TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  10/20/2025 2:47:14PM Notice End Date/Time:  10/21/2025 9:00:00am
Post Date/Time:  10/20/2025 2:47:14 PM Notice ID: 396412
Reqrd Rsp:  1 Rsp Date:  10/20/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 10-21-2025 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Tuesday, October 21, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING AREAS SOUTH OF STA 1 AND THE 500 LINE SEGMENTS 524, 527, 529, 530, 534, 539, 542, 548, 860) FOR UNDER-TAKES OR OVER-DELIVERIES FOR ALL BALANCING PARTIES

 

METER RESTRICTIONS

·         TGP/KMTEJAS King Ranch Exch #2 Roll Receipt Meter (Pin 55152) - through approx 30% of SIPsp due to operational concerns; 59,630 Dths

·         WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through approx 56% of SA due to nominations in excess of operational capacity; 129,173 Dths

·         KMTEJAS/TGP Jackson (Ganado) Delivery Meter (Pin 49803) - through approx 81% of SOP due to operational concerns; 48,326 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 44% of SIPss due to nominations in excess of operational capacity; 81,721 Dths

SEGMENT RESTRICTIONS

·         STA 542 (Segment 539 BH) - through SIPsp due to scheduled maintenance and nominations in excess of operational capacity

·         STA 1 (Segment 101 BH) - through approx 60% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 56,189 Dths

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 67,149 Dths

·         STA 823 (Segment 823 BH) - through approx 45% of SOP due to nominations in excess of operational capacity; 4,413 Dths

·         STA 834 (Segment 834 BH) - through 100% of SA due to operational concerns; 4,634 Dths

·         STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 9,972 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 1,500 Dths

·         STA 219 South (Segment 217 BH) - through 100% of SOP due to operational concerns; 25,041 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 595,006 Dths

·         MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 615,369 Dths

·         STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 652,987 Dths

·         STA 317 (Segment 317 BH) - through approx 54% of SOP due to nominations in excess of operational capacity; 121,820 Dths

·         STA 321 (Segment 321 FH) - through approx 41% of SOP due to nominations in excess of operational capacity; 415,026 Dths

·         MLV 330 (Segment 324 FH) - through approx 18% of SOP due to nominations in excess of operational capacity; 88,110 Dths

·         Z5hc North (Segment 299 FH) - through approx 81% of SOP due to nominations in excess of operational capacity; 696,987 Dths

·         STA 245 (Segment 245 FH) - through approx 80% of SOP due to nominations in excess of operational capacity; 868,602 Dths

·         STA 249 (Segment 249 FH) - through approx 77% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 521,569 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 238,317 Dths

LINEPACK RESTRICTIONS

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service

·         Paybacks will be evaluated at each cycle and scheduled only if operationally feasible

 

 

 

 

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:

·         Northern MA (460018) storage field

·         Portland MA (460025) storage field

·         Portland PA (460020) storage field

·         Bear Creek PA (460017) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

·         Northern MA (460018) storage field (IS-MA)

·         Bear Creek PA (460017) storage field (IS-PA)

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  10/20/2025 2:47:14PM Notice End Date/Time:  10/21/2025 9:00:00am
Post Date/Time:  10/20/2025 2:47:14 PM Notice ID: 396412
Reqrd Rsp:  1 Rsp Date:  10/20/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 10-21-2025 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Tuesday, October 21, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING AREAS SOUTH OF STA 1 AND THE 500 LINE SEGMENTS 524, 527, 529, 530, 534, 539, 542, 548, 860) FOR UNDER-TAKES OR OVER-DELIVERIES FOR ALL BALANCING PARTIES

 

METER RESTRICTIONS

·         TGP/KMTEJAS King Ranch Exch #2 Roll Receipt Meter (Pin 55152) - through approx 30% of SIPsp due to operational concerns; 59,630 Dths

·         WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through approx 56% of SA due to nominations in excess of operational capacity; 129,173 Dths

·         KMTEJAS/TGP Jackson (Ganado) Delivery Meter (Pin 49803) - through approx 81% of SOP due to operational concerns; 48,326 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 44% of SIPss due to nominations in excess of operational capacity; 81,721 Dths

SEGMENT RESTRICTIONS

·         STA 542 (Segment 539 BH) - through SIPsp due to scheduled maintenance and nominations in excess of operational capacity

·         STA 1 (Segment 101 BH) - through approx 60% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 56,189 Dths

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 67,149 Dths

·         STA 823 (Segment 823 BH) - through approx 45% of SOP due to nominations in excess of operational capacity; 4,413 Dths

·         STA 834 (Segment 834 BH) - through 100% of SA due to operational concerns; 4,634 Dths

·         STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 9,972 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 1,500 Dths

·         STA 219 South (Segment 217 BH) - through 100% of SOP due to operational concerns; 25,041 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 595,006 Dths

·         MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 615,369 Dths

·         STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 652,987 Dths

·         STA 317 (Segment 317 BH) - through approx 54% of SOP due to nominations in excess of operational capacity; 121,820 Dths

·         STA 321 (Segment 321 FH) - through approx 41% of SOP due to nominations in excess of operational capacity; 415,026 Dths

·         MLV 330 (Segment 324 FH) - through approx 18% of SOP due to nominations in excess of operational capacity; 88,110 Dths

·         Z5hc North (Segment 299 FH) - through approx 81% of SOP due to nominations in excess of operational capacity; 696,987 Dths

·         STA 245 (Segment 245 FH) - through approx 80% of SOP due to nominations in excess of operational capacity; 868,602 Dths

·         STA 249 (Segment 249 FH) - through approx 77% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 521,569 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 238,317 Dths

LINEPACK RESTRICTIONS

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service

·         Paybacks will be evaluated at each cycle and scheduled only if operationally feasible

 

 

 

 

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:

·         Northern MA (460018) storage field

·         Portland MA (460025) storage field

·         Portland PA (460020) storage field

·         Bear Creek PA (460017) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

·         Northern MA (460018) storage field (IS-MA)

·         Bear Creek PA (460017) storage field (IS-PA)

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.