Tennessee Gas Pipeline Notice 394460

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/30/2025 3:20:53PM Notice End Date/Time:  05/01/2025 9:00:00am
Post Date/Time:  4/30/2025 3:20:53 PM Notice ID: 394460
Reqrd Rsp:  1 Rsp Date:  04/30/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 05-01-2025 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Thursday, May 01, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING ALL AREAS SOUTH OF STA 1 AND THE 500 LINE ONLY) FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPps due to imbalance management quantity exceeded; 1,000 Dths

·         TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SIPss due to operational concerns; 23,253 Dths

·         TGP/SNG Bear Creek Injection Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 2,000 Dths

·         Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps due to operational concerns; 55,000 Dths

·         TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths

·         TGP/SNG Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through 100% of SIPps due to operational concerns; 30,151 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 81% of SIPss due to nominations in excess of operational capacity; 95,274 Dths

SEGMENT RESTRICTIONS

·         STA 860 (Segment 860 BH) - through 100% of SOP due to force majeure at STA 860; 2,060 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 15,279 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP due to nominations in excess of operational capacity; 438,714 Dths

·         MLV 314 East (Segment 314 BH) - through approx 92% of SOP due to nominations in excess of operational capacity; 525,211 Dths

·         STA 315 (Segment 315 BH) - through approx 84% of SOP due to nominations in excess of operational capacity; 632,804 Dths

·         STA 321 (Segment 321 FH) - through approx 64% of SOP due to nominations in excess of operational capacity due to an emergent repair at STA 321 UNIT 5B; 648,484 Dths

·         MLV 330 (Segment 324 FH) - through approx 35% of SOP due to nominations in excess of operational capacity; 162,379 Dths

·         Z5 HC North (Segment 299 FH) - through approx 78% of SOP due to nominations in excess of operational capacity; 647,708 Dths

·         STA 245 (Segment 245 FH) - through approx 77% of SOP due to nominations in excess of operational capacity; 742,985 Dths

·         STA 249 (Segment 249 FH) - through approx 54% of SOP due to nominations in excess of operational capacity; 373,660 Dths

·         MLV 256 East (Segment 256 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 126,435 Dths

·         MLV 273 (Segment 284 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 406,044 Dths

LINEPACK RESTRICTIONS

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service

·         Paybacks will be evaluated at each cycle and scheduled only if operationally feasible

 

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:

·         Northern MA (460018) storage field

·         Portland MA (460025) storage field

·         Portland PA (460020) storage field

·         Bear Creek PA (460017) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

·         Northern MA (460018) storage field (IS-MA)

·         Bear Creek PA (460017) storage field (IS-PA)

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/30/2025 3:20:53PM Notice End Date/Time:  05/01/2025 9:00:00am
Post Date/Time:  4/30/2025 3:20:53 PM Notice ID: 394460
Reqrd Rsp:  1 Rsp Date:  04/30/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 05-01-2025 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Thursday, May 01, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING ALL AREAS SOUTH OF STA 1 AND THE 500 LINE ONLY) FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPps due to imbalance management quantity exceeded; 1,000 Dths

·         TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SIPss due to operational concerns; 23,253 Dths

·         TGP/SNG Bear Creek Injection Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 2,000 Dths

·         Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps due to operational concerns; 55,000 Dths

·         TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths

·         TGP/SNG Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through 100% of SIPps due to operational concerns; 30,151 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 81% of SIPss due to nominations in excess of operational capacity; 95,274 Dths

SEGMENT RESTRICTIONS

·         STA 860 (Segment 860 BH) - through 100% of SOP due to force majeure at STA 860; 2,060 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 15,279 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP due to nominations in excess of operational capacity; 438,714 Dths

·         MLV 314 East (Segment 314 BH) - through approx 92% of SOP due to nominations in excess of operational capacity; 525,211 Dths

·         STA 315 (Segment 315 BH) - through approx 84% of SOP due to nominations in excess of operational capacity; 632,804 Dths

·         STA 321 (Segment 321 FH) - through approx 64% of SOP due to nominations in excess of operational capacity due to an emergent repair at STA 321 UNIT 5B; 648,484 Dths

·         MLV 330 (Segment 324 FH) - through approx 35% of SOP due to nominations in excess of operational capacity; 162,379 Dths

·         Z5 HC North (Segment 299 FH) - through approx 78% of SOP due to nominations in excess of operational capacity; 647,708 Dths

·         STA 245 (Segment 245 FH) - through approx 77% of SOP due to nominations in excess of operational capacity; 742,985 Dths

·         STA 249 (Segment 249 FH) - through approx 54% of SOP due to nominations in excess of operational capacity; 373,660 Dths

·         MLV 256 East (Segment 256 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 126,435 Dths

·         MLV 273 (Segment 284 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 406,044 Dths

LINEPACK RESTRICTIONS

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service

·         No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service

·         Paybacks will be evaluated at each cycle and scheduled only if operationally feasible

 

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:

·         Northern MA (460018) storage field

·         Portland MA (460025) storage field

·         Portland PA (460020) storage field

·         Bear Creek PA (460017) storage field

·         No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:

·         Northern MA (460018) storage field (IS-MA)

·         Bear Creek PA (460017) storage field (IS-PA)

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.