Tennessee Gas Pipeline Notice 395726

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/03/2025 7:46:26PM Notice End Date/Time:  09/04/2025 9:00:00am
Post Date/Time:  9/3/2025 7:46:26 PM Notice ID: 395726
Reqrd Rsp:  1 Rsp Date:  09/03/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 09-03-2025 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of Wednesday, September 03, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

SEGMENT RESTRICTIONS

·         MLV 548 (Segment 542 BH) - through SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 114 East (Segment 114 BH) - through PIP increases due to force majeure at STA 119 Unit 1A

·         STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 245 (Segment 245 FH) - through approx 63% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 69,058 Dths

LINEPACK RESTRICTIONS

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service

·         Paybacks will be evaluated at each cycle and scheduled only if operationally feasible

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:

·         Northern MA (460018) storage field

·         Portland MA (460025) storage field

·         Portland PA (460020) storage field

·         Bear Creek PA (460017) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

·         Northern MA (460018) storage field (IS-MA)

·         Bear Creek PA (460017) storage field (IS-PA)

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/03/2025 7:46:26PM Notice End Date/Time:  09/04/2025 9:00:00am
Post Date/Time:  9/3/2025 7:46:26 PM Notice ID: 395726
Reqrd Rsp:  1 Rsp Date:  09/03/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 09-03-2025 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of Wednesday, September 03, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

SEGMENT RESTRICTIONS

·         MLV 548 (Segment 542 BH) - through SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 114 East (Segment 114 BH) - through PIP increases due to force majeure at STA 119 Unit 1A

·         STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity

·         STA 245 (Segment 245 FH) - through approx 63% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 69,058 Dths

LINEPACK RESTRICTIONS

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service

·         Paybacks will be evaluated at each cycle and scheduled only if operationally feasible

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:

·         Northern MA (460018) storage field

·         Portland MA (460025) storage field

·         Portland PA (460020) storage field

·         Bear Creek PA (460017) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

·         Northern MA (460018) storage field (IS-MA)

·         Bear Creek PA (460017) storage field (IS-PA)

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.