Tennessee Gas Pipeline Notice 396429

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  TSP CAPACITY OFFERING Notice Type Desc (2):  TSP CAP OFFERING
Notice Eff Date/Time:  10/21/2025 10:00:14AM Notice End Date/Time:  10/28/2025 9:00:00am
Post Date/Time:  10/21/2025 10:00:14 AM Notice ID: 396429
Reqrd Rsp:  1 Rsp Date:  10/21/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RES OF CAP FOR FUTURE EXPANSION
Notice Text:

DATE: OCTOBER 21, 2025                                          TIME:   10:00 AM CST

 

TO: ALL TENNESSEE GAS PIPELINE COMPANY, L.L.C. CUSTOMERS

 

RE: RESERVATION OF CAPACITY FOR FUTURE EXPANSION IN ZONES L and 1

 

Pursuant to Article XXVI, Section 5.8 of the General Terms and Conditions (“GT&C”) of its FERC NGA Gas Tariff, as it may be revised from time to time (“Tariff”), Tennessee Gas Pipeline Company, L.L.C. (“Tennessee”) hereby gives notice that certain capacity as described below will be reserved for use in a future expansion of Tennessee's system.  The project for which the capacity is being reserved (“Project”) will be designed to provide incremental supply from existing and new receipt points in Zone L to existing and new delivery points in Zone L and Zone 1 and is estimated to go in-service as early as April 1,2028 . 

The Project capacity being reserved includes the following:

 

Capacity on Mainline Valve Segments:

 

·         200,000 Dth/d from MLV 820 (HPL Sabine) to MLV 823

·         6,511 Dth/d from MLV 823 to MLV 523

·         27,444 Dth/d from MLV 523 to MLV 534

·         227,444 Dth/d from MLV 534 to MLV 87 (Station 87 – Midwestern)

 

Receipt Meter Capacity:

·         200,000 Dth/d – 412398 (Zone L Jefferson Island)

·         110,105 Dth/d – 412690 (Zone L HPL Sabine)

·         200,000 Dth/d – 412737 (Zone L Cameron IPL DeQuincy Storage)

 

Delivery Meter Capacity:

·         33,570 Dth/d – 420366 (Zone L FGT Carnes)

·         227,444 Dth/d – 420383 (Zone L Kiln)

·         227,444 Dth/d – 420999 (Zone L Zone L Leg 500 Pool)

·         227,444 Dth/d – 420852 (Zone 1 Midwestern SMS)

 

Estimated In-Service Date:

·         April 1, 2028

 

Pursuant to Article XXVI, Section 5.8 of the GT&C of Tennessee's Tariff, Tennessee will make the reserved capacity available for transportation service on a limited-term basis up to the in-service date of the Project.  For any such limited-term agreements, Tennessee reserves the right to limit any extension rights provided commensurate with the proposed in-service date of the Project.

 

For further information, please contact:

 

Andoni Vossos

(713) 420-2054

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  TSP CAPACITY OFFERING Notice Type Desc (2):  TSP CAP OFFERING
Notice Eff Date/Time:  10/21/2025 10:00:14AM Notice End Date/Time:  10/28/2025 9:00:00am
Post Date/Time:  10/21/2025 10:00:14 AM Notice ID: 396429
Reqrd Rsp:  1 Rsp Date:  10/21/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RES OF CAP FOR FUTURE EXPANSION
Notice Text:

DATE: OCTOBER 21, 2025                                          TIME:   10:00 AM CST

 

TO: ALL TENNESSEE GAS PIPELINE COMPANY, L.L.C. CUSTOMERS

 

RE: RESERVATION OF CAPACITY FOR FUTURE EXPANSION IN ZONES L and 1

 

Pursuant to Article XXVI, Section 5.8 of the General Terms and Conditions (“GT&C”) of its FERC NGA Gas Tariff, as it may be revised from time to time (“Tariff”), Tennessee Gas Pipeline Company, L.L.C. (“Tennessee”) hereby gives notice that certain capacity as described below will be reserved for use in a future expansion of Tennessee's system.  The project for which the capacity is being reserved (“Project”) will be designed to provide incremental supply from existing and new receipt points in Zone L to existing and new delivery points in Zone L and Zone 1 and is estimated to go in-service as early as April 1,2028 . 

The Project capacity being reserved includes the following:

 

Capacity on Mainline Valve Segments:

 

·         200,000 Dth/d from MLV 820 (HPL Sabine) to MLV 823

·         6,511 Dth/d from MLV 823 to MLV 523

·         27,444 Dth/d from MLV 523 to MLV 534

·         227,444 Dth/d from MLV 534 to MLV 87 (Station 87 – Midwestern)

 

Receipt Meter Capacity:

·         200,000 Dth/d – 412398 (Zone L Jefferson Island)

·         110,105 Dth/d – 412690 (Zone L HPL Sabine)

·         200,000 Dth/d – 412737 (Zone L Cameron IPL DeQuincy Storage)

 

Delivery Meter Capacity:

·         33,570 Dth/d – 420366 (Zone L FGT Carnes)

·         227,444 Dth/d – 420383 (Zone L Kiln)

·         227,444 Dth/d – 420999 (Zone L Zone L Leg 500 Pool)

·         227,444 Dth/d – 420852 (Zone 1 Midwestern SMS)

 

Estimated In-Service Date:

·         April 1, 2028

 

Pursuant to Article XXVI, Section 5.8 of the GT&C of Tennessee's Tariff, Tennessee will make the reserved capacity available for transportation service on a limited-term basis up to the in-service date of the Project.  For any such limited-term agreements, Tennessee reserves the right to limit any extension rights provided commensurate with the proposed in-service date of the Project.

 

For further information, please contact:

 

Andoni Vossos

(713) 420-2054