power Cylinder Bearing #7 (4/14/2025 - 11/14/2025) Sta 87: Unit 2E - Turbocharger Replacement (10/27/2025 - 11/21/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)

Station 114

(segment 114 BH)

 

948

 

 

948

 

948

 

948

 

 

 

 

Station 204

(Segment 204 BH)

 

 

 

 

1,895

 

 

 

 

1459

(436)

 

 

 

1419

(476)

 

 

 

 

1,895

MLV 213-2A to MLV 214-2: Special Permit Replacement (10/9/2025 - 11/19/2025)

MLV 219-4 to MLV 214-4: Pig Run - Cleaning/Gauge 11/11/25 (M) (11/11/2025) MLV 219-4 to MLV 214-4: Pig Run - EMAT 11/20/25 (M) (11/20/2025)

MLV 219-4 to MLV 214-4: Pig Run - IMU/Caliper 11/13/25 (M) (11/13/2025) MLV 219-4 to MLV 214-4: Pig Run - MFL-C 11/18/25 (M) (11/18/2025)

Sta 209: Unit 12A - P3L pull piston and inspect rings and cylinder (11/10/2025 - 11/13/2025)

Station 245

(segment 245 FH)

 

1,063

 

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

 

1,045

 

1,045

 

1,045

 

Station 267 South (segment 266

FH)

 

503

 

 

346

(157)

 

346

(157)

 

346

(157)

Sta 267: Bldg A Controls Upgrade (9/2/2025 - 11/26/2025)

Station 307

(segment 307 BH)

 

1,202

 

 

1,202

 

1,202

 

1,202

 

Station 315

(segment 315 BH)

 

1,915

 

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

 

 

1,885

 

1,885

 

1,885

 

Station 405 HC Line (segment 299

FH)

 

827

 

 

827

 

827

 

827

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

December 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(12/1 - 12/7)

Week 2

(12/8 - 12/14)

Week 3

(12/15 - 12/21)

Week 4

(12/22 - 12/28)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

585

 

585

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

438

 

438

 

438

 

438

 

Station 9

(segment 109 BH)

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

Station 25

(segment 125 FH)

 

1,101

 

1087

(14)

 

1075

(26)

 

1075

(26)

 

1075

(26)

MLV 26-1 Relocation: Highway 59 Widening (11/11/2025 - 12/10/2025) MLV 26-1 to MLV 27-1: Install Road Casing (12/6/2025 - 1/19/2026) MLV 26-2 Relocation: Highway 59 Widening (12/11/2025 - 1/19/2026)

Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 40 South

(segment 132 FH)

 

1,299

 

910

(389)

 

1,299

 

1,299

 

1,299

MLV 32-2D TO MLV 40-2S: Pig Runs - Maintenance (12/2/2025)

Station 47

(segment 143 FH)

 

1,354

895

(459)

895

(459)

950

(404)

1349

(5)

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-3A to MLV 48-3: Pipe Replacement (11/25/2025 - 12/10/2025)

MLV 53-3BR to MLV 54-3BL: HydroTest (11/19/2025 - 12/16/2025)

Station 63

(segment 163 FH)

 

1,287

 

1,287

 

1,287

 

1,287

 

1,287

 

Station 823

(segment 823 BH)

 

759

 

759

 

759

 

759

 

759

 

Station 834

(segment 834 BH)

 

733

718

(15)

718

(15)

718

(15)

718

(15)

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

Station 847

(segment 847 BH)

 

338

200

(138)

200

(138)

 

338

 

338

MLV 856-1 to MLV 860-1: Pig Runs - Cal / IMU 12/9/25 (12/9/2025)

MLV 856-1 to MLV 860-1: Pig Runs - Cleaning / Gauge 12/4/25 (12/4/2025) MLV 856-1 to MLV 860-1: Pig Runs - MFL-C 12/11/25 (12/11/2025)

 

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

1,632

 

 

 

 

1294

(338)

 

 

 

 

1425

(207)

 

 

 

 

1425

(207)

 

 

 

 

1425

(207)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)

MLV 548

(segment 542 BH)

 

1,771

1735

(36)

1736

(35)

 

1,771

 

1,771

Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/5/2025)

Station 860

(segment 548 BH)

 

1,697

1681

(16)

1681

(16)

1681

(16)

 

1,697

Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025) Sta 550: Unit 3A - Turbocharger Exchange (12/8/2025 - 12/19/2025)

Station 860 North (Segment 860

BH)

 

2,028

 

2000

(28)

 

2000

(28)

 

2000

(28)

 

2000

(28)

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025)

Station 110

(segment 187 BH)

(south thru

Kentucky)

 

 

2,775

 

2600

(175)

 

2600

(175)

 

2645

(130)

 

2645

(130)

Sta 106 Clay City: Upgrade B Building Jacket Water System (11/14/2025 - 12/5/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026) Sta 96: Unit 1D - Compressor Valves (12/1/2025 - 12/12/2025)

Station 114

(segment 114 BH)

 

948

 

948

 

948

 

948

 

948

 

Station 204

(Segment 204 BH)

 

1,895

 

1,895

 

1,895

1722

(173)

 

1,895

MLV 204-2 to MLV 200-2: Pig Runs - EMAT 12/18/25 (M) (12/18/2025) MLV 204-2 to MLV 200-2: Pig Runs - MFL-C 12/16/25 (M) (12/16/2025)

Station 245

(segment 245 FH)

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

1,045

 

1,045

 

1,045

 

1,045

 


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

December 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(12/1 - 12/7)

Week 2

(12/8 - 12/14)

Week 3

(12/15 - 12/21)

Week 4

(12/22 - 12/28)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 307

(segment 307 BH)

 

1,202

 

1,202

 

1,202

 

1,202

 

1,202

 

Station 315

(segment 315 BH)

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

Station 405 HC Line (segment 299

FH)

 

827

 

827

 

827

 

827

 

827

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Primary impact restrictions may be necessary

 

 

TGP - Outage Impact Report

 

 

-Major impact restrictions may be necessary

 

January 2026 (updated 10/30/25)

 

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(12/29 - 1/4)

Week 2

(1/5 - 1/11)

Week 3

(1/12 - 1/18)

Week 4

(1/19 - 1/25)

Week 5

(1/26 - 2/1)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

585

 

585

 

585

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

438

 

438

 

438

 

438

 

438

 

Station 9

(segment 109 BH)

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

Station 25

(segment 125 FH)

 

1,101

 

1075

(26)

 

1075

(26)

 

1075

(26)

 

855

(246)

 

855

(246)

MLV 26-1 to MLV 27-1: Install Road Casing (12/6/2025 - 1/19/2026) MLV 26-2 Relocation: Highway 59 Widening (12/11/2025 - 1/19/2026) MLV 26-3 Relocation: Highway 59 Widening (M) (1/20/2026 - 2/19/2026)

Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 47

(segment 143 FH)

 

1,354

1349

(5)

 

1,354

 

1,354

 

1,354

 

1,354

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025)

Station 63

(segment 163 FH)

 

1,287

 

1,287

 

1,287

 

1,287

 

1,287

 

1,287

 

Station 823

(segment 823 BH)

 

759

 

759

 

759

 

759

 

759

 

759

 

Station 834

(segment 834 BH)

 

733

718

(15)

 

733

 

733

 

733

 

733

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

1,632

 

 

 

1425

(207)

 

 

 

1610

(22)

 

 

 

1610

(22)

 

 

 

1610

(22)

 

 

 

1610

(22)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

MLV 548

(segment 542 BH)

 

1,771

 

1,771

 

1,771

 

1,771

 

1,771

 

1,771

 

Station 860

(segment 548 BH)

 

1,697

 

1,697

 

1,697

 

1,697

 

1,697

 

1,697

 

Station 860 North (Segment 860

BH)

 

2,028

 

2000

(28)

 

2,028

 

2,028

 

2,028

 

2,028

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025)

Station 110

(segment 187 BH)

(south thru

Kentucky)

 

 

2,775

 

2535

(240)

 

2645

(130)

 

2645

(130)

 

2645

(130)

 

2645

(130)

Sta 871: Unit 1A - 3Q Engine Inspection (12/31/2025) Sta 871: Unit 2A - 3Q Engine Inspection (12/31/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)

Station 114

(segment 114 BH)

 

948

 

948

 

948

 

948

 

948

 

948

 

Station 204

(Segment 204 BH)

 

1,895

 

1,895

 

1,895

 

1,895

 

1,895

 

1,895

 

Station 245

(segment 245 FH)

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

1,045

 

1,045

 

1,045

 

1,045

 

1,045

 

Station 307

(segment 307 BH)

 

1,202

 

1,202

 

1,202

 

1,202

 

1,202

 

1,202

 

Station 315

(segment 315 BH)

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

Station 405 HC Line (segment 299

FH)

 

827

 

827

 

827

 

827

 

827

 

827

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  10/30/2025 2:49:28PM Notice End Date/Time:  10/31/2025 9:00:00am
Post Date/Time:  10/30/2025 2:49:28 PM Notice ID: 396669
Reqrd Rsp:  1 Rsp Date:  10/30/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  TGP Outage Impact Report
Notice Text:

 

 

 

 

 

 

 

-Primary impact restrictions may be necessary

 

 

 

TGP - Outage Impact Report

 

 

 

-Major impact restrictions may be necessary

 

 

Seven Day Forecast (updated 10/30/25)

 

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

Station / Seg

Est Nominal

Operating Capacity (Thousand Dth)

Monday

(11/3)

Tuesday

(11/4)

Wednesday

(11/5)

Thursday

(11/6)

Friday

(11/7)

Saturday

(11/8)

Sunday

(11/9)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409

(Donna Line) (segment 490 FH)

 

585

 

585

 

585

 

585

 

585

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

 

125

(313)

MLV 404-2 to MLV 405-2: Anomaly Remediation (M) (10/29/2025 - 11/3/2025)

MLV 403-2 to MLV 404-2: Anomaly Remediation (M) (11/3/2025 - 11/14/2025)

Station 9

(segment 109 BH)

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

Station 17

(segment 117 FH)

 

1,143

1130

(13)

1130

(13)

1130

(13)

1130

(13)

1130

(13)

1130

(13)

1130

(13)

MLV 17-1D to MLV 18-1: Anomaly Remediation (11/3/2025 - 11/21/2025)

Station 25

(segment 125 FH)

 

1,101

1087

(14)

1087

(14)

1087

(14)

1087

(14)

1087

(14)

1087

(14)

1087

(14)

Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 40 South

(segment 132 FH)

 

1,299

 

1,299

 

1286

(13)

 

1,299

 

1,299

 

1,299

 

1,299

 

1,299

MLV 32-3D to MLV 40-3S: Pig Runs - Maintenance (11/4/2025)

 

Station 47

(segment 143 FH)

 

 

1,354

 

 

1200

(154)

 

 

1200

(154)

 

 

1200

(154)

 

 

1200

(154)

 

 

1250

(104)

 

 

1250

(104)

 

 

1250

(104)

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-2A to MLV 48-2: Pipe Replacement (M) (11/1/2025 - 11/12/2025) Sta 47: Unit 1D - Flush & Clean Cooling Systems (11/3/2025 - 11/6/2025) Sta 47: Unit 2D - Flush & Clean Cooling Systems (11/3/2025 - 11/6/2025)

Sta 54: Unit 6B - Power Overhaul (10/1/2025 - 11/24/2025)

Sta 54: Unit 8B - Power Overhaul (10/1/2025 - 11/24/2025)

 

Station 63

(segment 163 FH)

 

 

1,287

 

 

1185

(102)

 

 

810

(477)

 

 

1187

(100)

 

 

810

(477)

 

 

1187

(100)

 

 

1187

(100)

 

 

1187

(100)

MLV 63-4D to MLV 71-4S: Pig Runs - EMAT 11/6/25 (11/6/2025) MLV 63-4D to MLV 71-4S: Pig Runs - MFL-C 11/4/25 (11/4/2025)

MLV 64-2 to MLV 65-2: Immediate Anomaly Remediation (10/8/2025 - 11/15/2025)

MLV 84-4 to MLV 85-4: Class Change Pipe Replacement (9/26/2025 -

11/3/2025)

Station 823

(segment 823 BH)

 

759

 

759

580

(179)

145

(614)

580

(179)

 

759

 

759

 

759

Sta 827 to Sta 823: Pig Run - Maintenance (M) (11/5/2025) Sta 834 to Sta 827: Maintenance Pig (M) (11/5/2025)

Station 827 (Alexandria): Station Recycle Valve (11/4/2025 - 11/6/2025)

Station 834

(segment 834 BH)

 

733

718

(15)

718

(15)

718

(15)

718

(15)

718

(15)

718

(15)

718

(15)

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

 

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

 

1,632

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)

MLV 548

(segment 542 BH)

 

1,771

1735

(36)

1735

(36)

1735

(36)

1735

(36)

1735

(36)

1735

(36)

1735

(36)

Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/5/2025)

 

Station 860

(segment 548 BH)

 

 

1,697

 

1681

(16)

 

1681

(16)

 

1585

(112)

 

980

(717)

 

1681

(16)

 

1681

(16)

 

1681

(16)

MLV 546-1 to MLV 542-1: Pig Runs - Maintenance (11/5/2025) MLV 546-2 to MLV 542-2: Pig Runs - Maintenance (11/6/2025) MLV 546-3 to MLV 544-3: Pig Runs - Maintenance (11/4/2025) Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025)

Sta 555: Unit 1A - Engine Maintenance (11/3/2025 - 11/7/2025)

 

 

 

Station 860 North (Segment 860 BH)

 

 

 

 

 

2,028

 

 

 

 

1920

(108)

 

 

 

 

1920

(108)

 

 

 

 

 

2,028

 

 

 

 

1930

(98)

 

 

 

 

1935

(93)

 

 

 

 

1935

(93)

 

 

 

 

1935

(93)

MLV 861-1 to MLV 862-1: Install New 30" Valve 861-1A (11/6/2025 - 11/12/2025)

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025)

Sta 860: Unit 1C - 4K Turbine Water Wash (11/3/2025 - 11/4/2025) Sta 860: Unit 1C - Engine Inspection/Condition Assessment (11/3/2025 -

11/4/2025)

Sta 860: Unit 2C - 4K Turbine Water Wash (11/5/2025 - 11/6/2025) Sta 860: Unit 2C - Engine Inspection/Condition Assessment (11/5/2025 -

11/6/2025)

 

 

 

 

Station 110

(segment 187 BH)

(south thru Kentucky)

 

 

 

 

 

 

2,775

 

 

 

 

 

 

2550

(225)

 

 

 

 

 

 

2175

(600)

 

 

 

 

 

 

2550

(225)

 

 

 

 

 

 

2175

(600)

 

 

 

 

 

 

2550

(225)

 

 

 

 

 

 

2560

(215)

 

 

 

 

 

 

2560

(215)

MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement (M) (11/1/2025 - 11/30/2025)

MLV 87-4 to MLV 96-4: Pig Runs - Caliper 11/6/25 (M) (11/6/2025) MLV 87-4 to MLV 96-4: Pig Runs - Cleaning / Gauge 11/4/25 (M) (11/4/2025)

MLV 90-3 to MLV 91-3: HDD River Crossing Replacement (10/23/2025 - 11/19/2025)

MLV 96-4 to MLV 97-4: Anomaly Remediation (9/25/2025 - 11/14/2025) Sta 106: Unit 1C - Replace Power Cylinder Bearing #7 (4/14/2025 - 11/14/2025)

Sta 87: Unit 2E - Turbocharger Replacement (10/27/2025 - 11/21/2025) Sta 87: Unit 8C - Install Governor (11/3/2025 - 11/7/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)

Station 114

(segment 114 BH)

 

948

 

948

 

948

 

948

 

948

 

948

 

948

 

948

 

Station 204

(Segment 204 BH)

 

1,895

 

1732

(163)

 

1432

(463)

 

1732

(163)

 

1432

(463)

 

1732

(163)

 

1732

(163)

 

1732

(163)

MLV 209-4 to MLV 204-4: Pig Runs - Cal & IMU 11/04/25 (M) (11/4/2025) MLV 209-4 to MLV 204-4: Pig Runs - MFL-A 11/06/25 (M) (11/6/2025)

MLV 213-2A to MLV 214-2: Special Permit Replacement (10/9/2025 -

11/19/2025)

Station 245

(segment 245 FH)

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

1,045

 

1,045

 

970

(75)

 

970

(75)

 

1,045

 

1,045

 

1,045

Sta 261 Agawam: Unit 5A - Change Valve (M) (11/5/2025 - 11/6/2025)


 

 

 

 

 

 

 

-Primary impact restrictions may be necessary

 

 

 

TGP - Outage Impact Report

 

 

 

-Major impact restrictions may be necessary

 

 

Seven Day Forecast (updated 10/30/25)

 

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

Station / Seg

Est Nominal

Operating Capacity (Thousand Dth)

Monday

(11/3)

Tuesday

(11/4)

Wednesday

(11/5)

Thursday

(11/6)

Friday

(11/7)

Saturday

(11/8)

Sunday

(11/9)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 267 South (segment 266

FH)

 

503

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

 

346

(157)

Sta 267: Bldg A Controls Upgrade (9/2/2025 - 11/26/2025)

Station 307

(segment 307 BH)

 

1,202

1145

(57)

1145

(57)

1145

(57)

1145

(57)

1145

(57)

 

1,202

 

1,202

Sta 307: Unit 2A - Engine Maintenance (11/3/2025 - 11/7/2025)

Station 315

(segment 315 BH)

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

1635

(250)

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

Sta 325: Unit 3A - Engine ESD Valve (10/2/2025 - 11/3/2025) Sta 325: Units 4A - Vibration (9/8/2025 - 11/3/2025)

Station 405 HC Line (segment 299

FH)

 

827

 

827

 

827

 

827

 

827

 

827

 

827

 

827

 

Station 224

(segment 224 FH)

 

399

205

(194)

205

(194)

205

(194)

205

(194)

205

(194)

 

399

 

399

Sta 229: Automation Upgrade & Maintenance (M) (8/11/2025 - 11/7/2025)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

November 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(11/3 - 11/9)

Week 2

(11/10 - 11/16)

Week 3

(11/17 - 11/23)

Week 4

(11/24 - 11/30)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409A (Alamo) (segment 492

FH)

 

295

 

 

295

 

145

(150)

 

295

MLV 409A-901 to MLV 409A-902: Pig Run - Cleaning 11/18/25 (M) (11/18/2025) MLV 409A-901 to MLV 409A-902: Pig Run - MFL-A 11/19/25 (M) (11/19/2025)

Station 409 (Donna Line) (segment 490

FH)

 

585

 

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

125

(313)

 

438

 

438

MLV 403-2 to MLV 404-2: Anomaly Remediation (M) (11/3/2025 - 11/14/2025)

MLV 4

(segment 101 FH)

 

1,033

 

 

1,033

 

1,033

 

1,033

MLV 1-2BL to MLV 1-2A: GCX Expansion Hot Tap/Tie in (M) (11/18/2025 - 11/21/2025)

Station 9

(segment 109 BH)

 

1,066

 

 

1,066

 

1,066

 

1,066

 

Station 17

(segment 117 FH)

 

1,143

 

1130

(13)

1130

(13)

 

1,143

MLV 17-1D to MLV 18-1: Anomaly Remediation (11/3/2025 - 11/21/2025)

Station 25

(segment 125 FH)

 

1,101

 

1087

(14)

1087

(14)

1087

(14)

MLV 26-1 Relocation: Highway 59 Widening (11/11/2025 - 12/10/2025) Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 40 KN South (segment 501

FH)

 

285

 

 

100

(185)

 

285

 

285

Sta 500-1 to Sta 823 (MLV 507-1): Pig Run - Maintenance (M) (11/11/2025)

 

 

Station 47

(segment 143 FH)

 

 

 

1,354

 

 

 

1250

(104)

 

 

890

(464)

 

 

890

(464)

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-2A to MLV 48-2: Pipe Replacement (M) (11/1/2025 - 11/12/2025) MLV 47-3A to MLV 48-3: Pipe Replacement (11/25/2025 - 12/10/2025) MLV 47-4A to MLV 48-4: Pipe Replacement (M) (11/13/2025 - 11/24/2025)

MLV 53-3BR to MLV 54-3BL: HydroTest (11/19/2025 - 12/16/2025)

Sta 54: Unit 6B - Power Overhaul (10/1/2025 - 11/24/2025) Sta 54: Unit 8B - Power Overhaul (10/1/2025 - 11/24/2025)

 

 

Station 63

(segment 163 FH)

 

 

 

1,287

 

 

 

1185

(102)

 

 

1135

(152)

 

 

1135

(152)

MLV 64-2 to MLV 65-2: Immediate Anomaly Remediation (10/8/2025 - 11/15/2025)

MLV 65-2 to MLV 66-2: Immediate Anomaly Remediation (11/17/2025 - 11/30/2025)

MLV 66-2 to MLV 67-2: Immediate Anomaly Remediation (11/17/2025 - 11/30/2025)

MLV 71-1D to MLV 77-1A: Pig Re-Runs - MDS 11/12/25 (11/12/2025)

Station 823

(segment 823 BH)

 

759

 

 

759

 

759

 

759

 

Station 834

(segment 834 BH)

 

733

 

718

(15)

718

(15)

718

(15)

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

 

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

1,632

 

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

 

 

 

 

1294

(338)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)

Station 542

(segment 539 BH)

 

1,905

 

1865

(40)

 

1,905

 

1,905

Sta 542: Unit 1B - Safety Device Testing (11/10/2025 - 11/14/2025)

MLV 548

(segment 542 BH)

 

1,771

 

1735

(36)

1735

(36)

1735

(36)

Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/5/2025)

Station 860

(segment 548 BH)

 

1,697

 

1681

(16)

1681

(16)

1681

(16)

Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025)

Station 860 North (Segment 860 BH)

 

 

2,028

 

 

1800

(228)

 

 

2,028

 

 

2,028

MLV 861-1 to MLV 862-1: Install New 30" Valve 861-1A (11/6/2025 - 11/12/2025)

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025) Sta. 860: A Building - replace discharge valves (11/11/2025 - 11/12/2025)


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

November 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(11/3 - 11/9)

Week 2

(11/10 - 11/16)

Week 3

(11/17 - 11/23)

Week 4

(11/24 - 11/30)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

 

 

 

Station 110

(segment 187 BH)

(south thru Kentucky)

 

 

 

 

 

 

2,775

 

 

 

 

 

 

 

2175

(600)

 

 

 

 

 

 

2540

(235)

 

 

 

 

 

 

2625

(150)

MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement (M) (11/1/2025 - 11/30/2025)

MLV 87-4 to MLV 96-4: Pig Runs - AFD Combo 11/11/25 (M) (11/11/2025) MLV 87-4 to MLV 96-4: Pig Runs - EMAT 11/13/25 (M) (11/13/2025)

MLV 90-3 to MLV 91-3: HDD River Crossing Replacement (10/23/2025 - 11/19/2025)

MLV 96-4 to MLV 97-4: Anomaly Remediation (9/25/2025 - 11/14/2025) Sta 106 Clay City: Upgrade B Building Jacket Water System (11/14/2025 - 12/5/2025)

Sta 106: Unit 1C - Replace Power Cylinder Bearing #7 (4/14/2025 - 11/14/2025) Sta 87: Unit 2E - Turbocharger Replacement (10/27/2025 - 11/21/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)

Station 114

(segment 114 BH)

 

948

 

 

948

 

948

 

948

 

 

 

 

Station 204

(Segment 204 BH)

 

 

 

 

1,895

 

 

 

 

1459

(436)

 

 

 

1419

(476)

 

 

 

 

1,895

MLV 213-2A to MLV 214-2: Special Permit Replacement (10/9/2025 - 11/19/2025)

MLV 219-4 to MLV 214-4: Pig Run - Cleaning/Gauge 11/11/25 (M) (11/11/2025) MLV 219-4 to MLV 214-4: Pig Run - EMAT 11/20/25 (M) (11/20/2025)

MLV 219-4 to MLV 214-4: Pig Run - IMU/Caliper 11/13/25 (M) (11/13/2025) MLV 219-4 to MLV 214-4: Pig Run - MFL-C 11/18/25 (M) (11/18/2025)

Sta 209: Unit 12A - P3L pull piston and inspect rings and cylinder (11/10/2025 - 11/13/2025)

Station 245

(segment 245 FH)

 

1,063

 

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

 

1,045

 

1,045

 

1,045

 

Station 267 South (segment 266

FH)

 

503

 

 

346

(157)

 

346

(157)

 

346

(157)

Sta 267: Bldg A Controls Upgrade (9/2/2025 - 11/26/2025)

Station 307

(segment 307 BH)

 

1,202

 

 

1,202

 

1,202

 

1,202

 

Station 315

(segment 315 BH)

 

1,915

 

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

 

 

1,885

 

1,885

 

1,885

 

Station 405 HC Line (segment 299

FH)

 

827

 

 

827

 

827

 

827

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

December 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(12/1 - 12/7)

Week 2

(12/8 - 12/14)

Week 3

(12/15 - 12/21)

Week 4

(12/22 - 12/28)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

585

 

585

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

438

 

438

 

438

 

438

 

Station 9

(segment 109 BH)

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

Station 25

(segment 125 FH)

 

1,101

 

1087

(14)

 

1075

(26)

 

1075

(26)

 

1075

(26)

MLV 26-1 Relocation: Highway 59 Widening (11/11/2025 - 12/10/2025) MLV 26-1 to MLV 27-1: Install Road Casing (12/6/2025 - 1/19/2026) MLV 26-2 Relocation: Highway 59 Widening (12/11/2025 - 1/19/2026)

Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 40 South

(segment 132 FH)

 

1,299

 

910

(389)

 

1,299

 

1,299

 

1,299

MLV 32-2D TO MLV 40-2S: Pig Runs - Maintenance (12/2/2025)

Station 47

(segment 143 FH)

 

1,354

895

(459)

895

(459)

950

(404)

1349

(5)

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-3A to MLV 48-3: Pipe Replacement (11/25/2025 - 12/10/2025)

MLV 53-3BR to MLV 54-3BL: HydroTest (11/19/2025 - 12/16/2025)

Station 63

(segment 163 FH)

 

1,287

 

1,287

 

1,287

 

1,287

 

1,287

 

Station 823

(segment 823 BH)

 

759

 

759

 

759

 

759

 

759

 

Station 834

(segment 834 BH)

 

733

718

(15)

718

(15)

718

(15)

718

(15)

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

Station 847

(segment 847 BH)

 

338

200

(138)

200

(138)

 

338

 

338

MLV 856-1 to MLV 860-1: Pig Runs - Cal / IMU 12/9/25 (12/9/2025)

MLV 856-1 to MLV 860-1: Pig Runs - Cleaning / Gauge 12/4/25 (12/4/2025) MLV 856-1 to MLV 860-1: Pig Runs - MFL-C 12/11/25 (12/11/2025)

 

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

1,632

 

 

 

 

1294

(338)

 

 

 

 

1425

(207)

 

 

 

 

1425

(207)

 

 

 

 

1425

(207)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)

MLV 548

(segment 542 BH)

 

1,771

1735

(36)

1736

(35)

 

1,771

 

1,771

Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/5/2025)

Station 860

(segment 548 BH)

 

1,697

1681

(16)

1681

(16)

1681

(16)

 

1,697

Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025) Sta 550: Unit 3A - Turbocharger Exchange (12/8/2025 - 12/19/2025)

Station 860 North (Segment 860

BH)

 

2,028

 

2000

(28)

 

2000

(28)

 

2000

(28)

 

2000

(28)

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025)

Station 110

(segment 187 BH)

(south thru

Kentucky)

 

 

2,775

 

2600

(175)

 

2600

(175)

 

2645

(130)

 

2645

(130)

Sta 106 Clay City: Upgrade B Building Jacket Water System (11/14/2025 - 12/5/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026) Sta 96: Unit 1D - Compressor Valves (12/1/2025 - 12/12/2025)

Station 114

(segment 114 BH)

 

948

 

948

 

948

 

948

 

948

 

Station 204

(Segment 204 BH)

 

1,895

 

1,895

 

1,895

1722

(173)

 

1,895

MLV 204-2 to MLV 200-2: Pig Runs - EMAT 12/18/25 (M) (12/18/2025) MLV 204-2 to MLV 200-2: Pig Runs - MFL-C 12/16/25 (M) (12/16/2025)

Station 245

(segment 245 FH)

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

1,045

 

1,045

 

1,045

 

1,045

 


 

 

 

-Primary impact restrictions may be necessary

 

TGP - Outage Impact Report

 

-Major impact restrictions may be necessary

 

December 2025 (updated 10/30/25)

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(12/1 - 12/7)

Week 2

(12/8 - 12/14)

Week 3

(12/15 - 12/21)

Week 4

(12/22 - 12/28)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 307

(segment 307 BH)

 

1,202

 

1,202

 

1,202

 

1,202

 

1,202

 

Station 315

(segment 315 BH)

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

Station 405 HC Line (segment 299

FH)

 

827

 

827

 

827

 

827

 

827

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Primary impact restrictions may be necessary

 

 

TGP - Outage Impact Report

 

 

-Major impact restrictions may be necessary

 

January 2026 (updated 10/30/25)

 

 

-Minor impact restrictions may be necessary depending on flow conditions

 

 

 

 

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral

Est Nominal Operating Capacity (Thousand Dth)

Week 1

(12/29 - 1/4)

Week 2

(1/5 - 1/11)

Week 3

(1/12 - 1/18)

Week 4

(1/19 - 1/25)

Week 5

(1/26 - 2/1)

 

Primary Outage(s)

 

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

585

 

585

 

585

 

585

 

585

 

585

 

Station 1

(segment 101 BH)

 

438

 

438

 

438

 

438

 

438

 

438

 

Station 9

(segment 109 BH)

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

1,066

 

Station 25

(segment 125 FH)

 

1,101

 

1075

(26)

 

1075

(26)

 

1075

(26)

 

855

(246)

 

855

(246)

MLV 26-1 to MLV 27-1: Install Road Casing (12/6/2025 - 1/19/2026) MLV 26-2 Relocation: Highway 59 Widening (12/11/2025 - 1/19/2026) MLV 26-3 Relocation: Highway 59 Widening (M) (1/20/2026 - 2/19/2026)

Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)

Station 47

(segment 143 FH)

 

1,354

1349

(5)

 

1,354

 

1,354

 

1,354

 

1,354

MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025)

Station 63

(segment 163 FH)

 

1,287

 

1,287

 

1,287

 

1,287

 

1,287

 

1,287

 

Station 823

(segment 823 BH)

 

759

 

759

 

759

 

759

 

759

 

759

 

Station 834

(segment 834 BH)

 

733

718

(15)

 

733

 

733

 

733

 

733

Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)

 

 

Station 534 South of Pool (segment 530 BH)

 

 

 

 

1,632

 

 

 

1425

(207)

 

 

 

1610

(22)

 

 

 

1610

(22)

 

 

 

1610

(22)

 

 

 

1610

(22)

Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)

Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)

Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)

Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)

Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)

MLV 548

(segment 542 BH)

 

1,771

 

1,771

 

1,771

 

1,771

 

1,771

 

1,771

 

Station 860

(segment 548 BH)

 

1,697

 

1,697

 

1,697

 

1,697

 

1,697

 

1,697

 

Station 860 North (Segment 860

BH)

 

2,028

 

2000

(28)

 

2,028

 

2,028

 

2,028

 

2,028

Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2025)

Station 110

(segment 187 BH)

(south thru

Kentucky)

 

 

2,775

 

2535

(240)

 

2645

(130)

 

2645

(130)

 

2645

(130)

 

2645

(130)

Sta 871: Unit 1A - 3Q Engine Inspection (12/31/2025) Sta 871: Unit 2A - 3Q Engine Inspection (12/31/2025)

Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)

Station 114

(segment 114 BH)

 

948

 

948

 

948

 

948

 

948

 

948

 

Station 204

(Segment 204 BH)

 

1,895

 

1,895

 

1,895

 

1,895

 

1,895

 

1,895

 

Station 245

(segment 245 FH)

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

1,063

 

Station 261 Discharge East (segment 261

FH)

 

1,045

 

1,045

 

1,045

 

1,045

 

1,045

 

1,045

 

Station 307

(segment 307 BH)

 

1,202

 

1,202

 

1,202

 

1,202

 

1,202

 

1,202

 

Station 315

(segment 315 BH)

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

1,915

 

MLV 324

(segment 324 FH)

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

1,885

 

Station 405 HC Line (segment 299

FH)

 

827

 

827

 

827

 

827

 

827

 

827

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.